RIGHT-OF-WAY CLEARANCE SH-32: FROM 1.6 MILES EAST OF THE US -77 JUNCTION, EXTEND EAST THEN NORTHEAST NEAR MARIETTA . PROJECT LENGTH = 6.980 MILES
- Let date
- Thursday, August 20, 2020
- Contract
- 200266
- J/P numbers
- 28814(08)
- District
- Division 7
- County
- Love
- Highway
- Limits
- RIGHT-OF-WAY CLEARANCE SH-32: FROM 1.6 MILES EAST OF THE US -77 JUNCTION, EXTEND EAST THEN NORTHEAST NEAR MARIETTA . PROJECT LENGTH = 6.980 MILES
- Project number
- STP-243C(039)PM
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | KC Durtworks, LLC Low bidder | $61,147 | ||
| 2 | Robin Hausner Demolition, LLC | $72,323 | +18.3% | |
| 3 | RMR DEMOLITION, LLC | $79,377 | +29.8% | |
| 4 | Built Right Construction, LLC | $99,500 | +62.7% | |
| 5 | SCHIRALLI CONSTRUCTION CORP. | $102,634 | +67.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 KC Durtworks, L… | #2 Robin Hausner D… | #3 RMR DEMOLITION,… | #4 Built Right Con… | #5 SCHIRALLI CONST… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 233(A) 2817 | VEGETATIVE MULCHING | 1 | AC | $1,000.00 | $4,500.00 | $100.00 | $300.00 | $2,500.00 | $3,000.00 |
| 2 | 619(G) 0094 | RIGHT-OF-WAY CLEARANCE | 1 | LSUM | $122,000.00 | $52,061.25 | $70,223.00 | $67,077.00 | $82,000.00 | $82,757.47 |
| 3 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $1,000.00 | $2,000.00 | $500.00 | $2,000.00 | $5,000.00 | $3,000.00 |
| 4 | 641 1552 | MOBILIZATION | 1 | LSUM | $6,000.00 | $2,586.00 | $1,500.00 | $10,000.00 | $10,000.00 | $13,876.97 |