ODOT Bid Results

Feb 2018 · 44 let jobs Sign up free
44Let jobs
$74,986,304Total low bids
$52,619,886Total estimates
+42.5%Low bids vs estimates

Feb 2018 results

Bid tabs (Excel) ExcelCSV
Let dateContractCounty / DistrictProject EstimateLow bidLow bidder% vs est.Bidders
Feb 15, 2018 180009NHPP-237N(019)SS Kingfisher
Division 4
GRADE, DRAIN, AND SURFACE US -81: FROM 1.3 MILES SOUTH OF THE SH -33 INTERSECTION, EXTEND SOUTHWEST NEAR THE CITY OF KINGFISHER . PROJECT LENGTH = 3.314 MILES · $10,215,350 $8,595,947 DUIT CONSTRUCTION COMPANY, INC. -15.9% 7
Feb 15, 2018 180086STP-225C(072)PM Garvin
Division 3
BRIDGE AND APPROACHES US -77: OVER WASHITA RIVER , 1.5 MILES WEST OF THE SH -29 JUNCTION NEAR WYNNEWOOD. PROJECT LENGTH = 0.944 MILE · — $8,373,922 MANHATTAN ROAD & BRIDGE COMPANY, LLC 3
Feb 15, 2018 180113CIRB-165C(100)RB Roger Mills
Division 5
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROADS (EW-97/NS-192/EW-98): ON EW-97 FROM 4.7 MI E OF US-283, EXTEND E THEN S ON NS -192, THEN E ON EW-98. PROJECT LENGTH = 6.975 MILES · $6,632,835 $5,668,110 CASWELL CONSTRUCTION, INC. -14.5% 5
Feb 15, 2018 180100NHPPI-4400-(027)PM Oklahoma
Division 4
BRIDGE REHABILITATION I -44 (WEST TO SOUTH RAMP ): OVER SH-66 AND SH-3, 3.6 MILES NORTH OF THE I -40 INTERCHANGE IN OKLAHOMA CITY . PROJECT LENGTH = 0.270 MILE · $3,744,539 $4,070,015 MANHATTAN ROAD & BRIDGE COMPANY, LLC +8.7% 1
Feb 15, 2018 180091STP-241C(058)PM Lincoln
Division 3
BRIDGE AND APPROACHES SH -18: OVER DRY CREEK OVERFLOW AND DRY CREEK , 5.6 MILES AND 5.7 MILES NORTH OF I -44 NEAR CHANDLER. PROJECT LENGTH = 0.661 MILE · $3,827,314 $3,216,964 BRIDGECO CONTRACTORS, INC. -15.9% 6
Feb 15, 2018 180033STP-267C(045)SS Seminole
Division 3
GRADE, DRAIN, SURFACE , AND BRIDGE SH-56: OVER JUMPER CREEK, 1.3 MILES EAST OF THE SH-99 INTERSECTION NEAR KONAWA . PROJECT LENGTH = 0.568 MILE · — $2,976,296 Treas Construction Inc 8
Feb 15, 2018 180089STP-233C(036)3P Nhpp-020n(044)3p
JACKSON RESURFACE (ASPHALT ) US-62/SH-6: FROM THE SH -34 JUNCTION, EXTEND EAST ON US -62 THEN SOUTH ON SH-6 NEAR ALTUS . PROJECT LENGTH = 13.390 MILES · $2,953,227 $2,583,106 CORNELL CONSTRUCTION COMPANY, INC. -12.5% 4
Feb 15, 2018 180052CIRB-248C(034)RB Marshall
Division 2
GRADE,DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (ENOS ROAD): FROM 4.0 MILES SOUTH OF SH-32, EXTEND SOUTH NEAR KINGSTON . PROJECT LENGTH = 3.039 MILES · $2,821,129 $2,563,205 THE CUMMINS CONSTRUCTION CO., INC. -9.1% 3
Feb 15, 2018 180096SSR-251C(082)SR Ssr-251c(083)sr
31383(04) STP-251C(084)3P MUSKOGEE RESURFACE (ASPHALT ) US-64/SH-2: FROM THE I -40 INTERCHANGE, EXTEND NORTH NEAR WARNER . PROJECT LENGTH = 6.374 MILES · — $2,515,300 GLOVER & ASSOCIATES, INC. 2
Feb 15, 2018 180080NHPPI-216N(073)3P Comanche
Division 7
RESURFACE (ASPHALT ) I-44 (EB): FROM 3.45 MILES SOUTH OF THE US -62 JUNCTION, EXTEND NORTH NEAR FORT SILL . PROJECT LENGTH = 3.45 MILES · — $2,102,474 T & G CONSTRUCTION, INC. 3
Feb 15, 2018 180010STP-238C(045)SS Stp-238c(046)ss
KIOWA BRIDGE AND APPROACHES SH -19: OVER UNNAMED CREEKS, 0.2 MI AND 3.1 MI WEST OF THE CADDO COUNTY LINE . PROJECT LENGTH = 0.496 MILE · — $2,082,170 RRY SERVICES LLC 5
Feb 15, 2018 180117NHPP-272N(242)3P Tulsa
Division 8
RESURFACE (P.C. CONCRETE) US-169: FROM 0.4 MILES SOUTH OF THE SH -20 EAST INTERCHANGE, EXTEND NORTH NEAR OWASSO . PROJECT LENGTH = 3.42 MILES · $1,850,598 $2,006,704 DIAMOND SURFACE, INC. +8.4% 5
Feb 15, 2018 180079NHPP-211N(029)3P Stp-211n(030)3p
CHEROKEE RESURFACE (ASPHALT ) US-62: FROM THE SH -51 JUNCTION, EXTEND NORTHEAST AND FROM THE SH-82 JUNCTION EXTEND NORTHEAST IN TAHLEQUAH . PROJECT LENGTH = 3.636 MILES · — $1,797,306 GLOVER & ASSOCIATES, INC. 2
Feb 15, 2018 180005HSIPG-216B(067)SS Comanche
Division 7
INTERSECTION MODIFICATION US -62: AT THE INTERSECTION OF MCCRACKEN RD AND MCINTOSH RD, 0.7 MI AND 1.7 MI N OF THE I -44 INTERCHANGE NEAR LAWTON . PROJECT LENGTH = 0.804 MILE · — $1,680,580 T & G CONSTRUCTION, INC. 2
Feb 15, 2018 180092STP-247C(021)3P Major
Division 6
RESURFACE (ASPHALT ) SH-8: FROM THE BLAINE COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 7.620 MILES · $1,516,237 $1,462,194 HIGHWAY CONTRACTORS, INC. -3.6% 5
Feb 15, 2018 180121STP-275C(042)3P Washita
Division 5
RESURFACE (ASPHALT ) SH-152: FROM 5.23 MILES EAST OF SH -44, EXTEND EAST NEAR CORDELL . PROJECT LENGTH = 5.19 MILES · $1,695,672 $1,460,279 CORNELL CONSTRUCTION COMPANY, INC. -13.9% 4
Feb 15, 2018 180070ACSTP-268D(050)CI Sequoyah
Division 1
BRIDGE AND APPROACHES COUNTY ROAD (EW-104/ALPHA ROAD ): OVER LITTLE VIAN CREEK, 1.4 MILES EAST OF SH -82 NEAR VIAN. PROJECT LENGTH = 0.427 MILE · $1,414,589 $1,285,423 B & B BRIDGE COMPANY, LLC -9.1% 7
Feb 15, 2018 180119SSP-272F(240)PM Tulsa
Division 8
JOINT SEAL /REPAIR US -64: OVER ARKANSAS RIVER AND ARKANSAS RIVER O 'FLOW, 0.8 MILES AND 1.0 MILE NORTH OF THE SH -67 JUNCTION IN BIXBY. · — $1,229,759 LOGOS CONSTRUCTION CO., LLC 2
Feb 15, 2018 180090SSR-236C(002)SR Kay
Division 4
RESURFACE (ASPHALT ) SH-156: FROM THE NOBLE COUNTY LINE , EXTEND NORTH NEAR PONCA CITY. PROJECT LENGTH = 6.130 MILES · $1,330,000 $1,227,358 Evans & Associates Construction Co., Inc. -7.7% 3
Feb 15, 2018 180064NHPP-256N(037) Pawnee
Division 8
GRADE AND DRAIN US -412: FROM THE US -64 INTERCHANGE, EXTEND EAST NEAR WESTPORT . PROJECT LENGTH = 7.58 MILES · $1,004,244 $1,179,474 BREWER CONSTRUCTION OKLAHOMA, LLC +17.4% 1
Feb 15, 2018 180110SSR-257C(002)SR Osage
Division 8
RESURFACE (ASPHALT ) SH-18: FROM THE US -60 JUNCTION, EXTEND NORTH THEN EAST THEN NORTH NEAR SHIDLER . PROJECT LENGTH = 5.980 MILES · $1,064,577 $1,129,994 APAC-CENTRAL, INC. +6.1% 3
Feb 15, 2018 180114NHPP-270N(033)3P Texas
Division 6
RESURFACE (ASPHALT ) US-54 EB: FROM 8.57 MILES NORTHEAST OF THE US -64W JUNCTION, EXTEND NORTHEAST NEAR GUYMON . PROJECT LENGTH = 4.000 MILES · — $1,128,837 J & R SAND COMPANY, INC. 2
Feb 15, 2018 180088STP-230B(028)3P Harper
Division 6
RESURFACE (ASPHALT ) SH-34: FROM THE US -64 JUNCTION, EXTEND SOUTH NEAR BUFFALO . PROJECT LENGTH = 6.90 MILES · — $1,018,861 Venture Corporation dba VCO Paving 2
Feb 15, 2018 180087STP-226B(065)3P Grady
Division 7
RESURFACE (ASPHALT ) US-62: FROM 3.0 MILES EAST OF THE CADDO COUNTY LINE , EXTEND EAST NEAR CHICKASHA . PROJECT LENGTH = 4.49 MILES · — $947,764 MARKWELL PAVING COMPANY, INC. 4
Feb 15, 2018 180108CIRB-157C(161)RB Osage
Division 8
BRIDGE AND APPROACHES COUNTY ROAD (EW-28/GEORGE BRADEN ROAD): OVER UNNAMED CREEK, 8.9 MILES EAST OF US -177 NEAR PONCA CITY . PROJECT LENGTH = 0.247 MILE · $998,372 $874,941 BRIDGECO CONTRACTORS, INC. -12.4% 7
Feb 15, 2018 180081CIRB-217D(036)RB Cotton
BRIDGE AND APPROACHES COUNTY ROAD (EW-193): OVER DEEP RED CREEK , 0.2 MILES AND 0.3 MILES WEST OF THE H .E. BAILEY TURNPIKE NEAR RANDLETT . PROJECT LENGTH = 0.293 MILE · $1,065,902 $863,145 SAC Services, Inc. -19.0% 8
Feb 15, 2018 180098MC-252N(041) Noble
Division 4
RESURFACE (ASPHALT ) US-64: FROM I-35, EXTEND EAST IN PERRY . PROJECT LENGTH = 2.70 MILES · $562,350 $839,700 INTERMOUNTAIN SLURRY SEAL, INC. +49.3% 1
Feb 15, 2018 180109SSR-157C(185)SR Osage
Division 8
RESURFACE (ASPHALT ) SH-20: FROM 1.0 MILE WEST OF THE SH -99 JUNCTION, EXTEND WEST IN HOMINY. PROJECT LENGTH = 4.520 MILES · $854,784 $826,998 APAC-CENTRAL, INC. -3.3% 5
Feb 15, 2018 180034NHPP-272N(236)SS Tulsa
Division 8
BRIDGE REHABILITATION CITY STREET (PEORIA AVENUE ): OVER US-75, 1.1 MILES NORTH OF I -244 IN THE CITY OF TULSA. PROJECT LENGTH = 0.040 MILE · $652,266 $775,929 PBX Corporation +19.0% 1
Feb 15, 2018 180078CIRB-211D(034)RB Cherokee
Division 1
BRIDGE AND APPROACHES COUNTY ROAD (EW-83): OVER MANARD BAYOU , 0.5 MILES EAST OF THE MUSKOGEE COUNTY LINE . PROJECT LENGTH = 0.198 MILE. · $930,745 $760,488 BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION -18.3% 8
Feb 15, 2018 180093NHPP-249N(044)3P Mayes
Division 8
RESURFACE (ASPHALT ) US-69: FROM 0.58 MILES NORTH OF THE SH -28 JUNCTION, EXTEND NORTH NEAR ADAIR . PROJECT LENGTH = 4.72 MILES · $932,942 $759,920 APAC-CENTRAL, INC. -18.5% 3
Feb 15, 2018 180116SSP-NBIP(525)PM Tulsa
Division 8
BRIDGE PAINTING I -244/CITY STREET (GILCREASE DRIVE WB): AT MULTIPLE LOCATIONS IN DIVISION VIII. · $1,044,568 $750,951 Southeast Bridge FL Corp -28.1% 6
Feb 15, 2018 180120SSP-4000(062)PM Washita
Division 5
BRIDGE AND APPROACHES I -40 NORTH FRONTAGE ROAD : OVER SAND CREEK, 0.1 MILES EAST OF SH-44 NEAR FOSS. PROJECT LENGTH = 0.012 MILE · $786,675 $740,533 C-GAWF CONSTRUCTION, INC. -5.9% 8
Feb 15, 2018 180074SSR-276B(028)SR Woods
Division 6
RESURFACE (ASPHALT ) US-64: FROM 6.0 MILES EAST OF THE SH -14 JUNCTION, EXTEND EAST NEAR ALVA . PROJECT LENGTH = 5.17 MILES · $790,715 $689,514 Venture Corporation dba VCO Paving -12.8% 4
Feb 15, 2018 180099NHPPI-2350-(007)PM Oklahoma
Division 4
GRADE, DRAIN, AND SURFACE I -235: NORTHBOUND OFF -RAMP TO NE 23RD STREET IN THE CITY OF OKLAHOMA CITY . PROJECT LENGTH = 0.141 MILE · $620,773 $686,705 RUDY CONSTRUCTION CO. +10.6% 4
Feb 15, 2018 180111CIRB-257D(065)RB Osage
Division 8
BRIDGE AND APPROACHES COUNTY ROAD (N 66TH W. AVE): OVER TRIBUTARY TO DELAWARE CREEK, 5.3 MILES NORTH OF THE TULSA COUNTY LINE . PROJECT LENGTH = 0.113 MILE · $759,231 $682,892 B & B BRIDGE COMPANY, LLC -10.1% 4
Feb 15, 2018 180076STP-201B(033)3P Adair
Division 1
RESURFACE (ASPHALT ) US-62: FROM THE US -59 JUNCTION, EXTEND WEST NEAR WESTVILLE . PROJECT LENGTH = 2.770 MILES · $615,718 $612,546 GLOVER & ASSOCIATES, INC. -0.5% 4
Feb 15, 2018 180066SSR-261C(078)SR Pittsburg
Division 2
RESURFACE (ASPHALT ) SH-31: FROM 10.6 MILES NORTHEAST OF THE US -270 INTERSECTION, EXTEND NORTHEAST NEAR KREBS . PROJECT LENGTH = 3.89 MILES · — $597,394 GLOVER & ASSOCIATES, INC. 2
Feb 15, 2018 180083STP-219B(062)3P Creek
Division 8
RESURFACE (ASPHALT ) SH-99: FROM THE SH -51 JUNCTION, EXTEND NORTH NEAR OILTON . PROJECT LENGTH = 3.02 MILES · $621,938 $565,377 THE QUAPAW COMPANY -9.1% 7
Feb 15, 2018 180085ACSTP-221C(041)CI Delaware
Division 8
RESURFACE (ASPHALT ) COUNTY ROAD (COLCORD-KEITHLY ROAD /CR S670): FROM SH-116, EXTEND NORTH IN COLCORD . PROJECT LENGTH = 2.01 MILES · — $489,509 GLOVER & ASSOCIATES, INC. 3
Feb 15, 2018 180082NHPP-218N(060)3P Craig
Division 8
RESURFACE (ASPHALT ) US-69: FROM 1.6 MILES NORTH OF THE MAYES COUNTY LINE , EXTEND NORTH NEAR BIG CABIN . PROJECT LENGTH = 1.14 MILES · $469,018 $390,000 BECCO CONTRACTORS, INC. -16.8% 4
Feb 15, 2018 180038SSR-208C(060)SR Caddo
Division 7
RESURFACE (ASPHALT ) SH-58: FROM 1.0 MILE SOUTH OF SH-9, EXTEND NORTH NEAR CARNEGIE . PROJECT LENGTH = 1.52 MILES · $456,376 $367,651 T & G CONSTRUCTION, INC. -19.4% 5
Feb 15, 2018 180118SSP-272F(239)PM Craig, Delaware, Mayes, Rogers, Tulsa
BRIDGE WATER PROOF SEAL INTERSTATES /US-HIGHWAYS /STATE HIGHWAYS /CITY STREETS : AT MULTIPLE LOCATIONS IN DIVISION VIII. · $321,400 $336,440 JLT Contracting, LLC +4.7% 3
Feb 15, 2018 180102TAP-255D(325)AG Oklahoma
Division 4
PEDESTRIAN IMPROVEMENTS (BUS STOPS ) CITY STREETS : AT MULTIPLE LOCATIONS IN OKLAHOMA CITY . · $65,805 $73,630 SAC Services, Inc. +11.9% 4
1–44 of 44

Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.