$16.40Avg low bid / LF
$8.75Avg of all bids
$10.31Avg engineer's estimate
4Jobs · 8,270 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 1 | 369 | $5.00 | $7.33 |
| 2019 | 2 | 5,901 | $3.36 | $6.35 |
| 2018 | 1 | 2,000 | $57.00 | $17.81 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 17, 2021 | 210195 | TulsaDivision 8 | 369 LF | $5.00 | Paragon Contractors, LLC |
| Aug 22, 2019 | 190262 | TulsaDivision 8 | 5,900 LF | $2.00 | BECCO CONTRACTORS, INC. |
| Apr 18, 2019 | 190099 | TulsaDivision 8 | 1 LF | $8,000.00 | Tri Star Construction Arkansas, LLC |
| Jun 14, 2018 | 180229 | Nhppi-4440-(007)pm | 2,000 LF | $57.00 | SHERWOOD CONSTRUCTION CO., INC. |