| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$7,000.00 |
$6,700.00 |
$5,000.00 |
$22,486.55 |
$8,500.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 2,310 | CY |
$10.60 |
$13.00 |
$15.00 |
$15.00 |
$27.50 |
| 3 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$10,000.00 |
$12,000.00 |
$8,000.00 |
$20,000.00 |
$23,000.00 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,500 | LF |
$3.30 |
$1.50 |
$2.00 |
$1.75 |
$3.00 |
| 5 | 221(H) 0450 |
(PL)TEMPORARY INLET SEDIMENT FILTER | 12 | EA |
$227.60 |
$138.00 |
$160.00 |
$105.00 |
$180.00 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 5,839 | SY |
$2.70 |
$2.50 |
$3.25 |
$4.00 |
$7.00 |
| 7 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 2,079 | CY |
$42.40 |
$40.00 |
$45.00 |
$44.00 |
$56.50 |
| 8 | 310(B) 0149 |
SUBGRADE, METHOD B | 8,420 | SY |
$1.80 |
$1.40 |
$2.00 |
$0.0100 |
$1.95 |
| 9 | 325 5271 |
SEPARATOR FABRIC | 9,445 | SY |
$1.30 |
$1.50 |
$1.50 |
$1.00 |
$1.65 |
| 10 | 407(B) 0250 |
TACK COAT | 800 | GAL |
$3.70 |
$3.60 |
$3.50 |
$3.85 |
$2.75 |
| 11 | 411(B) 5940 |
SUPERPAVE, TYPE S3(PG 70-28 OK) | 1,015 | TON |
$83.90 |
$88.00 |
$78.00 |
$97.00 |
$99.80 |
| 12 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 1,354 | TON |
$73.70 |
$77.00 |
$68.00 |
$79.00 |
$83.50 |
| 13 | 411(C) 5950 |
SUPERPAVE, TYPE S4(PG 76-28 OK) | 677 | TON |
$105.50 |
$112.00 |
$109.00 |
$125.00 |
$113.00 |
| 14 | 414(B) 5725 |
DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 2,669 | SY |
$25.50 |
$22.00 |
$36.00 |
$17.25 |
$38.25 |
| 15 | 414(G) 5275 |
P.C. CONCRETE FOR PAVEMENT | 741 | CY |
$124.70 |
$148.00 |
$150.00 |
$170.00 |
$130.00 |
| 16 | 609(A) 0300 |
CONCRETE CURB (6" BARRIER-INTEGRAL) | 1,324 | LF |
$6.90 |
$15.00 |
$12.00 |
$19.00 |
$25.00 |
| 17 | 610(A) 0602 |
4" CONCRETE SIDEWALK | 32 | SY |
$64.40 |
$76.00 |
$55.00 |
$110.00 |
$290.00 |
| 18 | 610(B) 0604 |
6" CONCRETE DRIVEWAY | 81 | SY |
$56.90 |
$69.00 |
$70.00 |
$56.00 |
$85.00 |
| 19 | 611(A) 2659 |
MANHOLE (6' DIAMETER) | 10 | EA |
$5,000.00 |
$4,000.00 |
$4,500.00 |
$4,150.00 |
$6,000.00 |
| 20 | 611(C) 4215 |
REPLACEMENT OF MANHOLE FRAME & COVER | 10 | EA |
$600.00 |
$618.00 |
$300.00 |
$460.00 |
$1,100.00 |
| 21 | 611(G) 5112 |
INLET CI DES. 2 (STD) | 1 | EA |
$3,252.80 |
$3,340.00 |
$3,600.00 |
$4,600.00 |
$4,200.00 |
| 22 | 611(G) 5113 |
INLET CI DES. 2 (B) | 2 | EA |
$3,816.80 |
$4,169.00 |
$4,400.00 |
$5,100.00 |
$5,100.00 |
| 23 | 611(G) 5115 |
INLET CI DES. 2 (D) | 6 | EA |
$4,664.30 |
$4,900.00 |
$5,500.00 |
$6,800.00 |
$6,200.00 |
| 24 | 611(G) 5705 |
INLET CDI RCP DES. 2 | 1 | EA |
$2,791.00 |
$3,177.00 |
$2,300.00 |
$2,800.00 |
$3,100.00 |
| 25 | 611(G) 6000 |
INLET (SMD-TYPE 1) | 10 | EA |
$2,635.90 |
$3,000.00 |
$3,500.00 |
$3,500.00 |
$3,300.00 |
| 26 | 611(G) 6002 |
INLET (SMD-TYPE 2) | 4 | EA |
$2,591.80 |
$2,097.00 |
$3,000.00 |
$3,500.00 |
$3,200.00 |
| 27 | 611(H) 5196 |
ADDITIONAL DEPTH IN INLET | 66 | VF |
$500.00 |
$477.00 |
$500.00 |
$150.00 |
$275.00 |
| 28 | 611(H) 5537 |
ADD'L DEPTH IN INLET CDI RCB DES. 2 | 4 | VF |
$190.00 |
$499.00 |
$480.00 |
$115.00 |
$250.00 |
| 29 | 611(I) 4489 |
REPLACEMENT OF INLET FRM&GRT (SSIF-FRM,CIG-GRT-RVG-F) | 16 | EA |
$1,000.00 |
$746.00 |
$440.00 |
$440.00 |
$500.00 |
| 30 | 611(M) 4488 |
REPLACEMENT OF CAST IRON HOOD | 44 | EA |
$800.00 |
$351.00 |
$225.00 |
$226.00 |
$300.00 |
| 31 | 612(A) 0641 |
MANHOLES ADJUST TO GRADE | 2 | EA |
$795.30 |
$933.00 |
$1,000.00 |
$945.00 |
$1,100.00 |
| 32 | 612(C) 0645 |
INLET ADJUST TO GRADE | 4 | EA |
$700.00 |
$933.00 |
$3,500.00 |
$1,950.00 |
$1,000.00 |
| 33 | 613(A) 0491 |
18" R.C.PIPE CLASS III | 312 | LF |
$53.50 |
$66.00 |
$100.00 |
$95.00 |
$89.65 |
| 34 | 613(A) 0492 |
24" R.C.PIPE CLASS III | 31 | LF |
$64.80 |
$88.00 |
$100.00 |
$115.00 |
$104.00 |
| 35 | 613(A) 0494 |
36" R.C.PIPE CLASS III | 312 | LF |
$105.00 |
$120.00 |
$200.00 |
$175.00 |
$139.50 |
| 36 | 613(A) 0495 |
42" R.C.PIPE CLASS III | 309 | LF |
$125.90 |
$140.00 |
$220.00 |
$225.00 |
$165.00 |
| 37 | 613(Y) 0100 |
(PL)VIDEO INSPECTION OF CONDUIT | 1 | LF |
$15,000.00 |
$8,000.00 |
$3,000.00 |
$10.00 |
$2,500.00 |
| 38 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$20,000.00 |
$24,000.00 |
$10,000.00 |
$41,400.00 |
$5,000.00 |
| 39 | 619(B) 4727 |
REMOVAL OF CONCRETE PAVEMENT | 9,800 | SY |
$7.30 |
$7.00 |
$10.00 |
$6.85 |
$5.50 |
| 40 | 619(B) 4766 |
REMOVAL OF CONCRETE DRIVEWAY | 81 | SY |
$7.50 |
$9.00 |
$10.00 |
$5.60 |
$12.00 |
| 41 | 629(E) 5048 |
REMOVE AND RESET MAILBOX | 1 | EA |
$194.30 |
$130.00 |
$125.00 |
$180.00 |
$250.00 |
| 42 | 802(B) 8334 |
1" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 25 | LF |
$4.60 |
$9.80 |
$10.00 |
$9.15 |
$10.00 |
| 43 | 802(B) 8342 |
2" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 70 | LF |
$11.70 |
$11.10 |
$25.00 |
$13.90 |
$15.00 |
| 44 | 802(B) 8346 |
3" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 220 | LF |
$14.60 |
$15.70 |
$35.00 |
$54.00 |
$45.00 |
| 45 | 803(A) 8065 |
PULL BOX(SIZE I) | 3 | EA |
$504.60 |
$980.90 |
$665.00 |
$1,185.00 |
$900.00 |
| 46 | 803(A) 8066 |
PULL BOX(SIZE II) | 1 | EA |
$567.80 |
$1,137.90 |
$775.00 |
$1,235.00 |
$1,000.00 |
| 47 | 804(A) 2915 |
STRUCTURAL CONCRETE | 13 | CY |
$707.40 |
$294.30 |
$742.00 |
$1,460.00 |
$1,200.00 |
| 48 | 804(B) 2916 |
REINFORCING STEEL | 2,000 | LB |
$1.90 |
$2.30 |
$1.98 |
$2.85 |
$2.10 |
| 49 | 806(A) 8333 |
32'MH POLE 40'TS & 15'LMA(G.STL.) | 1 | EA |
$12,000.00 |
$19,618.70 |
$15,750.00 |
$22,000.00 |
$19,750.00 |
| 50 | 806(A) 8334 |
32'MH POLE 35'TS & 15'LMA(G.STL.) | 2 | EA |
$10,000.00 |
$17,002.80 |
$15,500.00 |
$21,000.00 |
$18,750.00 |
| 51 | 806(A) 8338 |
32'MH POLE 30'TS & 15'LMA(G.STL.) | 1 | EA |
$8,000.00 |
$15,694.90 |
$15,250.00 |
$20,000.00 |
$18,500.00 |
| 52 | 809(A) 8090 |
ROADWAY LUMINAIRE | 4 | EA |
$913.90 |
$3,269.80 |
$540.00 |
$1,000.00 |
$750.00 |
| 53 | 811 8040 |
1/C NO.6 ELECTRICAL CONDUCTOR | 150 | LF |
$2.20 |
$11.10 |
$5.00 |
$3.00 |
$3.00 |
| 54 | 811 8044 |
1/C NO.10 ELECTRICAL CONDUCTOR | 600 | LF |
$1.50 |
$11.10 |
$4.00 |
$1.30 |
$1.25 |
| 55 | 825 8550 |
TRAFFIC SIGNAL CONTROLLER ASSEMBLY | 1 | EA |
$24,499.70 |
$52,316.40 |
$26,669.00 |
$26,000.00 |
$25,000.00 |
| 56 | 828 8132 |
(PL)DETECTION SYSTEM (VIDEO) | 1 | LSUM |
$44,575.60 |
$38,491.80 |
$29,800.00 |
$45,000.00 |
$35,000.00 |
| 57 | 831 8231 |
1WAY 3SEC. ADJ. SIG. HD. S-6 | 8 | EA |
$670.40 |
$1,131.30 |
$600.00 |
$950.00 |
$800.00 |
| 58 | 831 8252 |
1WAY 3SEC. ADJ. SIG. HD. S-9 | 2 | EA |
$665.40 |
$1,634.90 |
$616.00 |
$940.00 |
$800.00 |
| 59 | 831 8286 |
1WAY 5SEC. ADJ. SIG. HD. S-19 | 2 | EA |
$1,315.60 |
$2,419.60 |
$1,111.00 |
$1,585.00 |
$1,200.00 |
| 60 | 833 3030 |
BACKPLATE | 12 | EA |
$193.80 |
$327.00 |
$195.00 |
$230.00 |
$200.00 |
| 61 | 834(A) 8207 |
5/C TRAFFIC SIGNAL ELECTRICAL CABLE | 800 | LF |
$2.50 |
$2.60 |
$4.00 |
$2.40 |
$3.00 |
| 62 | 834(A) 8208 |
7/C TRAFFIC SIGNAL ELECTRICAL CABLE | 200 | LF |
$2.70 |
$3.50 |
$5.00 |
$2.90 |
$4.00 |
| 63 | 834(A) 8211 |
15/C TRAFFIC SIGNAL ELECTRICAL CABLE | 400 | LF |
$4.90 |
$6.00 |
$6.00 |
$5.90 |
$5.00 |
| 64 | 834(B) 8220 |
2/C SHIELDED LOOP DETECTOR LEAD-IN CABLE | 32 | LF |
$2.00 |
$3.60 |
$3.00 |
$1.80 |
$4.00 |
| 65 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 25 | SF |
$26.60 |
$26.20 |
$20.00 |
$23.00 |
$21.25 |
| 66 | 850(C) 8118 |
MAST ARM MOUNTED SIGNS(ALUMINUM) | 10 | SF |
$57.40 |
$73.20 |
$62.00 |
$120.00 |
$100.00 |
| 67 | 851(C) 8327 |
2 1/4" SQUARE TUBE POST | 37 | LF |
$19.00 |
$13.10 |
$10.00 |
$11.75 |
$10.00 |
| 68 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 6,636 | LF |
$0.8000 |
$1.30 |
$1.00 |
$1.15 |
$1.00 |
| 69 | 856(A) 8540 |
TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) | 216 | LF |
$1.40 |
$2.60 |
$2.00 |
$2.30 |
$2.00 |
| 70 | 856(A) 8548 |
TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 60 | LF |
$3.00 |
$5.20 |
$4.00 |
$4.65 |
$4.00 |
| 71 | 856(A) 8555 |
TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 144 | LF |
$3.30 |
$13.10 |
$10.00 |
$11.65 |
$10.00 |
| 72 | 856(B) 8860 |
TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) | 12 | EA |
$151.00 |
$163.50 |
$125.00 |
$145.00 |
$125.00 |
| 73 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 50 | LF |
$6.00 |
$2.60 |
$2.00 |
$2.35 |
$2.00 |
| 74 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$15,000.00 |
$17,002.80 |
$9,000.00 |
$11,500.00 |
$20,000.00 |
| 75 | 890 7700 |
(PL)TRAFFIC ITEMS | 1 | LSUM |
$35,000.00 |
$73.30 |
$7,210.00 |
$9,000.00 |
$9,500.00 |
| 76 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$25,000.00 |
$11,000.00 |
$12,900.00 |
$5,000.00 |
$12,000.00 |
| 77 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$10,000.00 |
$5,000.00 |
$500.00 |
$1,000.00 |
$3,500.00 |
| 78 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$123,000.00 |
$40,000.00 |
$100,000.00 |
$75,000.00 |
$20,000.00 |
| 79 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$5,000.00 |
$2,000.00 |
$1,000.00 |
$2,500.00 |
$1,500.00 |
| 80 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 212 | CY |
$15.00 |
$14.00 |
$25.00 |
$35.00 |
$17.00 |
| 81 | 616(B) 5229 |
12" POLYVINYL CHLORIDE (PVC) PIPE | 120 | LF |
$185.00 |
$148.00 |
$150.00 |
$87.00 |
$140.00 |
| 82 | 616(D) 1100 |
12" GATE VALVE | 1 | EA |
$2,500.00 |
$2,865.00 |
$3,500.00 |
$2,250.00 |
$5,500.00 |
| 83 | 616(D) 7051 |
STANDARD VALVE BOX | 1 | EA |
$210.00 |
$257.00 |
$200.00 |
$230.00 |
$250.00 |
| 84 | 616(F) 5208 |
METER INSTALLATION 1" | 2 | EA |
$900.00 |
$2,966.00 |
$2,350.00 |
$1,300.00 |
$3,500.00 |
| 85 | 616(F) 5211 |
METER INSTALLATION 2" | 3 | EA |
$1,200.00 |
$3,672.00 |
$3,600.00 |
$2,970.00 |
$9,000.00 |
| 86 | 616(I) 5270 |
24" STEEL CASING | 90 | LF |
$100.00 |
$187.00 |
$100.00 |
$150.00 |
$140.00 |
| 87 | 616(K) 0225 |
12" SOLID SLEEVE | 1 | EA |
$1,400.00 |
$1,549.00 |
$1,000.00 |
$1,850.00 |
$925.00 |
| 88 | 616(N) 0090 |
SERVICE CONNECTION (SHORT) | 1 | EA |
$1,000.00 |
$1,843.00 |
$1,700.00 |
$1,000.00 |
$1,900.00 |
| 89 | 616(N) 0092 |
SERVICE CONNECTION (LONG) | 1 | EA |
$1,550.00 |
$1,921.00 |
$2,750.00 |
$2,600.00 |
$2,800.00 |
| 90 | 616(O) 0550 |
12" 90 DEGREE FITTING | 6 | EA |
$1,850.00 |
$1,841.00 |
$1,800.00 |
$970.00 |
$1,400.00 |
| 91 | 619(B) 7200 |
REMOVE WATER METER AND METER CAN | 2 | EA |
$1,850.00 |
$2,155.00 |
$250.00 |
$175.00 |
$350.00 |