BRIDGE AND APPROACHES US -77: OVER WASHITA RIVER , 1.5 MILES WEST OF THE SH -29 JUNCTION NEAR WYNNEWOOD. PROJECT LENGTH = 0.944 MILE

Let date
Thursday, February 15, 2018
Contract
180086
J/P numbers
27999(04)
District
Division 3
County
Garvin
Highway
Limits
BRIDGE AND APPROACHES US -77: OVER WASHITA RIVER , 1.5 MILES WEST OF THE SH -29 JUNCTION NEAR WYNNEWOOD. PROJECT LENGTH = 0.944 MILE
Project number
STP-225C(072)PM

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 MANHATTAN ROAD & BRIDGE COMPANY, LLC Low bidder $8,373,922
2 Treas Construction Inc $8,489,724 +1.4%
3 OVERLAND CORPORATION $8,671,627 +3.6%

Bid tab: unit prices 99 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 MANHATTAN ROAD …#2 Treas Construct…#3 OVERLAND CORPOR…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $25,000.00 $35,000.00 $10,300.00 $182,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION7,374CY $8.00 $7.50 $5.67 $5.80
3202(D) 0184 UNCLASSIFIED BORROW24,323CY $8.00 $9.00 $8.76 $9.00
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $25,000.00 $26,850.00 $18,540.00 $20,000.00
5221(C) 2801 TEMPORARY SILT FENCE4,468LF $2.50 $3.00 $1.44 $1.30
6221(F) 0100 TEMPORARY SILT DIKE224LF $6.00 $12.50 $7.37 $9.00
7221(G) 0151 TEMPORARY ROCK FILTER DAM TYPE 250CY $100.00 $105.00 $87.32 $190.00
8230(A) 2806 SOLID SLAB SODDING34,846SY $2.00 $1.55 $1.60 $1.58
9233(A) 2817 VEGETATIVE MULCHING25.46AC $500.00 $390.00 $386.25 $413.00
10241 2832 MOWING14.4AC $110.00 $70.00 $66.95 $75.00
11307(K) 4300 STABILIZED SUBGRADE29,043SY $5.00 $5.00 $5.00 $3.80
12402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E200TON $40.00 $23.00 $19.32 $43.00
13407(B) 0250 TACK COAT6,753GAL $3.00 $3.10 $2.06 $0.0100
14408 5774 PRIME COAT10,908GAL $5.00 $2.51 $3.09 $0.0100
15409(A) 4242 FABRIC REINFORCEMENT598SY $4.00 $3.50 $3.09 $5.25
16409(B) 4268 BITUMINOUS BINDER120GAL $4.00 $12.00 $10.30 $7.50
17411(B) 5940 SUPERPAVE, TYPE S3(PG 70-28 OK)3,068TON $75.00 $61.00 $68.62 $67.00
18411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)9,560TON $70.00 $53.00 $61.82 $59.00
19411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)2,776TON $85.00 $67.00 $77.78 $71.50
20411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)1,179TON $80.00 $62.00 $63.90 $84.00
21412 5267 COLD MILLING PAVEMENT6,199SY $3.50 $2.00 $2.06 $1.20
22509(A) 0319 CLASS AA CONCRETE3.9CY $1,000.00 $1,600.00 $772.50 $520.00
23509(D) 0325 CLASS C CONCRETE624CY $350.00 $215.00 $334.75 $305.00
24511(A) 0332 REINFORCING STEEL470LB $2.00 $1.00 $2.06 $1.00
25613(A) 0492 24" R.C.PIPE CLASS III76LF $75.00 $65.00 $67.98 $69.00
26613(B) 0691 30" CORR. GALV. STEEL PIPE68LF $50.00 $40.00 $41.20 $50.00
27613(B) 4527 21" X 15" CORR. GALV. STEEL PIPE ARCH290LF $40.00 $34.00 $25.75 $26.00
28613(B) 4529 35" X 24" CORR. GALV. STEEL PIPE ARCH50LF $50.00 $44.00 $43.26 $43.00
29613(M) 7186 TYPE A4 CULVERT END TREATMENT10EA $1,100.00 $650.00 $1,236.00 $900.00
30613(M) 7187 TYPE B4 CULVERT END TREATMENT3EA $1,500.00 $800.00 $1,648.00 $1,300.00
31613(M) 7188 TYPE C4 CULVERT END TREATMENT2EA $1,800.00 $850.00 $1,957.00 $1,900.00
32619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $10,000.00 $27,800.00 $4,120.00 $5,000.00
33619(B) 4728 REMOVAL OF ASPHALT PAVEMENT16,853SY $4.00 $3.10 $4.12 $1.60
34623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE612.5LF $20.00 $18.00 $18.03 $17.50
35623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $3,000.00 $2,250.00 $2,214.50 $2,250.00
36623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $2,000.00 $2,400.00 $1,411.10 $1,700.00
37624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)3,544LF $5.00 $4.25 $4.22 $4.20
38501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON260CY $25.00 $50.00 $20.60 $11.30
39501(G) 6309 CLSM BACKFILL360CY $120.00 $155.00 $222.86 $140.00
40503(A) 1313 PRESTRESSED CONCRETE BEAMS (TYPE IV)1,883LF $230.00 $220.00 $220.10 $230.00
41504(A) 1304 APPROACH SLAB467.8SY $180.00 $152.00 $195.98 $165.00
42504(B) 1305 SAW-CUT GROOVING5,526SY $4.50 $3.05 $4.17 $2.16
43504(C) 6250 SEALED EXPANSION JOINT140.3LF $270.00 $155.00 $231.52 $170.00
44504(D) 6245 CONCRETE RAIL (TR4)1,463.3LF $80.00 $50.00 $87.56 $80.00
45506(A) 1322 STRUCTURAL STEEL1,576,610LB $1.75 $1.50 $1.39 $1.43
46507(A) 6170 STAINLESS STEEL FIXED BEARING ASSEMBLY21EA $2,680.00 $1,700.00 $1,753.06 $1,400.00
47507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY42EA $2,650.00 $1,500.00 $1,261.34 $1,400.00
48509(A) 1326 CLASS AA CONCRETE1,266.8CY $550.00 $475.00 $603.19 $750.00
49509(B) 1328 CLASS A CONCRETE568.3CY $575.00 $625.00 $603.19 $500.00
50509(D) 1331 CLASS C CONCRETE12.6CY $475.00 $600.00 $515.00 $400.00
51511 6306 MECHANICAL SPLICES92EA $150.00 $132.00 $119.87 $125.00
52511(A) 1332 REINFORCING STEEL2,820LB $1.00 $1.25 $1.49 $1.20
53511(B) 6010 EPOXY COATED REINFORCING STEEL348,350LB $1.00 $0.9500 $1.07 $0.8500
54514(A) 6010 PILES, FURNISHED (HP 10X42)282LF $35.00 $30.00 $25.10 $28.00
55514(A) 6011 PILES, FURNISHED (HP 12X53)1,486LF $36.00 $35.00 $30.30 $35.00
56514(B) 6292 PILES, DRIVEN (HP 10X42)282LF $15.00 $7.00 $12.36 $11.00
57514(B) 6294 PILES, DRIVEN (HP 12X53)1,486LF $15.00 $8.00 $11.33 $20.00
58514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00
59515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)2,469SY $4.00 $3.70 $4.79 $3.50
60516(A) 6098 DRILLED SHAFTS 72" DIAMETER453LF $850.00 $1,000.00 $973.15 $900.00
61516(A) 6100 DRILLED SHAFTS 84" DIAMETER486LF $1,000.00 $1,400.00 $1,354.25 $1,100.00
62516(C) 6200 CROSSHOLE SONIC LOGGING4EA $2,000.00 $2,870.00 $2,575.00 $4,000.00
63523(A) 6550 SEALER CRACK PREPARATION351LF $4.00 $4.10 $5.15 $6.00
64523(B) 6560 SEALER RESIN4GAL $125.00 $155.00 $169.95 $132.00
65601(B) 1353 TYPE I-A PLAIN RIPRAP3,040TON $40.00 $31.00 $39.28 $42.00
66601(C) 1355 TYPE I-A FILTER BLANKET600TON $35.00 $25.00 $28.62 $37.00
67613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND140LF $22.00 $16.00 $30.90 $40.00
68613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.44LF $22.00 $16.00 $30.90 $31.00
69619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $175,000.00 $180,000.00 $183,340.00 $250,000.00
70857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)6,297LF $0.2000 $0.2600 $0.2600 $0.2600
71857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)3,793LF $0.7500 $0.2600 $0.2600 $0.2600
72857(F) 8007 PAVEMENT MARKING REMOVAL(ARROWS)2EA $50.00 $52.00 $51.50 $52.56
73857(F) 8008 PAVEMENT MARKING REMOVAL(WORDS)1EA $70.00 $52.00 $51.50 $52.56
74880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF46,710SD $0.4000 $0.1100 $0.1000 $0.1100
75880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF11,070SD $1.00 $0.2600 $0.2600 $0.2600
76880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF2,970SD $1.50 $3.10 $3.09 $3.15
77880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)6,210SD $1.50 $1.05 $1.03 $1.05
78880(C) 8848 WING BARRICADES540SD $1.50 $2.05 $2.06 $2.10
79880(E) 8860 WARNING LIGHTS(TYPE A)12,420SD $0.5000 $0.1100 $0.1000 $0.1100
80880(F) 8878 DRUMS7,560SD $0.5000 $0.1100 $0.1000 $0.1100
81880(G) 8890 CHANNELIZER CONES3,780SD $0.5000 $0.1100 $0.1000 $0.1100
82882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN1,620SD $15.00 $10.25 $10.30 $10.51
83413(B) 4863 RUMBLE STRIP-METHOD HMA-CYC8,686LF $1.00 $0.3400 $0.2600 $0.3600
84805(A) 8724 (PL)REMOVAL OF EXISTING SIGNS25EA $70.00 $26.00 $25.75 $26.28
85805(D) 8756 (PL)REMOVE & RESET EXISTING SIGNS3EA $250.00 $170.00 $154.50 $157.68
86850(A) 8110 SHEET ALUMINUM SIGNS220.7SF $30.00 $14.50 $14.42 $14.72
87851(C) 8324 2" SQUARE TUBE POST421.5LF $12.00 $8.25 $8.24 $8.41
88853 9033 DELINEATORS(TYPE 2, CODE 1)21EA $20.00 $31.00 $30.90 $31.54
89853 9063 BARRIER DELINEATORS(TYPE 2, CODE 1)28EA $12.00 $10.50 $10.30 $10.51
90853 9069 GUARDRAIL DELINEATORS(TYPE 2, CODE 1)18EA $15.00 $15.50 $15.45 $10.51
91856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)27,831LF $0.7500 $0.3900 $0.3900 $0.4000
92856(A) 8540 TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE)621LF $1.50 $1.05 $1.03 $1.05
93856(A) 8548 TRAFFIC STRIPE(MULTI-POLY)(12" WIDE)1,110LF $2.50 $2.05 $2.06 $2.10
94856(A) 8555 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE)24LF $6.00 $10.25 $10.30 $10.51
95856(B) 8860 TRAFFIC STRIPE(MULTI-POLY.)(ARROWS)15EA $175.00 $130.00 $128.75 $131.40
96642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $38,000.00 $38,800.00 $25,750.00 $15,000.00
97220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $1,800.61 $3,090.00 $5,000.00
98640(A) 1426 FIELD OFFICE1EA $8,000.00 $10,501.00 $3,605.00 $50,000.00
99641 1552 MOBILIZATION1LSUM $420,000.00 $399,000.00 $270,156.23 $400,000.00