$127.80Avg low bid / LF
$157.84Avg of all bids
$152.40Avg engineer's estimate
26Jobs · 9,315.19 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 4 | 663 | $163.49 | $188.05 |
| 2020 | 8 | 4,574 | $126.64 | $138.97 |
| 2019 | 6 | 1,480 | $143.23 | $175.79 |
| 2018 | 6 | 2,087.19 | $96.08 | $174.15 |
| 2017 | 2 | 511 | $176.78 | $174.86 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 15, 2021 | 210209 | KayDivision 4 | 150 LF | $250.00 | H & H BRIDGE COMPANY |
| Jun 17, 2021 | 210176 | Leflore, Mccurtain | 296 LF | $151.00 | HUB Construction, Inc. |
| Feb 18, 2021 | 210048 | CraigDivision 8 | 49 LF | $225.00 | CONCRETE SERVICES CORPORATION |
| Feb 18, 2021 | 190362 | LoveDivision 7 | 168 LF | $90.33 | C3 Construction, Inc. |
| Oct 15, 2020 | 200317 | MccurtainDivision 2 | 210 LF | $161.00 | HUB Construction, Inc. |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 297 LF | $122.83 | SHERWOOD CONSTRUCTION CO., INC. |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 297 LF | $122.83 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200214 | Stp-266d(065)ci | 182 LF | $125.00 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| May 14, 2020 | 190347 | DelawareDivision 8 | 221 LF | $475.00 | RRY SERVICES LLC |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 1,760 LF | $54.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Apr 16, 2020 | 200152 | HaskellDivision 1 | 967 LF | $175.00 | C-GAWF CONSTRUCTION, INC. |
| Feb 20, 2020 | 200050 | BeckhamDivision 5 | 320 LF | $152.58 | Frontier Bridge, Inc. |
| Feb 20, 2020 | 190255 | Pontotoc | 320 LF | $99.00 | BRIDGECO CONTRACTORS, INC. |
| Nov 14, 2019 | 190378 | WashitaDivision 5 | 314 LF | $135.00 | SEWELL BROS., INC. |
| Aug 22, 2019 | 190257 | SequoyahDivision 1 | 56 LF | $207.00 | JOB CONSTRUCTION CO., INC. |
| Jun 20, 2019 | 190189 | AtokaDivision 2 | 310 LF | $140.00 | Built Right Construction, LLC |
| May 16, 2019 | 190027 | WashingtonDivision 8 | 330 LF | $150.00 | BECCO CONTRACTORS, INC. |
| Feb 14, 2019 | 190066 | AtokaDivision 2 | 135 LF | $204.23 | C3 Construction, Inc. |
| Feb 14, 2019 | 190090 | PittsburgDivision 2 | 335 LF | $112.00 | HUB Construction, Inc. |
| Nov 15, 2018 | 180359 | OklahomaDivision 4 | 117 LF | $60.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Nov 15, 2018 | 180359 | OklahomaDivision 4 | 175 LF | $60.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Nov 15, 2018 | 180345 | BryanDivision 2 | 804.19 LF | $60.56 | HUB Construction, Inc. |
| May 17, 2018 | 180195 | HughesDivision 3 | 135 LF | $225.00 | C-GAWF CONSTRUCTION, INC. |
| May 17, 2018 | 180215 | WoodsDivision 6 | 420 LF | $90.00 | Venture Corporation dba VCO Paving |
| Apr 19, 2018 | 180056 | McintoshDivision 1 | 186 LF | $236.12 | C3 Construction, Inc. |
| Feb 15, 2018 | 180033 | SeminoleDivision 3 | 250 LF | $88.86 | Treas Construction Inc |
| Feb 16, 2017 | 170064 | CaddoDivision 7 | 90 LF | $302.07 | FRONTIER BRIDGE, INC. / BRIDGECO CONTRACTORS, INC. |
| Jan 19, 2017 | 170016 | DelawareDivision 8 | 421 LF | $150.00 | RRY SERVICES LLC |