| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$17,408.00 |
$9,500.00 |
$10,000.00 |
$6,800.00 |
$12,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 57 | CY |
$16.38 |
$38.10 |
$18.00 |
$460.00 |
$50.00 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 5,488 | CY |
$10.88 |
$13.10 |
$16.00 |
$21.00 |
$19.00 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,420 | LF |
$1.78 |
$3.55 |
$2.75 |
$3.15 |
$3.12 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 160 | LF |
$9.45 |
$20.30 |
$9.00 |
$20.15 |
$19.98 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 29,164 | SY |
$4.10 |
$4.10 |
$7.00 |
$4.05 |
$3.99 |
| 7 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 286 | CY |
$57.93 |
$64.65 |
$98.50 |
$55.00 |
$100.00 |
| 8 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 100 | TON |
$25.04 |
$54.85 |
$50.00 |
$54.30 |
$50.00 |
| 9 | 407(B) 0250 |
TACK COAT | 14,704 | GAL |
$3.10 |
$3.25 |
$1.91 |
$2.50 |
$2.25 |
| 10 | 408 5774 |
PRIME COAT | 433 | GAL |
$7.00 |
$5.20 |
$5.00 |
$5.00 |
$3.00 |
| 11 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 300 | TON |
$96.00 |
$132.00 |
$135.60 |
$169.00 |
$225.00 |
| 12 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 10,935 | TON |
$68.00 |
$81.00 |
$74.77 |
$81.75 |
$83.00 |
| 13 | 411(D) 5975 |
SUPERPAVE, TYPE S5(PG 64-22 OK) | 9,453 | TON |
$68.00 |
$74.75 |
$70.90 |
$85.50 |
$83.40 |
| 14 | 412 5267 |
COLD MILLING PAVEMENT | 1,400 | SY |
$8.35 |
$7.30 |
$13.71 |
$10.00 |
$15.00 |
| 15 | 509(A) 0319 |
CLASS AA CONCRETE | 7.1 | CY |
$733.50 |
$2,190.00 |
$2,200.00 |
$1,005.00 |
$1,000.00 |
| 16 | 511(A) 0332 |
REINFORCING STEEL | 1,519.94 | LB |
$1.36 |
$1.95 |
$1.45 |
$1.00 |
$1.55 |
| 17 | 613(A) 4495 |
22" X 13" R.C.PIPE ARCH CLASS A-III | 60 | LF |
$71.08 |
$127.55 |
$78.00 |
$93.50 |
$150.00 |
| 18 | 613(L) 4506 |
22" X 13" PREFAB. CULVERT END SEC., ARCH | 2 | EA |
$880.00 |
$1,193.00 |
$1,500.00 |
$1,115.00 |
$1,200.00 |
| 19 | 619(B) 0291 |
REMOVAL OF HEADWALL | 1 | EA |
$1,750.00 |
$10,150.00 |
$10,000.00 |
$5,900.00 |
$2,000.00 |
| 20 | 619(B) 4778 |
REMOVAL OF EXISTING STRUCTURES | 2 | EA |
$2,000.00 |
$3,555.00 |
$2,500.00 |
$1,200.00 |
$2,000.00 |
| 21 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 100 | LF |
$19.30 |
$25.40 |
$22.50 |
$25.25 |
$22.00 |
| 22 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,570.00 |
$2,845.00 |
$1,600.00 |
$2,820.00 |
$1,550.00 |
| 23 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 4 | EA |
$2,380.00 |
$1,525.00 |
$2,750.00 |
$1,500.00 |
$2,750.00 |
| 24 | 504 6179 |
BRIDGE TRAFFIC RAIL | 84 | LF |
$220.00 |
$201.00 |
$200.00 |
$200.00 |
$255.00 |
| 25 | 884(C) 8424 |
REMOVE BRIDGE RAIL & POSTS(CONC.) | 84 | LF |
$55.00 |
$101.00 |
$100.00 |
$160.00 |
$55.00 |
| 26 | 823 8478 |
(SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 45 | SD |
$97.02 |
$152.25 |
$160.00 |
$150.00 |
$150.00 |
| 27 | 854(A) 8800 |
TRAFFIC STRIPE(PAINT)(4" WIDE) | 150,600 | LF |
$0.0800 |
$0.1000 |
$0.1200 |
$0.1000 |
$0.1000 |
| 28 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$7,200.00 |
$8,800.00 |
$12,000.00 |
$15,000.00 |
$6,000.00 |
| 29 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$14,500.00 |
$25,375.00 |
$20,000.00 |
$7,550.00 |
$10,000.00 |
| 30 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$3,400.00 |
$2,030.00 |
$5,000.00 |
$1,400.00 |
$2,000.00 |
| 31 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$66,900.00 |
$62,575.00 |
$125,000.00 |
$42,000.00 |
$141,810.00 |