$1.41Avg low bid / LF
$1.54Avg of all bids
$1.27Avg engineer's estimate
130Jobs · 343,269.16 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 24 | 53,168.36 | $1.46 | $1.57 |
| 2020 | 40 | 125,558.8 | $1.45 | $1.87 |
| 2019 | 38 | 122,293 | $1.34 | $1.25 |
| 2018 | 28 | 42,249 | $1.43 | $1.53 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 19, 2021 | 210149 | Nhpp-260n(054)pm | 1,090.36 LF | $5.39 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Jul 15, 2021 | 210228 | KayDivision 4 | 10,000 LF | $0.8400 | HASKELL LEMON CONSTRUCTION CO. |
| Jun 17, 2021 | 210195 | TulsaDivision 8 | 324 LF | $2.05 | Paragon Contractors, LLC |
| Jun 17, 2021 | 210173 | GarvinDivision 3 | 380 LF | $1.00 | OVERLAND CORPORATION |
| Jun 17, 2021 | 210178 | Cleveland, Mcclain | 6,092 LF | $1.05 | Silver Star Construction Company, Inc. |
| May 20, 2021 | 210156 | SeminoleDivision 3 | 408 LF | $1.71 | Rosscon, LLC |
| May 20, 2021 | 210136 | HughesDivision 3 | 428 LF | $2.50 | C-GAWF CONSTRUCTION, INC. |
| May 20, 2021 | 210160 | Muskogee, Wagoner | 1,200 LF | $1.10 | BECCO CONTRACTORS, INC. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 720 LF | $2.10 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 1,608 LF | $2.06 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210148 | PayneDivision 4 | 400 LF | $2.00 | BECCO CONTRACTORS, INC. |
| Mar 18, 2021 | 210060 | OttawaDivision 8 | 425 LF | $2.10 | Treas Construction Inc |
| Mar 18, 2021 | 210097 | KayDivision 4 | 830 LF | $2.00 | WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES |
| Mar 18, 2021 | 210073 | CanadianDivision 4 | 3,000 LF | $1.00 | HASKELL LEMON CONSTRUCTION CO. |
| Mar 18, 2021 | 210077 | GarvinDivision 3 | 3,000 LF | $0.9100 | IHC Scott, INC. |
| Mar 18, 2021 | 210086 | PittsburgDivision 2 | 1,753 LF | $2.40 | Robinson Construction, LLC |
| Mar 18, 2021 | 210090 | Nhppi-4440(009)pm | 6,150 LF | $1.87 | SHERWOOD CONSTRUCTION CO., INC. |
| Mar 18, 2021 | 210090 | Nhppi-4440(009)pm | 60 LF | $22.45 | SHERWOOD CONSTRUCTION CO., INC. |
| Feb 18, 2021 | 210053 | MajorDivision 6 | 660 LF | $0.5500 | THE CUMMINS CONSTRUCTION CO., INC. |
| Feb 18, 2021 | 210057 | NobleDivision 4 | 5,000 LF | $0.8000 | HASKELL LEMON CONSTRUCTION CO. |
| Jan 21, 2021 | 210025 | KingfisherDivision 4 | 210 LF | $1.55 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 210030 | McclainDivision 3 | 2,800 LF | $1.81 | IHC Scott, INC. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 1,160 LF | $2.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 210031 | OklahomaDivision 4 | 560 LF | $1.70 | SCHWARZ PAVING CO., INC. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 850 LF | $2.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 210007 | BeckhamDivision 5 | 460 LF | $1.29 | C3 Construction, Inc. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 2,500 LF | $2.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 210024 | KayDivision 4 | 1,100 LF | $1.25 | Evans & Associates Construction Co., Inc. |
| Nov 19, 2020 | 200355 | RogersDivision 8 | 1,751 LF | $1.05 | EMERY SAPP & SONS, INC. |
| Nov 19, 2020 | 200346 | ClevelandDivision 3 | 2,102 LF | $2.10 | Redlands Contracting, LLC |
| Oct 15, 2020 | 200333 | TulsaDivision 8 | 3,536 LF | $0.5800 | ACTION SAFETY SUPPLY CO., LLC |
| Oct 15, 2020 | 200318 | McintoshDivision 1 | 562 LF | $4.13 | C-P INTEGRATED SERVICES, INC. |
| Oct 15, 2020 | 200320 | OklahomaDivision 4 | 4,681 LF | $2.00 | SAC Services, Inc. |
| Sep 17, 2020 | 200174 | TulsaDivision 8 | 350 LF | $3.25 | CROSSLAND HEAVY CONTRACTORS INC. |
| Sep 17, 2020 | 200289 | OklahomaDivision 4 | 170 LF | $7.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Sep 17, 2020 | 200200 | McintoshDivision 1 | 4,881 LF | $1.00 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Sep 17, 2020 | 200291 | PittsburgDivision 2 | 6,008 LF | $1.50 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Aug 20, 2020 | 200163 | OkfuskeeDivision 3 | 3,800 LF | $0.8700 | HASKELL LEMON CONSTRUCTION CO. |
| Jul 23, 2020 | 200259 | WagonerDivision 1 | 105 LF | $1.07 | APAC-CENTRAL, INC. |
| Jul 23, 2020 | 200261 | Pontotoc | 485 LF | $1.05 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jul 23, 2020 | 200247 | ClevelandDivision 3 | 790 LF | $1.85 | CGC, LLC. |
| Jun 18, 2020 | 200234 | OklahomaDivision 4 | 530 LF | $2.00 | C3 Construction, Inc. |
| Jun 18, 2020 | 200238 | WagonerDivision 1 | 300 LF | $2.30 | TRAFFIC & LIGHTING SYSTEMS, LLC |
| Jun 18, 2020 | 200222 | CanadianDivision 4 | 2,785 LF | $2.30 | SHERWOOD CONSTRUCTION CO., INC. |
| Jun 18, 2020 | 200228 | Leflore | 4,600 LF | $1.20 | Robinson Construction, LLC |
| May 14, 2020 | 190120 | Nhppi-4400-(039)pm | 21,000 LF | $2.38 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 11,145 LF | $1.05 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 1,951 LF | $1.40 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Apr 16, 2020 | 200075 | OklahomaDivision 4 | 606 LF | $2.50 | SAC Services, Inc. |
| Apr 16, 2020 | 200175 | WagonerDivision 1 | 950 LF | $1.00 | APAC-CENTRAL, INC. |
| Apr 16, 2020 | 200154 | KayDivision 4 | 480.8 LF | $6.33 | Lopp Construction, LLC |
| Apr 16, 2020 | 200157 | MarshallDivision 2 | 3,100 LF | $1.08 | OVERLAND CORPORATION |
| Mar 19, 2020 | 200130 | Ssr-273n(054)sr | 388 LF | $2.00 | Rosscon, LLC |
| Mar 19, 2020 | 190198 | KayDivision 4 | 1,566 LF | $2.00 | Evans & Associates Construction Co., Inc. |
| Mar 19, 2020 | 200132 | CusterDivision 5 | 460 LF | $2.20 | SEWELL BROS., INC. |
| Mar 19, 2020 | 200095 | AtokaDivision 2 | 4,000 LF | $1.60 | OVERLAND CORPORATION |
| Mar 19, 2020 | 200136 | MajorDivision 6 | 196 LF | $0.9500 | Frontier Bridge, Inc. |
| Mar 19, 2020 | 200096 | BryanDivision 2 | 3,500 LF | $1.55 | OVERLAND CORPORATION |
| Mar 19, 2020 | 200099 | CanadianDivision 4 | 500 LF | $2.00 | Atlas Paving Company |
| Mar 19, 2020 | 200124 | Jefferson, Love, Stephens | 22,000 LF | $0.3100 | Direct Traffic Control, Inc. |
| Feb 20, 2020 | 200050 | BeckhamDivision 5 | 100 LF | $3.24 | Frontier Bridge, Inc. |
| Feb 20, 2020 | 200058 | CoalDivision 3 | 210 LF | $4.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Feb 20, 2020 | 200067 | KayDivision 4 | 2,000 LF | $1.95 | Evans & Associates Construction Co., Inc. |
| Feb 20, 2020 | 200071 | LoganDivision 4 | 400 LF | $1.50 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Jan 16, 2020 | 190356 | KayDivision 4 | 400 LF | $3.30 | Evans & Associates Construction Co., Inc. |
| Jan 16, 2020 | 200045 | JohnstonDivision 3 | 3,563 LF | $1.21 | C3 Construction, Inc. |
| Jan 16, 2020 | 200001 | AlfalfaDivision 6 | 307 LF | $2.30 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200015 | Ssr-242b(074)sr | 2,600 LF | $2.75 | HASKELL LEMON CONSTRUCTION CO. |
| Jan 16, 2020 | 200015 | Ssr-242b(074)sr | 3,700 LF | $0.9500 | HASKELL LEMON CONSTRUCTION CO. |
| Jan 16, 2020 | 200017 | MccurtainDivision 2 | 3,000 LF | $2.10 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 14, 2019 | 190379 | Nhpp-017n(256)pm | 575 LF | $0.8000 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 14, 2019 | 190383 | CimarronDivision 6 | 2,535 LF | $2.60 | IHC Scott, INC. |
| Nov 14, 2019 | 190388 | MuskogeeDivision 1 | 182 LF | $7.00 | Rosscon, LLC |
| Nov 14, 2019 | 190389 | TulsaDivision 8 | 1,728 LF | $2.30 | CROSSLAND HEAVY CONTRACTORS INC. |
| Nov 14, 2019 | 190109 | CanadianDivision 4 | 220 LF | $1.05 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Oct 17, 2019 | 190323 | Nhpp-255n(489)eh | 324 LF | $4.75 | CROSSLAND HEAVY CONTRACTORS INC. |
| Oct 17, 2019 | 190323 | Nhpp-255n(489)eh | 216 LF | $4.75 | CROSSLAND HEAVY CONTRACTORS INC. |
| Oct 17, 2019 | 190325 | OklahomaDivision 4 | 3,498 LF | $6.00 | Midstate Traffic Control, Inc. |
| Oct 17, 2019 | 190326 | OklahomaDivision 4 | 1,742 LF | $0.4500 | ACTION SAFETY SUPPLY CO., LLC |
| Oct 17, 2019 | 190331 | TulsaDivision 8 | 2,475 LF | $1.80 | SHERWOOD CONSTRUCTION CO., INC. |
| Oct 17, 2019 | 190275 | Atoka, Bryan | 2,530 LF | $1.07 | DUIT CONSTRUCTION COMPANY, INC. |
| Sep 19, 2019 | 190216 | McclainDivision 3 | 1,100 LF | $0.6500 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Jul 25, 2019 | 190215 | MarshallDivision 2 | 580 LF | $1.05 | OVERLAND CORPORATION |
| Jul 25, 2019 | 190124 | OklahomaDivision 4 | 1,056 LF | $2.00 | TRAFFIC SIGNALS, INC. |
| Jul 25, 2019 | 190270 | AlfalfaDivision 6 | 700 LF | $2.00 | Venture Corporation dba VCO Paving |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 18,780 LF | $1.07 | DUIT CONSTRUCTION COMPANY, INC. |
| Jun 20, 2019 | 190182 | OkfuskeeDivision 3 | 1,730 LF | $2.10 | HASKELL LEMON CONSTRUCTION CO. |
| Jun 20, 2019 | 190016 | McintoshDivision 1 | 5,438 LF | $0.9100 | OBC, INC. |
| Jun 20, 2019 | 190159 | OklahomaDivision 4 | 1,200 LF | $1.20 | TRAFFIC SIGNALS, INC. |
| Jun 20, 2019 | 190190 | AtokaDivision 2 | 350 LF | $0.6500 | APAC-CENTRAL, INC. |
| Jun 20, 2019 | 190195 | Stp-214b(069)ag | 77 LF | $5.30 | Silver Star Construction Company, Inc. |
| May 16, 2019 | 190086 | Adair, Cherokee, Muskogee, Okmulgee, Sequoyah, Wagoner | 37,597 LF | $1.00 | Direct Traffic Control, Inc. |
| May 16, 2019 | 190183 | OklahomaDivision 4 | 2,048 LF | $2.18 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| May 16, 2019 | 190153 | LincolnDivision 3 | 130 LF | $2.04 | LOGOS CONSTRUCTION CO., LLC |
| May 16, 2019 | 190186 | Nhppi-4000-(075)pm | 8,188 LF | $0.8500 | DUIT CONSTRUCTION COMPANY, INC. |
| May 16, 2019 | 190130 | Stp-259b(034)ss | 400 LF | $1.50 | Bridges, Inc. DBA Scudder Bridge Co. |
| May 16, 2019 | 190174 | ClevelandDivision 3 | 198 LF | $0.6000 | CROSSLAND HEAVY CONTRACTORS INC. |
| May 16, 2019 | 190177 | KingfisherDivision 4 | 100 LF | $1.21 | SCHIRALLI CONSTRUCTION CORP. |
| Apr 18, 2019 | 190151 | Caddo, Grady | 80 LF | $5.00 | CGC, LLC. |
| Apr 18, 2019 | 190099 | TulsaDivision 8 | 216 LF | $2.60 | Tri Star Construction Arkansas, LLC |
| Apr 18, 2019 | 190187 | PottawatomieDivision 3 | 4,500 LF | $0.5500 | Rosscon, LLC |
| Mar 14, 2019 | 190133 | RogersDivision 8 | 4,775 LF | $1.09 | SHERWOOD CONSTRUCTION CO., INC. |
| Feb 14, 2019 | 190097 | Nhpp-008n(090)fp | 2,272 LF | $0.4700 | J & R SAND COMPANY, INC. |
| Feb 14, 2019 | 190098 | TulsaDivision 8 | 755 LF | $1.50 | PBX Corporation |
| Feb 14, 2019 | 190100 | Stp-205b(076)pm | 8,708 LF | $2.14 | Frontier Bridge, Inc. |
| Jan 17, 2019 | 180294 | OklahomaDivision 4 | 700 LF | $1.93 | RESTEK, INC. |
| Jan 17, 2019 | 190038 | Ssr-219b(068)sr | 200 LF | $3.00 | BECCO CONTRACTORS, INC. |
| Jan 17, 2019 | 190044 | GrantDivision 4 | 4,000 LF | $0.5000 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 17, 2019 | 190061 | TexasDivision 6 | 390 LF | $1.50 | J & R SAND COMPANY, INC. |
| Nov 15, 2018 | 180310 | Creek, Tulsa | 2,660 LF | $2.42 | B & B CONSTRUCTION SERVICE J.T., INC. |
| Sep 20, 2018 | 180280 | CraigDivision 8 | 160 LF | $3.50 | CROSSLAND HEAVY CONTRACTORS INC. |
| Sep 20, 2018 | 180288 | Hsipg-240n(068)ad | 250 LF | $4.00 | JOB CONSTRUCTION CO., INC. |
| Sep 20, 2018 | 180307 | Ssp-272n(206)pm | 656 LF | $4.00 | BECCO CONTRACTORS, INC. |
| Sep 20, 2018 | 180307 | Ssp-272n(206)pm | 348 LF | $4.00 | BECCO CONTRACTORS, INC. |
| Aug 16, 2018 | 180020 | OklahomaDivision 4 | 3,700 LF | $2.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Aug 16, 2018 | 180261 | ClevelandDivision 3 | 278 LF | $2.68 | C3 Construction, Inc. |
| Aug 16, 2018 | 180263 | GarvinDivision 3 | 150 LF | $2.58 | Allen Contracting, Inc. |
| Jul 19, 2018 | 180251 | Nhppi-4000-(064)pm | 3,928 LF | $1.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Jul 19, 2018 | 180253 | Nhpp-272n(245)pm | 2,425 LF | $2.00 | BECCO CONTRACTORS, INC. |
| Jun 14, 2018 | 180230 | WashingtonDivision 8 | 800 LF | $1.75 | Keystone Services, Inc. |
| Jun 14, 2018 | 180127 | ClevelandDivision 3 | 4,497 LF | $0.6500 | Silver Star Construction Company, Inc. |
| Jun 14, 2018 | 180229 | Nhppi-4440-(007)pm | 8,340 LF | $1.10 | SHERWOOD CONSTRUCTION CO., INC. |
| May 17, 2018 | 180132 | GarfieldDivision 4 | 150 LF | $2.00 | Bridges, Inc. DBA Scudder Bridge Co. |
| Apr 19, 2018 | 180101 | OklahomaDivision 4 | 280 LF | $5.45 | HASKELL LEMON CONSTRUCTION CO. |
| Apr 19, 2018 | 180170 | McclainDivision 3 | 280 LF | $2.50 | Midstate Traffic Control, Inc. |
| Apr 19, 2018 | 180176 | PayneDivision 4 | 1,000 LF | $1.00 | BECCO CONTRACTORS, INC. |
| Mar 15, 2018 | 180062 | OsageDivision 8 | 430 LF | $0.4000 | APAC-CENTRAL, INC. |
| Mar 15, 2018 | 180148 | TulsaDivision 8 | 1,110 LF | $2.29 | SHERWOOD CONSTRUCTION CO., INC. |
| Mar 15, 2018 | 180122 | Acstp-277d(044)ur | 1,506 LF | $0.7000 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 15, 2018 | 180122 | Acstp-277d(044)ur | 676 LF | $0.5100 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 15, 2018 | 180129 | ComancheDivision 7 | 1,000 LF | $2.25 | Redlands Contracting, LLC |
| Feb 15, 2018 | 180099 | OklahomaDivision 4 | 340 LF | $3.60 | RUDY CONSTRUCTION CO. |
| Feb 15, 2018 | 180086 | GarvinDivision 3 | 621 LF | $1.05 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Feb 15, 2018 | 180089 | Nhpp-020n(044)3p | 1,150 LF | $0.4000 | CORNELL CONSTRUCTION COMPANY, INC. |
| Feb 15, 2018 | 180089 | Nhpp-020n(044)3p | 410 LF | $0.4000 | CORNELL CONSTRUCTION COMPANY, INC. |
| Jan 18, 2018 | 180045 | Ellis, Woodward | 244 LF | $0.6000 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 18, 2018 | 180008 | Ssr-228b(014)sr | 1,000 LF | $0.4300 | CASWELL CONSTRUCTION, INC. |
| Jan 18, 2018 | 180015 | McintoshDivision 1 | 800 LF | $0.9200 | GLOVER & ASSOCIATES, INC. |
| Jan 18, 2018 | 180030 | RogersDivision 8 | 1,575 LF | $1.10 | BECCO CONTRACTORS, INC. |
| Jan 18, 2018 | 180040 | ChoctawDivision 2 | 850 LF | $2.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 18, 2018 | 180008 | Ssr-228b(014)sr | 635 LF | $0.4300 | CASWELL CONSTRUCTION, INC. |