$165.47Avg low bid / LF
$207.55Avg of all bids
$225.61Avg engineer's estimate
12Jobs · 1,697 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 1 | 106 | $87.00 | $277.33 |
| 2020 | 4 | 607 | $156.76 | $222.04 |
| 2019 | 5 | 881 | $185.16 | $194.39 |
| 2018 | 2 | 103 | $129.13 | $175.17 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 17, 2021 | 210195 | TulsaDivision 8 | 106 LF | $87.00 | Paragon Contractors, LLC |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 65 LF | $318.57 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200126 | TulsaDivision 8 | 216 LF | $143.56 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200126 | TulsaDivision 8 | 58 LF | $110.43 | SHERWOOD CONSTRUCTION CO., INC. |
| Mar 19, 2020 | 200085 | TulsaDivision 8 | 168 LF | $160.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Feb 20, 2020 | 200050 | BeckhamDivision 5 | 100 LF | $101.52 | Frontier Bridge, Inc. |
| Nov 14, 2019 | 190389 | TulsaDivision 8 | 497 LF | $165.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Oct 17, 2019 | 190335 | TulsaDivision 8 | 46 LF | $143.40 | Tri Star Construction Arkansas, LLC |
| Oct 17, 2019 | 190331 | TulsaDivision 8 | 160 LF | $270.48 | SHERWOOD CONSTRUCTION CO., INC. |
| Apr 18, 2019 | 190099 | TulsaDivision 8 | 90 LF | $187.00 | Tri Star Construction Arkansas, LLC |
| Mar 14, 2019 | 190133 | RogersDivision 8 | 88 LF | $163.88 | SHERWOOD CONSTRUCTION CO., INC. |
| Oct 18, 2018 | 180297 | OttawaDivision 8 | 60 LF | $150.00 | RRY SERVICES LLC |
| Sep 20, 2018 | 180280 | CraigDivision 8 | 43 LF | $100.00 | CROSSLAND HEAVY CONTRACTORS INC. |