$1,874.97Avg low bid / EA
$1,883.76Avg of all bids
$1,772.36Avg engineer's estimate
105Jobs · 434 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 13 | 58 | $2,191.41 | $2,294.13 |
| 2020 | 40 | 156 | $1,779.49 | $1,804.13 |
| 2019 | 27 | 115 | $1,754.36 | $1,777.17 |
| 2018 | 25 | 105 | $1,974.14 | $1,864.73 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 16, 2021 | 210251 | Cirb-230c(045)rb | 4 EA | $2,447.50 | K & R BUILDERS, INC. |
| Sep 16, 2021 | 210251 | Cirb-230c(045)rb | 4 EA | $2,447.50 | K & R BUILDERS, INC. |
| Sep 16, 2021 | 210267 | PayneDivision 4 | 4 EA | $2,250.00 | H & H BRIDGE COMPANY |
| Jul 15, 2021 | 210209 | KayDivision 4 | 4 EA | $2,300.00 | H & H BRIDGE COMPANY |
| Jul 15, 2021 | 210180 | MuskogeeDivision 1 | 4 EA | $2,500.00 | H & H BRIDGE COMPANY |
| Jul 15, 2021 | 210200 | BeckhamDivision 5 | 2 EA | $2,200.00 | SEWELL BROS., INC. |
| Jun 17, 2021 | 210176 | Leflore, Mccurtain | 4 EA | $2,200.00 | HUB Construction, Inc. |
| May 20, 2021 | 210140 | McclainDivision 3 | 8 EA | $2,100.00 | Treas Construction Inc |
| May 20, 2021 | 210143 | MurrayDivision 7 | 4 EA | $2,645.50 | OVERLAND CORPORATION |
| Mar 18, 2021 | 210078 | KayDivision 4 | 4 EA | $1,955.00 | RRY SERVICES LLC |
| Feb 18, 2021 | 210046 | ComancheDivision 7 | 4 EA | $1,850.00 | K & R BUILDERS, INC. |
| Feb 18, 2021 | 210048 | CraigDivision 8 | 4 EA | $2,000.00 | CONCRETE SERVICES CORPORATION |
| Jan 21, 2021 | 210014 | GarfieldDivision 4 | 4 EA | $2,200.00 | K & R BUILDERS, INC. |
| Jan 21, 2021 | 210016 | GradyDivision 7 | 4 EA | $1,680.00 | K & R BUILDERS, INC. |
| Nov 19, 2020 | 200344 | CaddoDivision 7 | 4 EA | $1,812.60 | K & R BUILDERS, INC. |
| Nov 19, 2020 | 200359 | MccurtainDivision 2 | 4 EA | $2,163.00 | Frontier Bridge, Inc. |
| Nov 19, 2020 | 200156 | MajorDivision 6 | 4 EA | $2,257.00 | K & R BUILDERS, INC. |
| Oct 15, 2020 | 200317 | MccurtainDivision 2 | 8 EA | $1,814.00 | HUB Construction, Inc. |
| Oct 15, 2020 | 200304 | BlaineDivision 5 | 1 EA | $2,750.00 | K & R BUILDERS, INC. |
| Oct 15, 2020 | 200314 | KingfisherDivision 4 | 4 EA | $1,650.00 | K & R BUILDERS, INC. |
| Sep 17, 2020 | 200281 | KiowaDivision 5 | 2 EA | $2,300.00 | SEWELL BROS., INC. |
| Sep 17, 2020 | 200284 | MajorDivision 6 | 4 EA | $2,505.00 | BRIDGECO CONTRACTORS, INC. |
| Aug 20, 2020 | 200264 | Leflore | 4 EA | $1,200.00 | HUB Construction, Inc. |
| Aug 20, 2020 | 200225 | GradyDivision 7 | 4 EA | $1,760.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200239 | WoodsDivision 6 | 4 EA | $2,170.00 | K & R BUILDERS, INC. |
| Aug 20, 2020 | 200262 | BeckhamDivision 5 | 4 EA | $1,375.00 | SEWELL BROS., INC. |
| Jun 18, 2020 | 200237 | StephensDivision 7 | 4 EA | $1,650.00 | SEWELL BROS., INC. |
| May 14, 2020 | 200188 | Cirb-207d(100)rb | 4 EA | $1,750.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 14, 2020 | 200214 | Stp-266d(065)ci | 4 EA | $1,375.00 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| May 14, 2020 | 200190 | Cirb-210d(071)rb | 4 EA | $1,575.00 | Treas Construction Inc |
| May 14, 2020 | 190377 | WashingtonDivision 8 | 4 EA | $1,175.00 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| May 14, 2020 | 200192 | ComancheDivision 7 | 4 EA | $1,716.00 | Frontier Bridge, Inc. |
| May 14, 2020 | 190347 | DelawareDivision 8 | 4 EA | $1,000.00 | RRY SERVICES LLC |
| May 14, 2020 | 200202 | MuskogeeDivision 1 | 4 EA | $2,575.00 | Treas Construction Inc |
| May 14, 2020 | 200203 | MuskogeeDivision 1 | 4 EA | $1,391.00 | Treas Construction Inc |
| May 14, 2020 | 200212 | StephensDivision 7 | 4 EA | $1,650.00 | SEWELL BROS., INC. |
| Apr 16, 2020 | 200149 | DelawareDivision 8 | 2 EA | $3,520.00 | K & R BUILDERS, INC. |
| Apr 16, 2020 | 200028 | Cirb-264d(069)rb | 4 EA | $1,575.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Apr 16, 2020 | 200153 | Jefferson | 8 EA | $1,567.50 | K & R BUILDERS, INC. |
| Apr 16, 2020 | 200155 | LincolnDivision 3 | 4 EA | $1,575.00 | BRIDGECO CONTRACTORS, INC. |
| Apr 16, 2020 | 200166 | OsageDivision 8 | 2 EA | $2,625.00 | LOGOS CONSTRUCTION CO., LLC |
| Apr 16, 2020 | 200008 | CreekDivision 8 | 4 EA | $2,572.00 | LOGOS CONSTRUCTION CO., LLC |
| Apr 16, 2020 | 200138 | BeaverDivision 6 | 4 EA | $2,612.50 | K & R BUILDERS, INC. |
| Mar 19, 2020 | 200027 | PayneDivision 4 | 2 EA | $1,625.00 | Atlas Paving Company |
| Mar 19, 2020 | 200102 | GrantDivision 4 | 4 EA | $1,820.00 | H & H BRIDGE COMPANY |
| Mar 19, 2020 | 200032 | SeminoleDivision 3 | 4 EA | $1,250.00 | RRY SERVICES LLC |
| Mar 19, 2020 | 200109 | MajorDivision 6 | 4 EA | $1,750.00 | WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES |
| Mar 19, 2020 | 200113 | OkfuskeeDivision 3 | 4 EA | $1,375.00 | H & H BRIDGE COMPANY |
| Feb 20, 2020 | 200073 | MarshallDivision 2 | 4 EA | $1,669.27 | HUB Construction, Inc. |
| Feb 20, 2020 | 200069 | LincolnDivision 3 | 4 EA | $1,600.00 | Cowboy Contracting, Inc. |
| Jan 16, 2020 | 190317 | KayDivision 4 | 4 EA | $1,650.00 | BRIDGECO CONTRACTORS, INC. |
| Jan 16, 2020 | 190207 | CarterDivision 7 | 4 EA | $1,935.00 | K & R BUILDERS, INC. |
| Jan 16, 2020 | 200039 | WoodsDivision 6 | 4 EA | $1,900.00 | RRY SERVICES LLC |
| Jan 16, 2020 | 200043 | HaskellDivision 1 | 3 EA | $1,175.00 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Nov 14, 2019 | 190364 | MayesDivision 8 | 4 EA | $1,225.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Nov 14, 2019 | 190386 | CoalDivision 3 | 4 EA | $1,750.00 | BRIDGECO CONTRACTORS, INC. |
| Nov 14, 2019 | 190387 | LincolnDivision 3 | 4 EA | $1,650.00 | BRIDGECO CONTRACTORS, INC. |
| Nov 14, 2019 | 190355 | JacksonDivision 5 | 1 EA | $2,200.00 | SEWELL BROS., INC. |
| Nov 14, 2019 | 190361 | KiowaDivision 5 | 1 EA | $2,200.00 | SEWELL BROS., INC. |
| Sep 19, 2019 | 190290 | MarshallDivision 2 | 12 EA | $1,590.00 | OVERLAND CORPORATION |
| Sep 19, 2019 | 190224 | OklahomaDivision 4 | 4 EA | $1,655.00 | Silver Star Construction Company, Inc. |
| Aug 22, 2019 | 190244 | CusterDivision 5 | 1 EA | $2,550.00 | SEWELL BROS., INC. |
| Aug 22, 2019 | 190257 | SequoyahDivision 1 | 4 EA | $1,200.00 | JOB CONSTRUCTION CO., INC. |
| Jun 20, 2019 | 190189 | AtokaDivision 2 | 4 EA | $2,000.00 | Built Right Construction, LLC |
| Jun 20, 2019 | 180107 | OsageDivision 8 | 4 EA | $1,400.00 | RRY SERVICES LLC |
| Jun 20, 2019 | 190200 | NowataDivision 8 | 4 EA | $1,175.00 | H & H BRIDGE COMPANY |
| Jun 20, 2019 | 180207 | OttawaDivision 8 | 4 EA | $1,400.00 | B & B BRIDGE COMPANY, LLC |
| Jun 20, 2019 | 190119 | MuskogeeDivision 1 | 4 EA | $1,690.00 | H & H BRIDGE COMPANY |
| May 16, 2019 | 190173 | CanadianDivision 4 | 4 EA | $1,925.00 | SEWELL BROS., INC. |
| May 16, 2019 | 190179 | McclainDivision 3 | 4 EA | $1,875.00 | BRIDGECO CONTRACTORS, INC. |
| May 16, 2019 | 190181 | MarshallDivision 2 | 4 EA | $1,800.00 | HUB Construction, Inc. |
| May 16, 2019 | 190017 | NowataDivision 8 | 4 EA | $1,300.00 | H & H BRIDGE COMPANY |
| Apr 18, 2019 | 190167 | StephensDivision 7 | 4 EA | $1,825.00 | RRY SERVICES LLC |
| Mar 14, 2019 | 190140 | MurrayDivision 7 | 4 EA | $3,500.00 | BRIDGECO CONTRACTORS, INC. |
| Mar 14, 2019 | 190003 | BeaverDivision 6 | 4 EA | $2,200.00 | Bridges, Inc. DBA Scudder Bridge Co. |
| Feb 14, 2019 | 190066 | AtokaDivision 2 | 4 EA | $1,974.27 | C3 Construction, Inc. |
| Feb 14, 2019 | 190090 | PittsburgDivision 2 | 4 EA | $2,000.00 | HUB Construction, Inc. |
| Feb 14, 2019 | 190015 | MccurtainDivision 2 | 4 EA | $1,700.00 | L & N BRIDGE, LLC |
| Jan 17, 2019 | 180209 | PittsburgDivision 2 | 4 EA | $2,845.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 17, 2019 | 190059 | SequoyahDivision 1 | 4 EA | $1,500.00 | T. McDonald Construction, Inc. |
| Jan 17, 2019 | 190064 | Major, Woodward | 12 EA | $1,447.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 15, 2018 | 180243 | LoveDivision 7 | 4 EA | $2,280.00 | SCHIRALLI CONSTRUCTION CORP. |
| Nov 15, 2018 | 180260 | ChoctawDivision 2 | 4 EA | $1,725.00 | H & H BRIDGE COMPANY |
| Nov 15, 2018 | 180227 | NobleDivision 4 | 4 EA | $2,195.00 | B & B BRIDGE COMPANY, LLC |
| Nov 15, 2018 | 180273 | WagonerDivision 1 | 4 EA | $1,500.00 | B & B BRIDGE COMPANY, LLC |
| Nov 15, 2018 | 180238 | GradyDivision 7 | 4 EA | $1,925.00 | SEWELL BROS., INC. |
| Nov 15, 2018 | 180312 | WashitaDivision 5 | 1 EA | $2,500.00 | SEWELL BROS., INC. |
| Oct 18, 2018 | 180188 | CarterDivision 7 | 4 EA | $2,665.00 | OVERLAND CORPORATION |
| Sep 20, 2018 | 180202 | McintoshDivision 1 | 4 EA | $1,750.00 | RRY SERVICES LLC |
| Sep 20, 2018 | 180208 | PayneDivision 4 | 4 EA | $1,525.00 | K & R BUILDERS, INC. |
| Jul 19, 2018 | 180214 | WoodsDivision 6 | 4 EA | $1,950.00 | B & B BRIDGE COMPANY, LLC |
| Jul 19, 2018 | 180257 | MuskogeeDivision 1 | 4 EA | $1,700.00 | RRY SERVICES LLC |
| Jul 19, 2018 | 180240 | KingfisherDivision 4 | 4 EA | $2,045.00 | RRY SERVICES LLC |
| Jun 14, 2018 | 180225 | Stp-231c(033)ci | 4 EA | $1,650.00 | T. McDonald Construction, Inc. |
| Apr 19, 2018 | 180186 | GradyDivision 7 | 4 EA | $2,000.00 | K & R BUILDERS, INC. |
| Apr 19, 2018 | 180056 | McintoshDivision 1 | 4 EA | $2,983.27 | C3 Construction, Inc. |
| Apr 19, 2018 | 180168 | LoganDivision 4 | 4 EA | $2,000.00 | K & R BUILDERS, INC. |
| Mar 15, 2018 | 180054 | McclainDivision 3 | 4 EA | $1,600.00 | SEWELL BROS., INC. |
| Mar 15, 2018 | 180134 | LatimerDivision 2 | 4 EA | $1,500.00 | L & N BRIDGE, LLC |
| Mar 15, 2018 | 180151 | WashingtonDivision 8 | 4 EA | $2,000.00 | BECCO CONTRACTORS, INC. |
| Mar 15, 2018 | 180077 | AlfalfaDivision 6 | 4 EA | $2,226.65 | C3 Construction, Inc. |
| Feb 15, 2018 | 180108 | OsageDivision 8 | 4 EA | $1,550.00 | BRIDGECO CONTRACTORS, INC. |
| Feb 15, 2018 | 180070 | SequoyahDivision 1 | 4 EA | $1,450.00 | B & B BRIDGE COMPANY, LLC |
| Feb 15, 2018 | 180078 | CherokeeDivision 1 | 4 EA | $2,188.20 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| Jan 18, 2018 | 180061 | OsageDivision 8 | 12 EA | $2,346.00 | Built Right Construction, LLC |
| Jan 18, 2018 | 180043 | ComancheDivision 7 | 4 EA | $1,750.00 | BRIDGECO CONTRACTORS, INC. |