$22.13Avg low bid / LF
$24.77Avg of all bids
$24.55Avg engineer's estimate
254Jobs · 1,033,551.5 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 35 | 178,961.5 | $23.72 | $21.81 |
| 2020 | 88 | 386,350 | $21.67 | $25.29 |
| 2019 | 63 | 284,992.5 | $22.13 | $24.31 |
| 2018 | 68 | 183,247.5 | $21.56 | $27.48 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 18, 2021 | 210347 | DelawareDivision 8 | 4,612.5 LF | $35.00 | C-GAWF CONSTRUCTION, INC. |
| Sep 16, 2021 | 200324 | Osage, Pawnee | 1,806 LF | $20.00 | BECCO CONTRACTORS, INC. |
| Aug 19, 2021 | 210234 | Harper, Woodward | 450 LF | $22.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Aug 19, 2021 | 210149 | Nhpp-260n(054)pm | 717 LF | $20.00 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Aug 19, 2021 | 210241 | SequoyahDivision 1 | 1,755 LF | $19.95 | Treas Construction Inc |
| Aug 19, 2021 | 210149 | Nhpp-260n(054)pm | 2,262.5 LF | $20.00 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Jul 15, 2021 | 190363 | LoveDivision 7 | 7,788 LF | $24.30 | C3 Construction, Inc. |
| Jul 15, 2021 | 210111 | LincolnDivision 3 | 2,640 LF | $14.70 | HASKELL LEMON CONSTRUCTION CO. |
| Jun 17, 2021 | 210181 | Kay, Noble | 662.5 LF | $22.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Jun 17, 2021 | 210190 | PushmatahaDivision 2 | 2,462.5 LF | $25.00 | L & N BRIDGE, LLC |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 1,300 LF | $31.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210148 | PayneDivision 4 | 6,000 LF | $15.00 | BECCO CONTRACTORS, INC. |
| May 20, 2021 | 210129 | BryanDivision 2 | 550 LF | $20.00 | L & N BRIDGE, LLC |
| May 20, 2021 | 210155 | PushmatahaDivision 2 | 280 LF | $15.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 1,450 LF | $31.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Apr 15, 2021 | 210117 | Nhpp-255n(535)pm | 13,765 LF | $10.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Mar 18, 2021 | 210090 | Nhppi-4440(009)pm | 2,312 LF | $45.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Mar 18, 2021 | 210097 | KayDivision 4 | 8,576 LF | $18.10 | WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES |
| Mar 18, 2021 | 210072 | CaddoDivision 7 | 28,205 LF | $40.00 | OVERLAND CORPORATION |
| Mar 18, 2021 | 210060 | OttawaDivision 8 | 2,600 LF | $25.00 | Treas Construction Inc |
| Mar 18, 2021 | 210075 | CarterDivision 7 | 600 LF | $30.00 | OVERLAND CORPORATION |
| Mar 18, 2021 | 210077 | GarvinDivision 3 | 24,800 LF | $23.77 | IHC Scott, INC. |
| Mar 18, 2021 | 210086 | PittsburgDivision 2 | 2,000 LF | $38.00 | Robinson Construction, LLC |
| Feb 18, 2021 | 210070 | WoodwardDivision 6 | 3,775 LF | $17.80 | BRIDGECO CONTRACTORS, INC. |
| Feb 18, 2021 | 210057 | NobleDivision 4 | 900 LF | $11.25 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 18, 2021 | 210061 | PittsburgDivision 2 | 1,475 LF | $34.39 | BRIDGECO CONTRACTORS, INC. |
| Feb 18, 2021 | 210062 | Pontotoc | 8,500 LF | $14.90 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 18, 2021 | 210045 | ClevelandDivision 3 | 2,375 LF | $13.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Feb 18, 2021 | 210068 | TexasDivision 6 | 575 LF | $35.00 | CONCRETE SERVICES CORPORATION |
| Feb 18, 2021 | 190362 | LoveDivision 7 | 3,200 LF | $13.01 | C3 Construction, Inc. |
| Feb 18, 2021 | 210055 | MurrayDivision 7 | 7,438 LF | $38.00 | HUB Construction, Inc. |
| Jan 21, 2021 | 210008 | CaddoDivision 7 | 960 LF | $12.10 | Treas Construction Inc |
| Jan 21, 2021 | 210025 | KingfisherDivision 4 | 2,600 LF | $14.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 210030 | McclainDivision 3 | 14,550 LF | $14.83 | IHC Scott, INC. |
| Jan 21, 2021 | 210035 | Pontotoc | 2,378 LF | $29.10 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 3,400 LF | $16.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 210007 | BeckhamDivision 5 | 3,562.5 LF | $18.67 | C3 Construction, Inc. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 5,679 LF | $16.00 | OVERLAND CORPORATION |
| Nov 19, 2020 | 200343 | BryanDivision 2 | 287.5 LF | $23.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Nov 19, 2020 | 200356 | SeminoleDivision 3 | 2,675 LF | $15.30 | Frontier Bridge, Inc. |
| Nov 19, 2020 | 200346 | ClevelandDivision 3 | 1,888 LF | $28.00 | Redlands Contracting, LLC |
| Nov 19, 2020 | 200358 | Custer, Washita | 500 LF | $11.55 | Caswell Contracting, Inc. |
| Nov 19, 2020 | 200348 | CusterDivision 5 | 1,750 LF | $13.26 | Frontier Bridge, Inc. |
| Nov 19, 2020 | 200339 | BlaineDivision 5 | 400 LF | $25.12 | CORNELL CONSTRUCTION COMPANY, INC. |
| Nov 19, 2020 | 200359 | MccurtainDivision 2 | 1,347 LF | $18.54 | Frontier Bridge, Inc. |
| Nov 19, 2020 | 200349 | GarvinDivision 3 | 1,800 LF | $20.00 | Treas Construction Inc |
| Nov 19, 2020 | 200352 | Leflore | 322 LF | $20.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Nov 19, 2020 | 200355 | RogersDivision 8 | 6,487.5 LF | $46.20 | EMERY SAPP & SONS, INC. |
| Oct 15, 2020 | 200325 | PawneeDivision 8 | 2,100 LF | $25.00 | CONCRETE SERVICES CORPORATION |
| Oct 15, 2020 | 200310 | GarfieldDivision 4 | 600 LF | $20.06 | HASKELL LEMON CONSTRUCTION CO. |
| Oct 15, 2020 | 200077 | PottawatomieDivision 3 | 1,975 LF | $30.00 | OVERLAND CORPORATION |
| Oct 15, 2020 | 200333 | TulsaDivision 8 | 9,525 LF | $10.00 | ACTION SAFETY SUPPLY CO., LLC |
| Oct 15, 2020 | 200321 | OklahomaDivision 4 | 1,480 LF | $20.00 | Built Right Construction, LLC |
| Oct 15, 2020 | 200322 | OsageDivision 8 | 300 LF | $50.50 | BRIDGECO CONTRACTORS, INC. |
| Oct 15, 2020 | 200323 | OsageDivision 8 | 650 LF | $47.50 | BRIDGECO CONTRACTORS, INC. |
| Oct 15, 2020 | 200306 | CanadianDivision 4 | 2,800 LF | $13.39 | Frontier Bridge, Inc. |
| Sep 17, 2020 | 200279 | GradyDivision 7 | 1,750 LF | $25.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Sep 17, 2020 | 200290 | OsageDivision 8 | 1,200 LF | $26.00 | BRIDGECO CONTRACTORS, INC. |
| Sep 17, 2020 | 200034 | SequoyahDivision 1 | 7,207 LF | $23.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Sep 17, 2020 | 200291 | PittsburgDivision 2 | 2,975 LF | $38.03 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Sep 17, 2020 | 200273 | Stp-208b(091)pm | 4,100 LF | $17.80 | OVERLAND CORPORATION |
| Sep 17, 2020 | 200292 | PottawatomieDivision 3 | 5,000 LF | $21.70 | Silver Star Construction Company, Inc. |
| Sep 17, 2020 | 200274 | Carter, Love | 425 LF | $18.00 | Built Right Construction, LLC |
| Sep 17, 2020 | 200200 | McintoshDivision 1 | 55,550 LF | $25.00 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Sep 17, 2020 | 200295 | TulsaDivision 8 | 1,342 LF | $30.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Sep 17, 2020 | 200275 | CimarronDivision 6 | 550 LF | $33.00 | CONCRETE SERVICES CORPORATION |
| Aug 20, 2020 | 200163 | OkfuskeeDivision 3 | 35,750 LF | $12.60 | HASKELL LEMON CONSTRUCTION CO. |
| Aug 20, 2020 | 200230 | LoveDivision 7 | 150 LF | $30.00 | HUB Construction, Inc. |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 33,950 LF | $16.39 | SHERWOOD CONSTRUCTION CO., INC. |
| Jul 23, 2020 | 200260 | AtokaDivision 2 | 600 LF | $45.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jul 23, 2020 | 200108 | Love, Marshall | 4,300 LF | $12.00 | OVERLAND CORPORATION |
| Jul 23, 2020 | 200244 | CaddoDivision 7 | 1,320 LF | $26.25 | Frontier Bridge, Inc. |
| Jul 23, 2020 | 200247 | ClevelandDivision 3 | 212.5 LF | $85.00 | CGC, LLC. |
| Jul 23, 2020 | 190283 | GarvinDivision 3 | 1,650 LF | $11.70 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Jul 23, 2020 | 200250 | GarvinDivision 3 | 1,700 LF | $23.92 | Frontier Bridge, Inc. |
| Jul 23, 2020 | 200061 | DeweyDivision 5 | 4,000 LF | $14.50 | J & R SAND COMPANY, INC. |
| Jul 23, 2020 | 200252 | KayDivision 4 | 675 LF | $37.88 | CONCRETE SERVICES CORPORATION |
| Jun 18, 2020 | 200226 | Caddo, Grady | 625 LF | $23.00 | Built Right Construction, LLC |
| Jun 18, 2020 | 200231 | MarshallDivision 2 | 712.5 LF | $14.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Jun 18, 2020 | 200234 | OklahomaDivision 4 | 1,300 LF | $14.22 | C3 Construction, Inc. |
| Jun 18, 2020 | 200221 | AtokaDivision 2 | 575 LF | $30.00 | HUB Construction, Inc. |
| Jun 18, 2020 | 200235 | OklahomaDivision 4 | 100 LF | $45.00 | K & R BUILDERS, INC. |
| Jun 18, 2020 | 200222 | CanadianDivision 4 | 6,150 LF | $15.00 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200208 | PittsburgDivision 2 | 3,032 LF | $20.00 | DUIT CONSTRUCTION COMPANY, INC. |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 12,812.5 LF | $32.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 190120 | Nhppi-4400-(039)pm | 150 LF | $14.69 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200210 | Coal, Lincoln, Pontotoc | 725 LF | $20.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| May 14, 2020 | 200197 | JohnstonDivision 3 | 2,209 LF | $15.60 | C3 Construction, Inc. |
| May 14, 2020 | 200205 | Canadian, Noble, Oklahoma | 925 LF | $35.00 | PBX Corporation |
| May 14, 2020 | 200022 | OttawaDivision 8 | 600 LF | $20.10 | APAC-CENTRAL, INC. |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 22,500 LF | $12.25 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 190120 | Nhppi-4400-(039)pm | 4,900 LF | $14.69 | SHERWOOD CONSTRUCTION CO., INC. |
| Apr 16, 2020 | 200146 | CreekDivision 8 | 1,425 LF | $28.60 | CONCRETE SERVICES CORPORATION |
| Apr 16, 2020 | 200178 | WashingtonDivision 8 | 1,690 LF | $15.00 | Built Right Construction, LLC |
| Apr 16, 2020 | 200165 | OklahomaDivision 4 | 4,200 LF | $19.50 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Apr 16, 2020 | 200008 | CreekDivision 8 | 800 LF | $21.00 | LOGOS CONSTRUCTION CO., LLC |
| Apr 16, 2020 | 200148 | DelawareDivision 8 | 4,270 LF | $40.00 | C-GAWF CONSTRUCTION, INC. |
| Apr 16, 2020 | 200185 | OklahomaDivision 4 | 4,595.5 LF | $23.10 | Frontier Bridge, Inc. |
| Apr 16, 2020 | 200166 | OsageDivision 8 | 650 LF | $50.00 | LOGOS CONSTRUCTION CO., LLC |
| Apr 16, 2020 | 200079 | SeminoleDivision 3 | 100 LF | $35.30 | THE CUMMINS CONSTRUCTION CO., INC. |
| Apr 16, 2020 | 200216 | BlaineDivision 5 | 765 LF | $48.00 | K & R BUILDERS, INC. |
| Apr 16, 2020 | 200151 | GarfieldDivision 4 | 490 LF | $41.00 | BRIDGECO CONTRACTORS, INC. |
| Apr 16, 2020 | 200167 | Kay, Osage | 2,500 LF | $25.00 | LOGOS CONSTRUCTION CO., LLC |
| Apr 16, 2020 | 190163 | SequoyahDivision 1 | 600 LF | $26.00 | BRIDGECO CONTRACTORS, INC. |
| Apr 16, 2020 | 200152 | HaskellDivision 1 | 1,200 LF | $38.00 | C-GAWF CONSTRUCTION, INC. |
| Apr 16, 2020 | 200173 | TulsaDivision 8 | 425 LF | $25.85 | CONCRETE SERVICES CORPORATION |
| Apr 16, 2020 | 200157 | MarshallDivision 2 | 275 LF | $50.75 | OVERLAND CORPORATION |
| Apr 16, 2020 | 200176 | WagonerDivision 1 | 2,350 LF | $25.00 | BECCO CONTRACTORS, INC. |
| Mar 19, 2020 | 200120 | Pontotoc | 2,687.5 LF | $13.00 | OVERLAND CORPORATION |
| Mar 19, 2020 | 200123 | SequoyahDivision 1 | 500 LF | $25.76 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Mar 19, 2020 | 200132 | CusterDivision 5 | 1,500 LF | $38.00 | SEWELL BROS., INC. |
| Mar 19, 2020 | 200103 | Sbr-020n(047)sb | 1,000 LF | $35.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Mar 19, 2020 | 200136 | MajorDivision 6 | 75 LF | $42.40 | Frontier Bridge, Inc. |
| Mar 19, 2020 | 200103 | Sbr-020n(047)sb | 669 LF | $34.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Feb 20, 2020 | 200062 | EllisDivision 6 | 6,000 LF | $18.00 | J & R SAND COMPANY, INC. |
| Feb 20, 2020 | 200047 | AtokaDivision 2 | 7,350 LF | $24.60 | C3 Construction, Inc. |
| Feb 20, 2020 | 200050 | BeckhamDivision 5 | 350 LF | $27.00 | Frontier Bridge, Inc. |
| Feb 20, 2020 | 200090 | CoalDivision 3 | 1,134 LF | $24.00 | Built Right Construction, LLC |
| Feb 20, 2020 | 200057 | ClevelandDivision 3 | 450 LF | $27.05 | Silver Star Construction Company, Inc. |
| Jan 16, 2020 | 200001 | AlfalfaDivision 6 | 6,250 LF | $37.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200046 | McclainDivision 3 | 24,000 LF | $19.64 | SHERWOOD CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200031 | RogersDivision 8 | 287.5 LF | $30.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Jan 16, 2020 | 200009 | CusterDivision 5 | 1,000 LF | $25.00 | SEWELL BROS., INC. |
| Jan 16, 2020 | 190370 | PittsburgDivision 2 | 23,000 LF | $25.00 | DUIT CONSTRUCTION COMPANY, INC. |
| Jan 16, 2020 | 200036 | TulsaDivision 8 | 460 LF | $25.00 | PBX Corporation |
| Jan 16, 2020 | 200012 | KayDivision 4 | 3,976 LF | $32.12 | LOGOS CONSTRUCTION CO., LLC |
| Jan 16, 2020 | 190352 | GarvinDivision 3 | 9,375 LF | $24.40 | Silver Star Construction Company, Inc. |
| Jan 16, 2020 | 200044 | Stp-257b(038)pm | 3,602 LF | $21.25 | SHERWOOD CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200018 | McintoshDivision 1 | 3,995 LF | $26.25 | L & N BRIDGE, LLC |
| Jan 16, 2020 | 200044 | Stp-257b(038)pm | 3,744 LF | $21.25 | SHERWOOD CONSTRUCTION CO., INC. |
| Nov 14, 2019 | 190341 | CaddoDivision 7 | 1,700 LF | $9.00 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Nov 14, 2019 | 190344 | ComancheDivision 7 | 490 LF | $15.00 | Built Right Construction, LLC |
| Nov 14, 2019 | 190384 | MajorDivision 6 | 1,412.5 LF | $65.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Nov 14, 2019 | 190369 | PittsburgDivision 2 | 2,485 LF | $17.80 | C3 Construction, Inc. |
| Nov 14, 2019 | 190351 | GarfieldDivision 4 | 1,550 LF | $30.00 | LOGOS CONSTRUCTION CO., LLC |
| Nov 14, 2019 | 190389 | TulsaDivision 8 | 213 LF | $17.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Nov 14, 2019 | 190392 | PayneDivision 4 | 400 LF | $75.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Nov 14, 2019 | 190373 | Sbr-264b(066)sb | 395 LF | $25.00 | L & N BRIDGE, LLC |
| Nov 14, 2019 | 190354 | GreerDivision 5 | 975 LF | $31.50 | Frontier Bridge, Inc. |
| Nov 14, 2019 | 190379 | Nhpp-017n(256)pm | 2,775 LF | $29.40 | THE CUMMINS CONSTRUCTION CO., INC. |
| Oct 17, 2019 | 190381 | ClevelandDivision 3 | 525 LF | $15.00 | RESTEK, INC. |
| Oct 17, 2019 | 190275 | Atoka, Bryan | 35,300 LF | $22.00 | DUIT CONSTRUCTION COMPANY, INC. |
| Oct 17, 2019 | 190264 | Stp-264c(063)pm | 1,580 LF | $25.37 | HUB Construction, Inc. |
| Oct 17, 2019 | 190331 | TulsaDivision 8 | 8,425 LF | $6.61 | SHERWOOD CONSTRUCTION CO., INC. |
| Oct 17, 2019 | 180304 | SeminoleDivision 3 | 1,763 LF | $15.51 | OVERLAND CORPORATION |
| Sep 19, 2019 | 190299 | StephensDivision 7 | 562.5 LF | $34.51 | LOGOS CONSTRUCTION CO., LLC |
| Sep 19, 2019 | 190301 | TulsaDivision 8 | 1,100 LF | $22.00 | PBX Corporation |
| Sep 19, 2019 | 190302 | WashitaDivision 5 | 800 LF | $23.00 | Built Right Construction, LLC |
| Sep 19, 2019 | 190278 | CusterDivision 5 | 1,487.5 LF | $12.60 | CASWELL CONSTRUCTION, INC. |
| Sep 19, 2019 | 190337 | TulsaDivision 8 | 600 LF | $35.00 | BECCO CONTRACTORS, INC. |