Bid tab 200030

Let Mar 18, 2021 · Division 8 · Rogers Sign up free

‹ Mar 2021 results

BRIDGE AND APPROACHES COUNTY ROAD (E0590): OVER SH-88 AND THE UNION PACIFIC RAILROAD, 9.8 MILES WEST OF THE US -69 JUNCTION NEAR INOLA. PROJECT LENGTH = 0.380 MILE

Let date
Thursday, March 18, 2021
Contract
200030
J/P numbers
29400(04)
District
Division 8
County
Rogers
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (E0590): OVER SH-88 AND THE UNION PACIFIC RAILROAD, 9.8 MILES WEST OF THE US -69 JUNCTION NEAR INOLA. PROJECT LENGTH = 0.380 MILE
Project number
CIRB-266D(061)RB

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$3,476,291
1 CONCRETE SERVICES CORPORATION Low bidder $2,826,236 -18.7%
2 L & N BRIDGE, LLC $3,342,988 -3.8% +18.3%
4 OBC, INC. $3,535,389 +1.7% +25.1%
5 HASKELL LEMON CONSTRUCTION CO. $3,599,397 +3.5% +27.4%
6 MANHATTAN ROAD & BRIDGE COMPANY, LLC $3,697,850 +6.4% +30.8%
7 RRY SERVICES LLC $4,302,320 +23.8% +52.2%
8 BECCO CONTRACTORS, INC. $4,357,000 +25.3% +54.2%

Bid tab: unit prices 69 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 CONCRETE SERVIC…#2 L & N BRIDGE, L…#4 OBC, INC.#5 HASKELL LEMON C…#6 MANHATTAN ROAD …#7 RRY SERVICES LLC#8 BECCO CONTRACTO…
10201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $20,000.00 $7,100.00 $10,000.00 $85,000.00 $32,500.00 $20,000.00 $55,000.00
20202(A) 0183 UNCLASSIFIED EXCAVATION6,096CY $9.00 $3.00 $8.79 $5.00 $9.30 $9.00 $9.50 $22.00
30202(D) 0184 UNCLASSIFIED BORROW22,535CY $12.00 $6.00 $8.74 $9.00 $9.25 $13.00 $12.25 $25.00
40205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $15,000.00 $10,000.00 $10,250.00 $20,000.00 $45,000.00 $5,000.00 $15,000.00 $15,000.00
50221(C) 2801 TEMPORARY SILT FENCE4,204LF $2.25 $2.67 $1.99 $2.12 $2.10 $2.00 $1.99 $2.00
60221(F) 0100 TEMPORARY SILT DIKE36LF $15.00 $20.00 $18.95 $20.18 $20.00 $16.00 $20.00 $20.00
70221(G) 0150 TEMPORARY ROCK FILTER DAM TYPE 17CY $110.00 $200.00 $80.00 $300.00 $173.00 $68.00 $225.00 $300.00
80230(A) 2806 SOLID SLAB SODDING15,801SY $3.00 $1.89 $1.89 $2.01 $2.00 $1.90 $1.89 $2.00
90232(A) 2813 SEEDING METHOD A1AC $1,500.00 $900.00 $900.00 $958.50 $950.00 $920.00 $900.00 $900.00
100233(A) 2817 VEGETATIVE MULCHING1AC $1,500.00 $900.00 $900.00 $958.50 $950.00 $925.00 $900.00 $900.00
110241 2832 MOWING2AC $175.00 $500.00 $195.00 $207.68 $206.00 $196.00 $195.00 $100.00
120303(A) 2100 AGGREGATE BASE TYPE A1,055CY $50.00 $45.00 $51.40 $68.00 $54.30 $45.00 $45.00 $45.00
130310(B) 0149 SUBGRADE, METHOD B7,230SY $2.00 $4.00 $1.90 $3.90 $2.00 $2.00 $1.50 $2.00
140325 5271 SEPARATOR FABRIC9,569SY $1.50 $3.50 $2.39 $1.60 $2.50 $1.75 $2.00 $1.50
150407(B) 0250 TACK COAT1,655GAL $3.60 $2.00 $3.00 $4.26 $4.20 $3.15 $4.00 $2.00
160408 5774 PRIME COAT1,652GAL $4.00 $5.00 $3.50 $6.39 $6.35 $2.00 $6.00 $1.00
170411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,537TON $75.00 $86.00 $77.50 $82.01 $81.30 $80.00 $77.00 $65.00
180411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)644TON $90.00 $102.00 $89.00 $101.18 $100.50 $91.00 $95.00 $75.00
190601(B) 0536 TYPE I-A PLAIN RIPRAP50TON $45.00 $30.00 $35.00 $45.00 $47.30 $36.00 $50.00 $70.00
200601(C) 0538 TYPE I-A FILTER BLANKET12TON $45.00 $75.00 $24.00 $45.00 $55.40 $40.00 $38.00 $35.00
210613(EE) 5660 (SP) 48" CORRUGATED POLYPROPYLENE PIPE66LF $120.00 $120.00 $185.00 $215.00 $195.50 $200.00 $160.00 $100.00
220613(L) 5738 48" PREFAB. CULVERT END SECTION, ROUND2EA $2,380.00 $1,800.00 $3,870.00 $3,200.00 $4,086.00 $2,795.00 $2,600.00 $3,000.00
230619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $5,000.00 $15,000.00 $6,900.00 $8,256.00 $37,500.00 $7,660.00 $7,000.00 $10,708.20
240619(B) 4728 REMOVAL OF ASPHALT PAVEMENT4,721SY $5.00 $4.00 $3.00 $7.50 $15.00 $5.00 $8.00 $7.00
250619(C) 0924 SAWING PAVEMENT48LF $8.00 $10.00 $10.00 $17.00 $10.60 $17.00 $5.00 $10.00
260622(A) 4445 2" PIPE RAILING150LF $90.00 $150.00 $150.00 $190.00 $97.10 $190.00 $185.00 $120.00
270623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE350LF $20.00 $35.00 $22.50 $23.96 $23.80 $23.00 $19.00 $23.00
280623(G) 8590 GUARDRAIL END TREATMENT (31")6EA $2,480.00 $3,000.00 $2,650.00 $2,822.25 $2,798.00 $2,700.00 $2,425.00 $2,700.00
290623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $1,750.00 $2,200.00 $1,850.00 $1,970.25 $1,953.00 $2,825.00 $2,350.00 $1,900.00
300624(A) 4281 FENCE-STYLE WWF1,015LF $8.50 $7.50 $7.00 $10.65 $7.70 $9.85 $9.40 $10.00
310853 9069 GUARDRAIL DELINEATORS(TYPE 2, CODE 1)13EA $17.00 $10.00 $15.00 $15.98 $15.80 $16.00 $13.25 $15.00
320501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON251CY $30.00 $27.14 $15.00 $35.00 $37.60 $90.00 $15.00 $40.00
330501(G) 6309 CLSM BACKFILL120CY $155.00 $150.00 $125.00 $175.00 $161.00 $120.00 $160.00 $115.00
340504(A) 1304 APPROACH SLAB322SY $200.00 $205.00 $175.00 $225.00 $211.00 $180.00 $255.00 $180.00
350504(B) 1305 SAW-CUT GROOVING1,259.2SY $5.00 $4.15 $4.15 $4.42 $4.40 $4.25 $4.15 $4.00
360504(C) 6250 SEALED EXPANSION JOINT86LF $320.00 $275.00 $275.00 $310.00 $292.00 $260.00 $325.00 $280.00
370504(E) 1381 CONCRETE PARAPET404.7LF $150.00 $150.00 $100.00 $130.00 $106.00 $75.00 $120.00 $100.00
380504(E) 6190 42" F-SHAPED PARAPET809.4LF $110.00 $110.00 $110.00 $110.00 $113.00 $80.00 $120.00 $125.00
390506(A) 1322 STRUCTURAL STEEL365,950LB $2.50 $1.95 $2.19 $2.29 $1.75 $2.40 $3.20 $2.45
400507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY12EA $1,500.00 $1,000.00 $1,750.00 $2,000.00 $1,772.00 $1,600.00 $1,700.00 $2,000.00
410507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY12EA $1,500.00 $1,000.00 $1,750.00 $2,000.00 $1,772.00 $1,600.00 $1,700.00 $2,300.00
420509(A) 1326 CLASS AA CONCRETE311.8CY $750.00 $500.00 $700.00 $700.00 $658.50 $725.00 $950.00 $900.00
430509(B) 1328 CLASS A CONCRETE218.4CY $600.00 $525.00 $700.00 $850.00 $671.00 $850.00 $950.00 $900.00
440509(D) 1331 CLASS C CONCRETE10CY $375.00 $1,000.00 $1,100.00 $1,500.00 $836.50 $475.00 $1,500.00 $700.00
450510(C) 6138 SLOPE WALL (5")757SY $150.00 $75.00 $120.00 $130.00 $145.00 $125.00 $125.00 $100.00
460511(A) 1332 REINFORCING STEEL31,100LB $1.00 $1.00 $1.10 $1.20 $1.50 $1.40 $1.25 $1.00
470511(B) 6010 EPOXY COATED REINFORCING STEEL86,870LB $1.10 $1.20 $1.20 $1.40 $1.15 $1.60 $1.50 $1.25
480514(A) 6010 PILES, FURNISHED (HP 10X42)162LF $35.00 $35.00 $31.50 $40.00 $41.80 $47.00 $50.00 $40.00
490514(A) 6011 PILES, FURNISHED (HP 12X53)588LF $40.00 $40.00 $40.00 $50.00 $49.70 $50.00 $65.00 $50.00
500514(B) 6292 PILES, DRIVEN (HP 10X42)162LF $25.00 $25.00 $13.50 $25.00 $26.20 $13.00 $10.00 $10.00
510514(B) 6294 PILES, DRIVEN (HP 12X53)588LF $20.00 $20.00 $17.00 $25.00 $21.60 $14.00 $10.00 $10.00
520514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
530516(A) 6098 DRILLED SHAFTS 72" DIAMETER198LF $900.00 $607.00 $1,500.00 $1,100.00 $1,063.00 $1,500.00 $1,000.00 $1,100.00
540516(C) 6200 CROSSHOLE SONIC LOGGING1EA $1,500.00 $1,500.00 $1,600.00 $1,704.00 $5,872.00 $1,450.00 $6,500.00 $7,500.00
550613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND254LF $30.00 $25.00 $50.00 $30.00 $41.10 $20.00 $25.00 $10.00
560613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.110LF $30.00 $25.00 $25.00 $30.00 $36.90 $20.00 $25.00 $10.00
570619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $70,000.00 $70,000.00 $75,000.00 $150,000.00 $270,134.73 $167,280.00 $355,000.00 $367,000.00
580624(E) 4294 FENCE-STYLE CLF (8'HIGH, CLASS A)651LF $75.00 $84.00 $175.00 $58.58 $88.70 $140.00 $191.00 $175.00
590104 0955 (SP) RAILROAD FLAGGING(NON-BIDDABLE)240DAY $600.00 $600.00 $600.00 $600.00 $600.00 $600.00 $600.00 $600.00
600856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)11,243LF $1.00 $0.8500 $0.4600 $0.4900 $0.4900 $0.4700 $0.9000 $0.5000
610880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF7,200SD $0.4000 $0.5000 $0.2500 $0.2700 $0.2600 $0.2700 $0.1000 $0.2500
620880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF3,840SD $1.20 $1.25 $1.00 $1.07 $1.05 $1.10 $0.1000 $1.00
630880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)2,400SD $0.5000 $1.00 $0.5000 $0.5300 $0.5300 $0.5300 $0.1000 $0.5000
640880(E) 8860 WARNING LIGHTS(TYPE A)8,640SD $0.0500 $0.1000 $0.1000 $0.1100 $0.1100 $0.1100 $0.0500 $0.1000
650880(I) 8902 FLAGGER10SD $100.00 $85.00 $100.00 $1,387.28 $1,704.00 $540.00 $350.00 $500.00
660642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $15,000.00 $12,000.00 $10,500.00 $11,715.00 $58,625.00 $21,700.00 $10,000.00 $67,000.00
670220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $5,000.00 $4,000.00 $6,500.00 $7,918.00 $1,750.64 $500.00 $27,000.00
680641 1399 MOBILIZATION1LSUM $193,000.00 $160,000.00 $180,000.00 $199,781.00 $204,950.00 $212,000.00 $225,000.00 $239,000.00
690542 4600 (PL)INSTALLATION OF BRIDGE ITEMS1LSUM $45,000.00 $36,168.00 $66,000.00 $60,000.00 $48,915.00 $36,168.00 $65,000.00 $45,000.00