$31.85Avg low bid / LF
$35.07Avg of all bids
$36.05Avg engineer's estimate
198Jobs · 86,859.48 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 26 | 8,367 | $36.27 | $42.63 |
| 2020 | 57 | 29,063.66 | $28.95 | $33.28 |
| 2019 | 46 | 20,536 | $34.33 | $36.85 |
| 2018 | 56 | 22,693.42 | $33.30 | $35.48 |
| 2017 | 13 | 6,199.4 | $25.96 | $30.51 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 18, 2021 | 210347 | DelawareDivision 8 | 61 LF | $35.00 | C-GAWF CONSTRUCTION, INC. |
| Sep 16, 2021 | 210251 | Cirb-230c(045)rb | 335 LF | $39.90 | K & R BUILDERS, INC. |
| Sep 16, 2021 | 210267 | PayneDivision 4 | 188 LF | $50.00 | H & H BRIDGE COMPANY |
| Sep 16, 2021 | 210251 | Cirb-230c(045)rb | 223 LF | $42.00 | K & R BUILDERS, INC. |
| Jul 15, 2021 | 210180 | MuskogeeDivision 1 | 124 LF | $34.00 | H & H BRIDGE COMPANY |
| Jul 15, 2021 | 210200 | BeckhamDivision 5 | 200 LF | $40.00 | SEWELL BROS., INC. |
| Jul 15, 2021 | 210201 | BlaineDivision 5 | 194 LF | $38.00 | SEWELL BROS., INC. |
| Jul 15, 2021 | 210209 | KayDivision 4 | 80 LF | $45.00 | H & H BRIDGE COMPANY |
| Jun 17, 2021 | 210185 | NowataDivision 8 | 184 LF | $43.52 | Frontier Bridge, Inc. |
| Jun 17, 2021 | 210171 | DeweyDivision 5 | 322 LF | $38.30 | Frontier Bridge, Inc. |
| Jun 17, 2021 | 210176 | Leflore, Mccurtain | 80 LF | $62.00 | HUB Construction, Inc. |
| May 20, 2021 | 210140 | McclainDivision 3 | 262 LF | $37.66 | Treas Construction Inc |
| May 20, 2021 | 200338 | BeckhamDivision 5 | 747 LF | $40.00 | OBC, INC. |
| May 20, 2021 | 210143 | MurrayDivision 7 | 450 LF | $45.10 | OVERLAND CORPORATION |
| May 20, 2021 | 210158 | TillmanDivision 5 | 210 LF | $32.00 | SEWELL BROS., INC. |
| May 20, 2021 | 210129 | BryanDivision 2 | 1,839 LF | $32.00 | L & N BRIDGE, LLC |
| Mar 18, 2021 | 200030 | RogersDivision 8 | 162 LF | $35.00 | CONCRETE SERVICES CORPORATION |
| Mar 18, 2021 | 210078 | KayDivision 4 | 158 LF | $39.00 | RRY SERVICES LLC |
| Mar 18, 2021 | 210097 | KayDivision 4 | 278 LF | $34.00 | WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES |
| Mar 18, 2021 | 210097 | KayDivision 4 | 284 LF | $34.00 | WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES |
| Mar 18, 2021 | 210060 | OttawaDivision 8 | 715 LF | $32.28 | Treas Construction Inc |
| Feb 18, 2021 | 210070 | WoodwardDivision 6 | 168 LF | $35.16 | BRIDGECO CONTRACTORS, INC. |
| Feb 18, 2021 | 210046 | ComancheDivision 7 | 100 LF | $41.58 | K & R BUILDERS, INC. |
| Feb 18, 2021 | 210048 | CraigDivision 8 | 60 LF | $55.00 | CONCRETE SERVICES CORPORATION |
| Feb 18, 2021 | 210055 | MurrayDivision 7 | 124 LF | $40.00 | HUB Construction, Inc. |
| Feb 18, 2021 | 210061 | PittsburgDivision 2 | 182 LF | $32.72 | BRIDGECO CONTRACTORS, INC. |
| Jan 21, 2021 | 210017 | GradyDivision 7 | 201 LF | $28.87 | Treas Construction Inc |
| Jan 21, 2021 | 210016 | GradyDivision 7 | 436 LF | $25.20 | K & R BUILDERS, INC. |
| Nov 19, 2020 | 200344 | CaddoDivision 7 | 1,134 LF | $25.20 | K & R BUILDERS, INC. |
| Nov 19, 2020 | 200348 | CusterDivision 5 | 224 LF | $27.43 | Frontier Bridge, Inc. |
| Nov 19, 2020 | 200355 | RogersDivision 8 | 401 LF | $31.90 | EMERY SAPP & SONS, INC. |
| Nov 19, 2020 | 200156 | MajorDivision 6 | 116 LF | $28.00 | K & R BUILDERS, INC. |
| Nov 19, 2020 | 200359 | MccurtainDivision 2 | 214 LF | $29.03 | Frontier Bridge, Inc. |
| Oct 15, 2020 | 200329 | StephensDivision 7 | 2,359 LF | $19.65 | BRIDGECO CONTRACTORS, INC. |
| Oct 15, 2020 | 200317 | MccurtainDivision 2 | 333 LF | $40.00 | HUB Construction, Inc. |
| Oct 15, 2020 | 200317 | MccurtainDivision 2 | 70 LF | $40.00 | HUB Construction, Inc. |
| Oct 15, 2020 | 200322 | OsageDivision 8 | 920 LF | $26.81 | BRIDGECO CONTRACTORS, INC. |
| Oct 15, 2020 | 200323 | OsageDivision 8 | 488 LF | $31.71 | BRIDGECO CONTRACTORS, INC. |
| Oct 15, 2020 | 200304 | BlaineDivision 5 | 186 LF | $26.60 | K & R BUILDERS, INC. |
| Oct 15, 2020 | 200329 | StephensDivision 7 | 2,555 LF | $19.65 | BRIDGECO CONTRACTORS, INC. |
| Oct 15, 2020 | 200314 | KingfisherDivision 4 | 206 LF | $24.50 | K & R BUILDERS, INC. |
| Sep 17, 2020 | 200284 | MajorDivision 6 | 236 LF | $25.96 | BRIDGECO CONTRACTORS, INC. |
| Sep 17, 2020 | 200291 | PittsburgDivision 2 | 384 LF | $28.43 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Sep 17, 2020 | 200291 | PittsburgDivision 2 | 414 LF | $29.30 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Sep 17, 2020 | 200278 | DeweyDivision 5 | 108 LF | $34.60 | HASKELL LEMON CONSTRUCTION CO. |
| Sep 17, 2020 | 200281 | KiowaDivision 5 | 152 LF | $30.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200262 | BeckhamDivision 5 | 100 LF | $35.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200264 | Leflore | 130 LF | $30.42 | HUB Construction, Inc. |
| Aug 20, 2020 | 200239 | WoodsDivision 6 | 278 LF | $25.20 | K & R BUILDERS, INC. |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 634 LF | $28.28 | SHERWOOD CONSTRUCTION CO., INC. |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 1,585 LF | $28.28 | SHERWOOD CONSTRUCTION CO., INC. |
| Aug 20, 2020 | 200225 | GradyDivision 7 | 1,197 LF | $25.00 | SEWELL BROS., INC. |
| Jul 23, 2020 | 200108 | Love, Marshall | 1,590 LF | $32.00 | OVERLAND CORPORATION |
| Jul 23, 2020 | 200250 | GarvinDivision 3 | 208 LF | $32.25 | Frontier Bridge, Inc. |
| Jun 18, 2020 | 200237 | StephensDivision 7 | 912 LF | $25.00 | SEWELL BROS., INC. |
| Jun 18, 2020 | 200221 | AtokaDivision 2 | 60 LF | $60.00 | HUB Construction, Inc. |
| Jun 18, 2020 | 200222 | CanadianDivision 4 | 324 LF | $24.45 | SHERWOOD CONSTRUCTION CO., INC. |
| Jun 18, 2020 | 200229 | LincolnDivision 3 | 211 LF | $33.00 | L & N BRIDGE, LLC |
| May 14, 2020 | 200190 | Cirb-210d(071)rb | 546 LF | $33.29 | Treas Construction Inc |
| May 14, 2020 | 190377 | WashingtonDivision 8 | 74 LF | $60.00 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| May 14, 2020 | 200192 | ComancheDivision 7 | 715 LF | $30.17 | Frontier Bridge, Inc. |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 226 LF | $30.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 190347 | DelawareDivision 8 | 70 LF | $45.00 | RRY SERVICES LLC |
| May 14, 2020 | 200202 | MuskogeeDivision 1 | 106 LF | $30.39 | Treas Construction Inc |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 214 LF | $30.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 200212 | StephensDivision 7 | 184 LF | $30.00 | SEWELL BROS., INC. |
| May 14, 2020 | 200214 | Stp-266d(065)ci | 60 LF | $97.35 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| Apr 16, 2020 | 200185 | OklahomaDivision 4 | 132 LF | $33.75 | Frontier Bridge, Inc. |
| Apr 16, 2020 | 200149 | DelawareDivision 8 | 60 LF | $46.10 | K & R BUILDERS, INC. |
| Apr 16, 2020 | 200216 | BlaineDivision 5 | 729 LF | $38.50 | K & R BUILDERS, INC. |
| Apr 16, 2020 | 200153 | Jefferson | 78 LF | $46.90 | K & R BUILDERS, INC. |
| Apr 16, 2020 | 200153 | Jefferson | 202 LF | $29.40 | K & R BUILDERS, INC. |
| Apr 16, 2020 | 200155 | LincolnDivision 3 | 176 LF | $32.52 | BRIDGECO CONTRACTORS, INC. |
| Apr 16, 2020 | 200138 | BeaverDivision 6 | 224 LF | $33.60 | K & R BUILDERS, INC. |
| Apr 16, 2020 | 200065 | HughesDivision 3 | 984 LF | $26.94 | Treas Construction Inc |
| Mar 19, 2020 | 200102 | GrantDivision 4 | 170 LF | $25.00 | H & H BRIDGE COMPANY |
| Mar 19, 2020 | 200032 | SeminoleDivision 3 | 170.66 LF | $45.00 | RRY SERVICES LLC |
| Mar 19, 2020 | 200113 | OkfuskeeDivision 3 | 180 LF | $25.00 | H & H BRIDGE COMPANY |
| Feb 20, 2020 | 190255 | Pontotoc | 680 LF | $29.15 | BRIDGECO CONTRACTORS, INC. |
| Feb 20, 2020 | 200069 | LincolnDivision 3 | 200 LF | $22.00 | Cowboy Contracting, Inc. |
| Feb 20, 2020 | 200047 | AtokaDivision 2 | 276 LF | $36.57 | C3 Construction, Inc. |
| Feb 20, 2020 | 200050 | BeckhamDivision 5 | 420 LF | $56.19 | Frontier Bridge, Inc. |
| Jan 16, 2020 | 200039 | WoodsDivision 6 | 188 LF | $40.00 | RRY SERVICES LLC |
| Jan 16, 2020 | 190317 | KayDivision 4 | 228 LF | $29.75 | BRIDGECO CONTRACTORS, INC. |
| Jan 16, 2020 | 200018 | McintoshDivision 1 | 880 LF | $26.00 | L & N BRIDGE, LLC |
| Jan 16, 2020 | 200044 | Stp-257b(038)pm | 302 LF | $28.33 | SHERWOOD CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200044 | Stp-257b(038)pm | 198 LF | $28.33 | SHERWOOD CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200035 | TillmanDivision 5 | 228 LF | $32.20 | K & R BUILDERS, INC. |
| Jan 16, 2020 | 190352 | GarvinDivision 3 | 150 LF | $37.00 | Silver Star Construction Company, Inc. |
| Jan 16, 2020 | 200003 | BlaineDivision 5 | 720 LF | $35.00 | K & R BUILDERS, INC. |
| Jan 16, 2020 | 190207 | CarterDivision 7 | 284 LF | $33.60 | K & R BUILDERS, INC. |
| Jan 16, 2020 | 200035 | TillmanDivision 5 | 150 LF | $35.00 | K & R BUILDERS, INC. |
| Jan 16, 2020 | 190352 | GarvinDivision 3 | 150 LF | $37.00 | Silver Star Construction Company, Inc. |
| Jan 16, 2020 | 200004 | BlaineDivision 5 | 980 LF | $35.00 | K & R BUILDERS, INC. |
| Nov 14, 2019 | 190354 | GreerDivision 5 | 176 LF | $33.72 | Frontier Bridge, Inc. |
| Nov 14, 2019 | 190386 | CoalDivision 3 | 94 LF | $34.40 | BRIDGECO CONTRACTORS, INC. |
| Nov 14, 2019 | 190375 | StephensDivision 7 | 194 LF | $26.19 | Treas Construction Inc |
| Nov 14, 2019 | 190354 | GreerDivision 5 | 600 LF | $37.99 | Frontier Bridge, Inc. |
| Nov 14, 2019 | 190387 | LincolnDivision 3 | 136 LF | $31.25 | BRIDGECO CONTRACTORS, INC. |
| Nov 14, 2019 | 190340 | BlaineDivision 5 | 1,111 LF | $22.31 | BRIDGECO CONTRACTORS, INC. |
| Nov 14, 2019 | 190355 | JacksonDivision 5 | 188 LF | $35.00 | SEWELL BROS., INC. |
| Nov 14, 2019 | 190378 | WashitaDivision 5 | 80 LF | $35.00 | SEWELL BROS., INC. |
| Nov 14, 2019 | 190309 | WashingtonDivision 8 | 160 LF | $40.00 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| Nov 14, 2019 | 190361 | KiowaDivision 5 | 90 LF | $35.00 | SEWELL BROS., INC. |
| Nov 14, 2019 | 190379 | Nhpp-017n(256)pm | 210 LF | $36.95 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 14, 2019 | 190109 | CanadianDivision 4 | 258 LF | $40.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Nov 14, 2019 | 190369 | PittsburgDivision 2 | 142 LF | $41.93 | C3 Construction, Inc. |
| Nov 14, 2019 | 190379 | Nhpp-017n(256)pm | 219 LF | $34.40 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 14, 2019 | 190375 | StephensDivision 7 | 188 LF | $26.19 | Treas Construction Inc |
| Oct 17, 2019 | 180304 | SeminoleDivision 3 | 734 LF | $32.00 | OVERLAND CORPORATION |
| Oct 17, 2019 | 190312 | CanadianDivision 4 | 343 LF | $27.82 | SHERWOOD CONSTRUCTION CO., INC. |
| Oct 17, 2019 | 180304 | SeminoleDivision 3 | 440 LF | $33.00 | OVERLAND CORPORATION |
| Oct 17, 2019 | 190314 | GradyDivision 7 | 1,288 LF | $36.82 | Central Bridge Company |
| Aug 22, 2019 | 190257 | SequoyahDivision 1 | 238 LF | $52.00 | JOB CONSTRUCTION CO., INC. |
| Aug 22, 2019 | 190244 | CusterDivision 5 | 364 LF | $35.00 | SEWELL BROS., INC. |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 718 LF | $35.00 | DUIT CONSTRUCTION COMPANY, INC. |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 910 LF | $35.00 | DUIT CONSTRUCTION COMPANY, INC. |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 1,044 LF | $35.00 | DUIT CONSTRUCTION COMPANY, INC. |
| Jun 20, 2019 | 190149 | CusterDivision 5 | 210 LF | $31.12 | Treas Construction Inc |
| Jun 20, 2019 | 180107 | OsageDivision 8 | 208 LF | $35.00 | RRY SERVICES LLC |
| Jun 20, 2019 | 190189 | AtokaDivision 2 | 108 LF | $45.00 | Built Right Construction, LLC |
| Jun 20, 2019 | 180343 | BeckhamDivision 5 | 590 LF | $34.65 | Frontier Bridge, Inc. |
| Jun 20, 2019 | 190200 | NowataDivision 8 | 130 LF | $27.00 | H & H BRIDGE COMPANY |
| Jun 20, 2019 | 190016 | McintoshDivision 1 | 1,032 LF | $32.00 | OBC, INC. |
| Jun 20, 2019 | 190016 | McintoshDivision 1 | 995 LF | $32.00 | OBC, INC. |
| Jun 20, 2019 | 190119 | MuskogeeDivision 1 | 142 LF | $30.00 | H & H BRIDGE COMPANY |
| May 16, 2019 | 190179 | McclainDivision 3 | 270 LF | $29.71 | BRIDGECO CONTRACTORS, INC. |
| May 16, 2019 | 190017 | NowataDivision 8 | 203 LF | $40.00 | H & H BRIDGE COMPANY |
| May 16, 2019 | 190130 | Stp-259b(034)ss | 352 LF | $45.00 | Bridges, Inc. DBA Scudder Bridge Co. |
| May 16, 2019 | 190181 | MarshallDivision 2 | 200 LF | $37.00 | HUB Construction, Inc. |
| May 16, 2019 | 190027 | WashingtonDivision 8 | 88 LF | $38.00 | BECCO CONTRACTORS, INC. |
| May 16, 2019 | 190013 | McclainDivision 3 | 110 LF | $39.80 | Silver Star Construction Company, Inc. |
| May 16, 2019 | 180356 | JacksonDivision 5 | 146 LF | $30.00 | SEWELL BROS., INC. |
| May 16, 2019 | 180351 | Cotton | 1,070 LF | $30.00 | SEWELL BROS., INC. |
| May 16, 2019 | 190173 | CanadianDivision 4 | 276 LF | $30.00 | SEWELL BROS., INC. |
| May 16, 2019 | 180351 | Cotton | 760 LF | $30.00 | SEWELL BROS., INC. |
| Apr 18, 2019 | 190161 | RogersDivision 8 | 819 LF | $35.00 | BECCO CONTRACTORS, INC. |
| Apr 18, 2019 | 190161 | RogersDivision 8 | 819 LF | $35.00 | BECCO CONTRACTORS, INC. |
| Apr 18, 2019 | 190167 | StephensDivision 7 | 435 LF | $45.00 | RRY SERVICES LLC |
| Mar 14, 2019 | 190003 | BeaverDivision 6 | 234 LF | $56.00 | Bridges, Inc. DBA Scudder Bridge Co. |
| Mar 14, 2019 | 190140 | MurrayDivision 7 | 202 LF | $32.23 | BRIDGECO CONTRACTORS, INC. |
| Feb 14, 2019 | 190066 | AtokaDivision 2 | 78 LF | $37.89 | C3 Construction, Inc. |
| Feb 14, 2019 | 190090 | PittsburgDivision 2 | 96 LF | $40.99 | HUB Construction, Inc. |
| Feb 14, 2019 | 190100 | Stp-205b(076)pm | 206 LF | $40.36 | Frontier Bridge, Inc. |
| Feb 14, 2019 | 190015 | MccurtainDivision 2 | 218 LF | $28.00 | L & N BRIDGE, LLC |
| Feb 14, 2019 | 190100 | Stp-205b(076)pm | 124 LF | $44.54 | Frontier Bridge, Inc. |
| Jan 17, 2019 | 190039 | CusterDivision 5 | 92 LF | $30.00 | SEWELL BROS., INC. |
| Jan 17, 2019 | 180358 | Stp-242c(058)ss | 186 LF | $42.00 | RRY SERVICES LLC |
| Jan 17, 2019 | 190059 | SequoyahDivision 1 | 98 LF | $47.25 | T. McDonald Construction, Inc. |
| Jan 17, 2019 | 190064 | Major, Woodward | 114 LF | $42.60 | THE CUMMINS CONSTRUCTION CO., INC. |