| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$8,750.00 |
$15,000.00 |
$20,000.00 |
$23,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 1,580 | CY |
$6.90 |
$12.00 |
$12.00 |
$9.80 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 3,540 | CY |
$9.72 |
$15.00 |
$14.00 |
$12.92 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 500 | LF |
$1.50 |
$4.00 |
$6.00 |
$8.00 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 200 | LF |
$6.00 |
$12.00 |
$20.00 |
$8.00 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 1,830 | SY |
$3.50 |
$7.00 |
$9.00 |
$6.00 |
| 7 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 980 | TON |
$58.25 |
$35.00 |
$35.00 |
$29.05 |
| 8 | 613(B) 4527 |
21" X 15" CORR. GALV. STEEL PIPE ARCH | 30 | LF |
$66.00 |
$50.00 |
$50.00 |
$63.20 |
| 9 | 613(EE) 5680 |
(SP) 60" CORRUGATED POLYPROPYLENE PIPE | 212 | LF |
$155.00 |
$175.00 |
$200.00 |
$280.00 |
| 10 | 613(P) 7025 |
21" X 15" GALV. STEEL CULVERT END SECTION ARCH | 2 | EA |
$350.00 |
$350.00 |
$350.00 |
$200.00 |
| 11 | 623(F) 4446 |
GUARDRAIL ANCHOR UNIT (TYPE A) | 4 | EA |
$1,575.00 |
$2,200.00 |
$2,075.00 |
$2,400.00 |
| 12 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,753.00 |
$2,000.00 |
$1,075.00 |
$2,220.00 |
| 13 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 168 | CY |
$10.00 |
$18.00 |
$15.00 |
$18.00 |
| 14 | 501(G) 6309 |
CLSM BACKFILL | 64 | CY |
$159.70 |
$200.00 |
$200.00 |
$170.00 |
| 15 | 504(B) 1305 |
SAW-CUT GROOVING | 152 | SY |
$7.00 |
$10.00 |
$16.45 |
$19.88 |
| 16 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 178 | LF |
$70.00 |
$85.00 |
$100.00 |
$95.00 |
| 17 | 506(A) 1322 |
STRUCTURAL STEEL | 5,230 | LB |
$1.79 |
$4.50 |
$6.00 |
$4.50 |
| 18 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 4 | EA |
$1,089.85 |
$1,500.00 |
$1,800.00 |
$2,400.00 |
| 19 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 4 | EA |
$1,200.00 |
$1,500.00 |
$1,800.00 |
$2,222.00 |
| 20 | 509(A) 1326 |
CLASS AA CONCRETE | 47 | CY |
$300.00 |
$625.00 |
$850.00 |
$900.00 |
| 21 | 509(B) 1328 |
CLASS A CONCRETE | 65 | CY |
$595.23 |
$1,350.00 |
$850.00 |
$900.00 |
| 22 | 511(A) 1332 |
REINFORCING STEEL | 20,000 | LB |
$0.9000 |
$2.00 |
$1.20 |
$1.30 |
| 23 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 108 | LF |
$31.54 |
$45.00 |
$45.00 |
$40.00 |
| 24 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 230 | LF |
$40.11 |
$45.00 |
$55.00 |
$45.00 |
| 25 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 108 | LF |
$15.23 |
$15.00 |
$10.00 |
$10.00 |
| 26 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 230 | LF |
$12.35 |
$15.00 |
$10.00 |
$10.00 |
| 27 | 514(K) 6260 |
(PL)PILOT HOLES | 310 | LF |
$175.00 |
$140.00 |
$205.00 |
$200.00 |
| 28 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 29 | 535 6225 |
HAUL AND ERECT STEEL BEAMS | 1 | LSUM |
$25,000.00 |
$2,000.00 |
$30,000.00 |
$42,865.00 |
| 30 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 530 | TON |
$45.00 |
$50.00 |
$50.00 |
$41.00 |
| 31 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 660 | TON |
$36.00 |
$35.00 |
$42.00 |
$30.00 |
| 32 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$10,000.00 |
$5,000.00 |
$10,000.00 |
$10,000.00 |
| 33 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$2,500.00 |
$4,000.00 |
$3,000.00 |
$3,600.00 |
| 34 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$8,500.00 |
$8,000.00 |
$7,380.00 |
$7,000.00 |
| 35 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$8,500.00 |
$2,500.00 |
$500.00 |
$2,500.00 |
| 36 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$45,697.00 |
$45,000.00 |
$55,000.00 |
$50,000.00 |