Bid tab 200314

Let Oct 15, 2020 · Division 4 · Kingfisher Sign up free

‹ Oct 2020 results

BRIDGE AND APPROACHES COUNTY ROAD (EW-67): OVER TURKEY CREEK , 2.5 MILES WEST OF THE US -81 JUNCTION NEAR HENNESSEY. PROJECT LENGTH = 0.284 MILE

Let date
Thursday, October 15, 2020
Contract
200314
J/P numbers
28439(04)
District
Division 4
County
Kingfisher
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-67): OVER TURKEY CREEK , 2.5 MILES WEST OF THE US -81 JUNCTION NEAR HENNESSEY. PROJECT LENGTH = 0.284 MILE
Project number
STP-237D(051)CI

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$859,182
1 K & R BUILDERS, INC. Low bidder $768,168 -10.6%
2 BRIDGECO CONTRACTORS, INC. $841,502 -2.1% +9.5%
3 RRY SERVICES LLC $871,906 +1.5% +13.5%
4 HASKELL LEMON CONSTRUCTION CO. $928,297 +8.0% +20.8%
5 Treas Construction Inc $933,355 +8.6% +21.5%
6 Bridges, Inc. DBA Scudder Bridge Co. $939,992 +9.4% +22.4%
7 Built Right Construction, LLC $999,110 +16.3% +30.1%
8 Frontier Bridge, Inc. $1,036,588 +20.6% +34.9%

Bid tab: unit prices 46 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 K & R BUILDERS,…#2 BRIDGECO CONTRA…#3 RRY SERVICES LLC#4 HASKELL LEMON C…#5 Treas Construct…#6 Bridges, Inc. D…#7 Built Right Con…#8 Frontier Bridge…
10202(D) 0184 UNCLASSIFIED BORROW400CY $12.00 $3.50 $11.00 $1.00 $14.68 $11.00 $11.00 $25.00 $9.68
20202(H) 0185 EARTHWORK1LSUM $40,000.00 $48,000.00 $59,766.24 $50,000.00 $58,584.70 $36,800.00 $36,800.00 $9,000.00 $73,637.50
30221(C) 2801 TEMPORARY SILT FENCE1,000LF $3.25 $1.30 $2.65 $3.00 $3.03 $1.65 $2.00 $5.00 $3.11
40221(F) 0100 TEMPORARY SILT DIKE364LF $11.00 $7.15 $9.00 $13.50 $13.40 $6.98 $7.50 $15.00 $13.74
50230(A) 2806 SOLID SLAB SODDING9,228SY $3.15 $2.53 $2.50 $2.65 $2.61 $2.29 $2.29 $4.00 $2.68
60233(A) 2817 VEGETATIVE MULCHING1.91AC $700.00 $500.00 $900.00 $1,275.00 $1,337.35 $850.00 $850.00 $4,200.00 $1,370.63
70402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E1,070TON $36.00 $38.15 $39.35 $40.00 $70.82 $41.00 $41.00 $47.00 $40.78
80509(D) 0325 CLASS C CONCRETE10CY $400.00 $265.00 $300.00 $250.00 $336.24 $585.00 $350.00 $500.00 $427.90
90613(B) 0690 24" CORR. GALV. STEEL PIPE64LF $35.00 $27.00 $36.20 $40.00 $28.71 $29.75 $29.75 $60.00 $39.61
100613(B) 4530 42" X 29" CORR. GALV. STEEL PIPE ARCH230LF $74.00 $44.00 $56.10 $60.00 $54.59 $57.00 $57.00 $75.00 $77.34
110613(M) 7187 TYPE B4 CULVERT END TREATMENT2EA $1,300.00 $1,250.00 $1,800.00 $1,600.00 $1,187.94 $1,884.75 $1,400.00 $2,500.00 $1,642.41
120613(M) 7188 TYPE C4 CULVERT END TREATMENT6EA $1,500.00 $2,080.00 $2,300.00 $1,900.00 $1,712.48 $2,165.25 $1,550.00 $2,000.00 $2,136.57
130619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $3,000.00 $2,250.00 $3,500.00 $3,500.00 $9,630.69 $2,700.00 $2,700.00 $10,000.00 $6,450.00
140623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE80LF $38.00 $44.00 $42.00 $40.00 $20.45 $40.00 $40.00 $22.00 $43.00
150623(F) 4446 GUARDRAIL ANCHOR UNIT (TYPE A)2EA $1,200.00 $1,650.00 $1,600.00 $1,500.00 $1,258.68 $1,500.00 $1,500.00 $2,000.00 $1,612.50
160623(F) 5686 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $1,850.00 $1,650.00 $1,600.00 $1,500.00 $1,599.57 $1,500.00 $1,500.00 $2,000.00 $1,612.50
170501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON180CY $12.00 $9.00 $12.00 $15.00 $16.80 $30.00 $26.00 $20.00 $32.25
180501(F) 6352 GRANULAR BACKFILL66CY $75.00 $62.25 $72.00 $85.00 $108.34 $84.92 $70.00 $85.00 $109.47
190503(A) 1311 PRESTRESSED CONCRETE BEAMS (TYPE II)238LF $205.00 $184.50 $197.70 $195.00 $168.03 $308.62 $250.00 $225.00 $185.13
200503(A) 1312 PRESTRESSED CONCRETE BEAMS (TYPE III)224LF $232.00 $219.00 $219.00 $210.00 $219.88 $224.05 $290.00 $225.00 $240.59
210504(C) 6250 SEALED EXPANSION JOINT58.34LF $290.00 $260.00 $280.50 $244.00 $248.33 $1.00 $320.00 $450.00 $317.19
220504(D) 6239 CONCRETE RAIL (TR3)368.8LF $81.00 $74.00 $80.00 $80.00 $88.92 $81.93 $90.00 $115.00 $75.27
230506(A) 1322 STRUCTURAL STEEL1,070LB $3.40 $2.75 $3.05 $2.65 $2.78 $3.57 $4.50 $4.00 $3.80
240507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY9EA $900.00 $810.00 $825.00 $850.00 $895.93 $944.85 $850.00 $1,500.00 $1,223.57
250507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY9EA $900.00 $810.00 $825.00 $850.00 $895.93 $944.85 $850.00 $1,500.00 $1,223.57
260509(A) 1326 CLASS AA CONCRETE123.3CY $700.00 $590.00 $650.00 $650.00 $591.89 $764.92 $650.00 $600.00 $920.31
270509(B) 1328 CLASS A CONCRETE107.4CY $725.00 $620.00 $650.00 $650.00 $675.82 $764.92 $850.00 $600.00 $824.83
280511(A) 1332 REINFORCING STEEL48,480LB $1.05 $0.9500 $1.05 $1.00 $1.15 $1.48 $1.00 $1.50 $1.18
290514(A) 6010 PILES, FURNISHED (HP 10X42)206LF $35.00 $24.50 $24.20 $40.00 $29.58 $19.54 $42.00 $45.00 $37.70
300514(A) 6011 PILES, FURNISHED (HP 12X53)485LF $39.00 $28.00 $29.10 $50.00 $36.50 $24.64 $51.00 $45.00 $41.46
310514(B) 6292 PILES, DRIVEN (HP 10X42)206LF $14.00 $10.50 $12.00 $10.00 $22.34 $15.00 $10.50 $35.00 $26.88
320514(B) 6294 PILES, DRIVEN (HP 12X53)485LF $15.00 $12.00 $10.00 $10.00 $18.00 $15.00 $12.50 $35.00 $22.58
330514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
340516(A) 6094 DRILLED SHAFTS 48" DIAMETER172LF $700.00 $616.00 $645.80 $650.00 $685.84 $807.43 $825.00 $650.00 $908.94
350601(B) 1353 TYPE I-A PLAIN RIPRAP1,061TON $46.00 $52.15 $51.35 $60.00 $54.40 $61.51 $62.00 $65.00 $54.74
360601(C) 1355 TYPE I-A FILTER BLANKET354TON $38.00 $42.65 $48.00 $50.00 $42.25 $50.55 $46.00 $45.00 $43.23
370613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND52LF $35.00 $28.00 $45.00 $40.00 $45.21 $12.11 $30.00 $20.00 $25.76
380613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.40LF $30.00 $28.00 $45.00 $40.00 $29.31 $12.11 $30.00 $35.00 $27.05
390619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $12,000.00 $6,500.00 $15,000.00 $23,000.00 $26,345.50 $7,595.00 $20,000.00 $15,000.00 $16,125.00
400850(A) 8110 SHEET ALUMINUM SIGNS7.46SF $38.00 $55.00 $52.00 $50.00 $50.35 $50.00 $50.00 $85.00 $53.75
410880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF2,304SD $0.6000 $0.1100 $0.1200 $0.1000 $1.84 $0.1000 $0.1000 $1.75 $0.1100
420880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)2,016SD $1.00 $0.1100 $0.1200 $0.1000 $0.1600 $0.1000 $0.1000 $0.1500 $0.1100
421880(E) 8860 WARNING LIGHTS(TYPE A)4,560SD $0.0400 $0.0600 $0.1000 $0.0500 $0.1300 $0.0500 $0.0500 $0.1200 $0.0500
430642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $7,200.00 $6,250.00 $9,100.00 $5,500.00 $8,896.46 $8,000.00 $5,000.00 $17,500.00 $5,912.50
440220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $2,500.00 $1,650.00 $3,000.00 $500.00 $2,294.01 $2,500.00 $2,000.00 $2,500.00 $2,687.50
450641 1399 MOBILIZATION1LSUM $50,000.00 $39,000.00 $42,600.00 $66,000.00 $61,053.40 $65,833.82 $59,500.00 $88,000.00 $74,373.24