| 10 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$2,500.00 |
$12,000.00 |
$82,500.00 |
$93,750.00 |
| 20 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$8,500.00 |
$10,000.00 |
$16,500.00 |
$18,750.00 |
| 30 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$2,500.00 |
$7,500.00 |
$5,500.00 |
$6,250.00 |
| 40 | 221(C) 2801 |
TEMPORARY SILT FENCE | 683 | LF |
$8.50 |
$2.99 |
$3.30 |
$6.00 |
| 50 | 221(D) 2803 |
TEMPORARY SEDIMENT FILTER | 4 | EA |
$275.00 |
$395.00 |
$434.50 |
$450.00 |
| 60 | 221(F) 0100 |
TEMPORARY SILT DIKE | 308 | LF |
$15.00 |
$7.95 |
$8.75 |
$10.00 |
| 70 | 230(A) 2806 |
SOLID SLAB SODDING | 3,610.8 | SY |
$5.00 |
$6.95 |
$7.75 |
$15.00 |
| 80 | 411(B) 5940 |
SUPERPAVE, TYPE S3(PG 70-28 OK) | 789.6 | TON |
$125.00 |
$130.00 |
$93.50 |
$110.00 |
| 90 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 94.4 | TON |
$150.00 |
$200.00 |
$220.00 |
$250.00 |
| 100 | 412 5267 |
COLD MILLING PAVEMENT | 2,350 | SY |
$6.00 |
$6.00 |
$5.50 |
$7.00 |
| 110 | 509(B) 0321 |
CLASS A CONCRETE | 188.2 | CY |
$600.00 |
$590.00 |
$990.00 |
$1,125.00 |
| 120 | 511(A) 0332 |
REINFORCING STEEL | 10,701 | LB |
$1.00 |
$1.05 |
$1.65 |
$2.00 |
| 130 | 613(A) 0491 |
18" R.C.PIPE CLASS III | 726 | LF |
$65.00 |
$83.00 |
$93.50 |
$110.00 |
| 140 | 613(M) 7196 |
TYPE A6 CULVERT END TREATMENT | 10 | EA |
$1,200.00 |
$1,300.00 |
$1,320.00 |
$1,500.00 |
| 150 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$15,000.00 |
$150,000.00 |
$162,800.00 |
$185,000.00 |
| 160 | 619(B) 4915 |
REMOVAL OF CONCRETE MEDIAN BARRIER | 1,226.23 | LF |
$20.00 |
$25.00 |
$77.00 |
$90.00 |
| 170 | 619(B) 5190 |
REMOVAL OF CABLE BARRIER | 671 | LF |
$9.00 |
$12.11 |
$10.10 |
$20.00 |
| 180 | 619(C) 0924 |
SAWING PAVEMENT | 940 | LF |
$3.75 |
$7.00 |
$8.80 |
$10.00 |
| 190 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 587.5 | LF |
$22.50 |
$17.73 |
$18.70 |
$30.00 |
| 200 | 623(F) 8300 |
GUARDRAIL TRAIL END TURNDOWN (31") | 2 | EA |
$850.00 |
$970.00 |
$715.00 |
$2,000.00 |
| 210 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 2 | EA |
$2,700.00 |
$2,350.00 |
$2,860.00 |
$5,500.00 |
| 220 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 2 | EA |
$2,000.00 |
$2,150.00 |
$1,760.00 |
$5,000.00 |
| 230 | 627(A) 4317 |
CONCRETE LONGITUDINAL BARRIER, DESIGN 1 | 481.19 | LF |
$120.00 |
$115.00 |
$151.00 |
$175.00 |
| 240 | 627(B) 4410 |
CONCRETE LONGITUDINAL BARRIER END SECTIONS | 1 | EA |
$750.00 |
$850.00 |
$8,250.00 |
$9,500.00 |
| 250 | 509(D) 1331 |
CLASS C CONCRETE | 88.79 | CY |
$450.00 |
$450.00 |
$660.00 |
$750.00 |
| 260 | 511(A) 1332 |
REINFORCING STEEL | 3,653 | LB |
$1.15 |
$1.00 |
$1.65 |
$2.00 |
| 270 | 516(A) 6096 |
DRILLED SHAFTS 60" DIAMETER | 1,362 | LF |
$1,250.00 |
$775.00 |
$800.00 |
$1,000.00 |
| 280 | 628(B) 5125 |
HIGH-TENSION CABLE BARRIER(TL-4) | 620 | LF |
$15.50 |
$13.20 |
$31.50 |
$25.00 |
| 290 | 628(C) 5110 |
END ANCHORS | 6 | EA |
$7,500.00 |
$6,700.00 |
$3,300.00 |
$5,000.00 |
| 300 | 628(F) 5185 |
(PL)HIGH TENSION CABLE BARRIER - RE-TENSIONING | 5 | EA |
$350.00 |
$600.00 |
$8,415.00 |
$500.00 |
| 310 | 805(A) 8716 |
(PL)REMOVAL OF OVERHEAD SIGN STRUCTURE | 20 | EA |
$18,500.00 |
$7,500.00 |
$5,000.00 |
$12,500.00 |
| 320 | 805(A) 8724 |
(PL)REMOVAL OF EXISTING SIGNS | 4 | EA |
$45.00 |
$3,900.00 |
$375.00 |
$500.00 |
| 330 | 805(D) 8744 |
(PL)REMOVE & RESET LIGHT POLE | 1 | EA |
$4,000.00 |
$17,275.00 |
$4,700.00 |
$5,000.00 |
| 340 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 132 | SF |
$20.00 |
$25.00 |
$27.50 |
$22.00 |
| 350 | 850(B) 8114 |
EXTRUDED ALUMINUM PANEL SIGNS(OVERHEAD SIGNS) | 8,498.5 | SF |
$32.50 |
$26.00 |
$49.50 |
$32.00 |
| 360 | 852(D) 0295 |
OVHD.SN.STR., MONOTUBE TYPE B 65' | 2 | EA |
$85,000.00 |
$100,000.00 |
$104,330.00 |
$126,000.00 |
| 370 | 852(D) 0300 |
OVHD.SN.STR., MONOTUBE TYPE B 70' | 1 | EA |
$100,000.00 |
$103,750.00 |
$117,250.00 |
$131,000.00 |
| 380 | 852(D) 0310 |
OVHD.SN.STR., MONOTUBE TYPE B 80' | 4 | EA |
$120,000.00 |
$110,500.00 |
$117,500.00 |
$144,000.00 |
| 390 | 852(D) 0315 |
OVHD.SN.STR., MONOTUBE TYPE B 85' | 1 | EA |
$125,000.00 |
$114,650.00 |
$122,250.00 |
$151,000.00 |
| 400 | 852(D) 0320 |
OVHD.SN.STR., MONOTUBE TYPE B 90' | 1 | EA |
$130,000.00 |
$118,900.00 |
$125,000.00 |
$155,000.00 |
| 410 | 852(D) 0325 |
OVHD.SN.STR., MONOTUBE TYPE B 95' | 3 | EA |
$135,000.00 |
$124,850.00 |
$132,450.00 |
$165,000.00 |
| 420 | 852(D) 0330 |
OVHD.SN.STR., MONOTUBE TYPE B 100' | 1 | EA |
$140,000.00 |
$130,000.00 |
$133,100.00 |
$175,000.00 |
| 430 | 852(D) 0335 |
OVHD.SN.STR., MONOTUBE TYPE B 105' | 1 | EA |
$145,000.00 |
$132,500.00 |
$134,000.00 |
$185,000.00 |
| 440 | 852(D) 0340 |
OVHD.SN.STR., MONOTUBE TYPE B 110' | 2 | EA |
$150,000.00 |
$142,000.00 |
$152,100.00 |
$195,000.00 |
| 450 | 852(E) 0500 |
OVHD.SN.STR., MONOTUBE TYPE C | 6 | EA |
$65,000.00 |
$67,500.00 |
$55,000.00 |
$80,000.00 |
| 460 | 856(A) 8535 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 42,336 | LF |
$0.6000 |
$0.4300 |
$2.20 |
$2.50 |
| 470 | 856(A) 8540 |
TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) | 3,536 | LF |
$1.25 |
$0.5800 |
$3.30 |
$5.00 |
| 480 | 856(A) 8548 |
TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 1,300 | LF |
$2.25 |
$1.00 |
$4.40 |
$8.00 |
| 490 | 870(A) 8011 |
SAND FILLED IMPACT ATTENUATION MODULE | 247 | EA |
$350.00 |
$400.00 |
$423.50 |
$450.00 |
| 500 | 870(B) 8012 |
REPLACEMENT IMPACT ATTENUATION | 247 | EA |
$315.00 |
$385.00 |
$357.50 |
$375.00 |
| 510 | 857(C) 8851 |
REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 87,491 | LF |
$0.6500 |
$0.7600 |
$1.10 |
$2.00 |
| 520 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 47,211 | LF |
$0.3000 |
$0.2700 |
$0.4000 |
$2.00 |
| 530 | 871(B) 8705 |
(SP)CONST.ZONE IMPACT ATTEN. | 315 | SD |
$6.00 |
$100.00 |
$27.50 |
$35.00 |
| 540 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 9,525 | LF |
$30.00 |
$10.00 |
$27.50 |
$25.00 |
| 550 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 8,975 | LF |
$5.00 |
$0.5000 |
$19.80 |
$18.00 |
| 560 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 28,560 | SD |
$0.3500 |
$0.0200 |
$0.1100 |
$1.25 |
| 570 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 26,880 | SD |
$0.5500 |
$0.0200 |
$0.1100 |
$2.25 |
| 580 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 20,475 | SD |
$1.05 |
$0.0200 |
$1.10 |
$5.50 |
| 590 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 15,120 | SD |
$0.7500 |
$0.0500 |
$0.5500 |
$2.00 |
| 600 | 880(C) 8848 |
WING BARRICADES | 2,100 | SD |
$1.00 |
$6.00 |
$0.5500 |
$2.00 |
| 610 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 46,410 | SD |
$0.2000 |
$0.0200 |
$0.3000 |
$2.00 |
| 620 | 880(F) 8878 |
DRUMS | 131,145 | SD |
$0.3500 |
$0.0200 |
$0.5500 |
$1.50 |
| 630 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$34,000.00 |
$15,825.00 |
$25,000.00 |
$65,000.00 |
| 640 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$7,500.00 |
$10,000.00 |
$5,000.00 |
$9,000.00 |
| 650 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$325,300.00 |
$268,014.84 |
$400,000.00 |
$735,000.00 |
| 660 | 852(D) 0400 |
POWDER COAT TYPE B1 | 2 | EA |
$9,000.00 |
$15,600.00 |
$12,000.00 |
$13,200.00 |
| 670 | 852(D) 0405 |
POWDER COAT TYPE B2 | 1 | EA |
$12,000.00 |
$17,400.00 |
$14,500.00 |
$17,700.00 |
| 680 | 852(E) 0600 |
POWDER COAT TYPE C | 3 | EA |
$6,000.00 |
$6,100.00 |
$5,000.00 |
$6,500.00 |