17Let jobs
$143,782,774Total low bids
$149,696,173Total estimates
-4.0%Low bids vs estimates
Aug 2020 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Aug 20, 2020 | 200270NHPPI-4400(054)PM | Nhppi-4400(077)pm |
TULSA INTERCHANGE AND BRIDGE AND APPROACHES I-44: AT THE US-75 INTERCHANGE, 1.7 MILES EAST OF I -244 AND OVER UNION AVENUE , 1.5 MILES EAST OF I -244 IN TULSA . PROJECT LENGTH = 1.902 MILES · | $91,459,537 | $87,207,269 | SHERWOOD CONSTRUCTION CO., INC. | -4.6% | 4 |
| Aug 20, 2020 | 200163NHPPI-4000-(100)PM | Okfuskee Division 3 |
PAVEMENT REHABILITATION (ASPHALT ) I-40: FROM 0.4 MILES WEST OF SH -27, EXTEND EAST NEAR OKEMAH. PROJECT LENGTH = 5.792 MILES · | $18,568,000 | $17,697,697 | HASKELL LEMON CONSTRUCTION CO. | -4.7% | 4 |
| Aug 20, 2020 | 200225CIRB-226C(066)RB | Grady Division 7 |
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROADS (NINNEKAH RD/EW-142/EW-142.5 (DELL ST)/NS-284): AT MULTIPLE LOCATIONS IN NINNEKAH. PROJECT LENGTH = 5.158 MILES · | $9,160,069 | $9,911,422 | SEWELL BROS., INC. | +8.2% | 6 |
| Aug 20, 2020 | 200010CIRB-222C(026)RB | Dewey Division 5 |
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROADS (INDIAN ROAD/E0600 RD/N2360 RD): FROM US-60, EXTEND EAST ON E 0600 RD THEN SOUTH ON N 2360 RD IN SEILING. PROJECT LENGTH = 7.943 MILES · | $8,823,932 | $8,869,940 | SEWELL BROS., INC. | +0.5% | 4 |
| Aug 20, 2020 | 200158NHPP-013N(173)PM | Muskogee Division 1 |
RESURFACE (ASPHALT ) US-69: FROM 4.5 MILES NORTH OF THE MCINTOSH COUNTY LINE , EXTEND NORTH NEAR OKTAHA . PROJECT LENGTH = 8.000 MILES · | $6,215,090 | $6,355,196 | APAC-CENTRAL, INC. | +2.3% | 2 |
| Aug 20, 2020 | 200150CIRB-223C(017)RB | Ellis Division 6 |
GRADE, DRAIN, AND SURFACE COUNTY ROAD (EW-37): FROM THE US -283 JUNCTION, EXTEND EAST NEAR CHANEY . PROJECT LENGTH = 3.560 MILES · | $4,057,028 | $4,173,219 | J & R SAND COMPANY, INC. | +2.9% | 2 |
| Aug 20, 2020 | 200268CIRB-261C(098)RB | Pittsburg Division 2 |
RESURFACE (COLD IN PLACE RECYCLE) COUNTY ROAD (CROWDER BLOCKER ROAD): FROM THE SH -31 JUNCTION, EXTEND NORTHWEST NEAR CROWDER AND BLOCKER . PROJECT LENGTH = 7.950 MILES · | $2,839,001 | $2,795,827 | Rosscon, LLC | -1.5% | 2 |
| Aug 20, 2020 | 200239STP-276C(047)CI | Woods Division 6 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-237): OVER GREEN LEAF CREEK, 8.7 MILES NORTH OF THE US -64 JUNCTION NEAR THE KANSAS STATE LINE . PROJECT LENGTH = 0.239 MILE · | $1,225,981 | $1,199,890 | K & R BUILDERS, INC. | -2.1% | 8 |
| Aug 20, 2020 | 200298TAP-272D(296)IG | Tulsa Division 8 |
PEDESTRIAN IMPROVEMENTS (BROKEN ARROW CREEK TRAIL ) CITY STREETS (S DATE AVE /W MIAMI ST/S ASH AVE/W AUSTIN ST/S 1ST PLACE ): AT MULTIPLE LOCATIONS IN BROKEN ARROW . PROJECT LENGTH = 2.090 MILES · | $1,176,732 | $1,040,680 | CROSSLAND HEAVY CONTRACTORS INC. | -11.6% | 4 |
| Aug 20, 2020 | 200264STP-240C(090)CI | Leflore |
BRIDGE AND APPROACHES COUNTY ROAD (NS-464): OVER BRAZIL CREEK , 3.4 MILES SOUTH OF SH-31 NEAR BOKOSHE. PROJECT LENGTH = 0.210 MILE · | $1,262,351 | $933,068 | HUB Construction, Inc. | -26.1% | 5 |
| Aug 20, 2020 | 200265CIRB-242D(071)RB | Logan Division 4 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-71): OVER TRIBUTARY TO SKELETON CREEK , 5.9 MILES EAST OF THE SH -74 JUNCTION NEAR CRESCENT. PROJECT LENGTH = 0.208 MILE · | $1,321,348 | $882,069 | Wyatt Contracting | -33.2% | 15 |
| Aug 20, 2020 | 200262STP-205D(088)CI | Beckham Division 5 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-112): OVER WEST ELK CREEK , 3.4 MILES EAST OF THE I-40 BUSINESS JUNCTION IN ELK CITY. PROJECT LENGTH = 0.151 MILE · | $817,935 | $762,027 | SEWELL BROS., INC. | -6.8% | 7 |
| Aug 20, 2020 | 200111STP-246C(044)PM | Mcintosh Division 1 |
BRIDGE PAINTING SH -9: OVER SOUTH CANADIAN RIVER, 1.3 MILES NORTHWEST OF THE SH -9A JUNCTION NEAR EUFAULA . PROJECT LENGTH = 0.000 MILE · | $917,845 | $698,080 | OMEGA COATINGS & CONSTRUCTION, LLC | -23.9% | 10 |
| Aug 20, 2020 | 200230STP-243D(034)CI | Love Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-3210/DORY ROAD ): OVER TRIBUTARY TO WALNUT BAYOU , 2.5 MILES NORTH OF SH -32 NEAR BURNEYVILLE. PROJECT LENGTH = 0.148 MILE · | $1,015,512 | $601,019 | HUB Construction, Inc. | -40.8% | 8 |
| Aug 20, 2020 | 200263NHPPI-4000-(105)3B | Custer Division 5 |
JOINT SEAL /REPAIR I -40: OVER I-40 BUSINESS AND FMRC RAILROAD , 2.2 MILES EAST OF THE SH-54 JUNCTION NEAR WEATHERFORD . PROJECT LENGTH - 0.000 MILE · | $778,055 | $535,904 | PBX Corporation | -31.1% | 7 |
| Aug 20, 2020 | 200266STP-243C(039)PM | Love Division 7 |
RIGHT-OF-WAY CLEARANCE SH-32: FROM 1.6 MILES EAST OF THE US -77 JUNCTION, EXTEND EAST THEN NORTHEAST NEAR MARIETTA . PROJECT LENGTH = 6.980 MILES · | — | $61,147 | KC Durtworks, LLC | 5 | |
| Aug 20, 2020 | 200299STP-277F(047)PM | Woods, Woodward |
BRIDGE WATER PROOF SEAL US -64/US-183/US-270/SH-3 WB/SH-50: AT MULTIPLE LOCATIONS IN DIVISION VI. PROJECT LENGTH = 0.000 MILE · | $57,757 | $58,320 | GARY A. CRAIN, INC. | +1.0% | 2 |
1–17 of 17
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.