| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$19,000.00 |
$8,000.00 |
$10,000.00 |
$11,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 2,900 | CY |
$10.21 |
$7.25 |
$8.50 |
$4.50 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 500 | CY |
$14.68 |
$10.50 |
$11.00 |
$7.50 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 926 | LF |
$2.00 |
$3.99 |
$2.10 |
$1.90 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 72 | LF |
$9.00 |
$22.50 |
$7.00 |
$6.35 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 1,849 | SY |
$4.00 |
$6.95 |
$6.95 |
$7.30 |
| 7 | 233(A) 2817 |
VEGETATIVE MULCHING | 0.76 | AC |
$550.00 |
$5,950.00 |
$5,950.00 |
$1,028.00 |
| 8 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 291 | CY |
$55.00 |
$50.00 |
$31.00 |
$45.25 |
| 9 | 310(B) 0149 |
SUBGRADE, METHOD B | 1,123 | SY |
$4.00 |
$2.00 |
$4.50 |
$2.55 |
| 10 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 317 | TON |
$28.25 |
$23.00 |
$29.00 |
$23.60 |
| 11 | 407(B) 0250 |
TACK COAT | 171 | GAL |
$3.78 |
$6.45 |
$6.45 |
$8.30 |
| 12 | 408 5774 |
PRIME COAT | 674 | GAL |
$7.77 |
$3.56 |
$3.56 |
$4.60 |
| 13 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 180 | TON |
$120.00 |
$119.95 |
$119.95 |
$154.25 |
| 14 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 284 | TON |
$150.00 |
$121.95 |
$121.95 |
$156.70 |
| 15 | 412 5267 |
COLD MILLING PAVEMENT | 1,208 | SY |
$7.00 |
$9.00 |
$9.00 |
$11.60 |
| 16 | 509(D) 0325 |
CLASS C CONCRETE | 20 | CY |
$310.53 |
$265.00 |
$300.00 |
$429.20 |
| 17 | 601(A) 0297 |
TYPE I PLAIN RIPRAP | 570 | TON |
$44.00 |
$38.00 |
$37.00 |
$56.55 |
| 18 | 613(EE) 5680 |
(SP) 60" CORRUGATED POLYPROPYLENE PIPE | 160 | LF |
$125.00 |
$150.00 |
$155.00 |
$157.55 |
| 19 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 210 | CY |
$17.69 |
$12.00 |
$15.00 |
$15.50 |
| 20 | 501(G) 6309 |
CLSM BACKFILL | 92 | CY |
$175.00 |
$130.00 |
$100.00 |
$111.80 |
| 21 | 503(A) 1312 |
PRESTRESSED CONCRETE BEAMS (TYPE III) | 358.67 | LF |
$233.91 |
$220.00 |
$260.00 |
$242.50 |
| 22 | 504(A) 1304 |
APPROACH SLAB | 142.22 | SY |
$185.73 |
$185.00 |
$200.00 |
$126.75 |
| 23 | 504(B) 1305 |
SAW-CUT GROOVING | 405.02 | SY |
$10.00 |
$6.90 |
$6.90 |
$8.00 |
| 24 | 504(C) 6250 |
SEALED EXPANSION JOINT | 35.17 | LF |
$259.75 |
$113.00 |
$350.00 |
$178.60 |
| 25 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 241.2 | LF |
$81.77 |
$75.00 |
$85.00 |
$87.25 |
| 26 | 506(A) 1322 |
STRUCTURAL STEEL | 630 | LB |
$4.00 |
$3.60 |
$8.00 |
$2.50 |
| 27 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 4 | EA |
$901.61 |
$1,000.00 |
$400.00 |
$629.65 |
| 28 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 4 | EA |
$1,048.86 |
$1,000.00 |
$400.00 |
$706.75 |
| 29 | 509(A) 1326 |
CLASS AA CONCRETE | 87.8 | CY |
$650.00 |
$585.00 |
$595.00 |
$414.90 |
| 30 | 509(B) 1328 |
CLASS A CONCRETE | 83.86 | CY |
$700.00 |
$585.00 |
$595.00 |
$590.10 |
| 31 | 511(A) 1332 |
REINFORCING STEEL | 30,915 | LB |
$1.00 |
$1.00 |
$1.00 |
$0.9000 |
| 32 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 70.6 | LF |
$37.22 |
$48.00 |
$35.00 |
$34.85 |
| 33 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 226.4 | LF |
$45.00 |
$60.00 |
$45.00 |
$43.90 |
| 34 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 70.6 | LF |
$12.75 |
$10.00 |
$15.50 |
$12.85 |
| 35 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 226.4 | LF |
$20.00 |
$10.00 |
$20.00 |
$12.85 |
| 36 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 37 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 578.36 | TON |
$44.00 |
$40.00 |
$37.00 |
$55.25 |
| 38 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 130.12 | TON |
$37.84 |
$34.00 |
$32.00 |
$77.75 |
| 39 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 64 | LF |
$26.36 |
$25.00 |
$40.00 |
$15.40 |
| 40 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 60 | LF |
$21.38 |
$25.00 |
$40.00 |
$15.00 |
| 41 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$36,510.20 |
$9,500.00 |
$10,000.00 |
$13,550.00 |
| 42 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,738.04 |
$1,700.00 |
$1,525.00 |
$2,725.00 |
| 43 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 4 | EA |
$2,352.49 |
$2,800.00 |
$2,525.00 |
$2,850.00 |
| 44 | 823 8478 |
(SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 90 | SD |
$400.00 |
$50.00 |
$50.00 |
$192.75 |
| 45 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 2,000 | LF |
$0.5600 |
$1.50 |
$1.50 |
$3.20 |
| 46 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 800 | LF |
$26.73 |
$35.00 |
$28.00 |
$28.25 |
| 47 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 800 | LF |
$3.76 |
$7.00 |
$5.00 |
$2.60 |
| 48 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$5,000.00 |
$8,250.00 |
$8,250.00 |
$10,280.00 |
| 49 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$11,670.38 |
$5,928.00 |
$5,500.00 |
$11,400.00 |
| 50 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$1,275.00 |
$2,000.00 |
$3,225.00 |
| 51 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$55,774.00 |
$59,000.00 |
$47,580.00 |
$27,000.00 |