42Let jobs
$56,693,032Total low bids
$50,899,174Total estimates
+11.4%Low bids vs estimates
Jan 2017 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jan 19, 2017 | 170054NHPPIY-2440-(013) | Nhppiy-2440-(014) |
TULSA BRIDGE REHABILITATION CITY STREETS (HARVARD AVE /PITTSBURG AVE /YALE AVE/ MEMORIAL DR): OVER I-244 IN THE CITY OF TULSA. PROJECT LENGTH = 0.121 MILE · | $7,144,262 | $8,097,437 | MANHATTAN ROAD & BRIDGE COMPANY, LLC | +13.3% | 3 |
| Jan 19, 2017 | 170053ACNHPPI-4400-(016)SS | Acnhppi-4400-(014)ss |
29775(04) ACNHPPI-4400-(015)SS TULSA BRIDGE REHABILITATION I -44/GILCREASE EXPWY RAMP : OVER I-244, CITY ST , CNTY RD , TSU RR AND BNSF RR, AT MULTIPLE LOCATIONS IN TULSA. PROJECT LENGTH = 0.170 MILE · | $4,918,222 | $5,833,000 | BECCO CONTRACTORS, INC. | +18.6% | 3 |
| Jan 19, 2017 | 170052SSR-271B(054)SR | Tillman Division 5 |
RESURFACE (ASPHALT ) SH-5: FROM 0.42 MILES EAST OF THE US -183 JUNCTION, EXTEND EAST IN FREDERICK. PROJECT LENGTH = 15.81 MILES · | $4,463,312 | $3,585,473 | OVERLAND CORPORATION | -19.7% | 5 |
| Jan 19, 2017 | 170011BSAP-213N(015)FM | Cimarron Division 6 |
WEIGH STATION US -56: BOISE CITY WEIGH STATION , 0.7 MILES WEST OF US -287. PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE . · | $2,637,750 | $2,942,104 | UNIFIED SERVICES OF TEXAS, INC. | +11.5% | 3 |
| Jan 19, 2017 | 170007SSR-207C(067)SR | Ssr-207c(070)sr |
BRYAN RESURFACE (ASPHALT ) SH-78: FROM THE RED RIVER , EXTEND NORTH NEAR THE TEXAS STATE LINE. PROJECT LENGTH = 15.58 MILES · | $3,762,736 | $2,383,318 | OVERLAND CORPORATION | -36.7% | 3 |
| Jan 19, 2017 | 170023SSR-232B(051)SR | Ssr-232b(052)sr |
HUGHES RESURFACE (ASPHALT ) US-270: FROM 0.25 MILES WEST OF US -75, EXTEND EAST IN CALVIN . PROJECT LENGTH = 10.730 MILES · | $2,741,393 | $2,002,094 | GLOVER & ASSOCIATES, INC. | -27.0% | 5 |
| Jan 19, 2017 | 170029STP-244E(054)UR | Mcclain Division 3 |
SAFETY IMPROVEMENT (SIDEWALKS , LIGHTING AND LANDSCAPE ) CITY STREET (GREEN AVENUE ): FROM WASHINGTON AVENUE , EXTEND NORTH IN PURCELL . PROJECT LENGTH = 1.065 MILES · | $1,838,170 | $1,972,840 | Tri-City Seal Company, Inc. TCS General Contractors | +7.3% | 3 |
| Jan 19, 2017 | 170015SSR-219B(053)SR | Creek, Pawnee |
RESURFACE (ASPHALT ) SH-48: FROM THE SH -51 JUNCTION, EXTEND NORTH NEAR MANNFORD . PROJECT LENGTH = 6.990 MILES · | $2,286,403 | $1,972,305 | APAC-CENTRAL, INC. | -13.7% | 5 |
| Jan 19, 2017 | 170056STPY-175C(109) | Washita Division 5 |
BRIDGE AND APPROACHES SH -152: OVER TRAIL CREEK , 4.2 MILES EAST OF THE BECKHAM COUNTY LINE . PROJECT LENGTH = 0.342 MILE · | $2,041,058 | $1,770,140 | K & R BUILDERS, INC. | -13.3% | 5 |
| Jan 19, 2017 | 170014SSR-216B(064)SR | Comanche Division 7 |
RESURFACE (ASPHALT ) SH-36: FROM THE TILLMAN COUNTY LINE , EXTEND NORTHEAST NEAR CHATTANOOGA . PROJECT LENGTH = 5.34 MILES · | — | $1,461,600 | MARKWELL PAVING COMPANY, INC. | 4 | |
| Jan 19, 2017 | 170018SSR-129C(045)SR | Harmon Division 5 |
RESURFACE (ASPHALT ) SH-30: FROM THE US -62 JUNCTION, EXTEND NORTH IN HOLLIS . PROJECT LENGTH = 8.00 MILES · | $1,721,365 | $1,447,468 | OVERLAND CORPORATION | -15.9% | 6 |
| Jan 19, 2017 | 170032SSR-249N(026)SR | Mayes Division 8 |
RESURFACE (ASPHALT ) US-69: FROM 0.88 MILES NORTH OF SH -20, EXTEND NORTH NEAR PRYOR . PROJECT LENGTH = 7.990 MILES · | — | $1,361,195 | APAC-CENTRAL, INC. | 4 | |
| Jan 19, 2017 | 170003SSR-204N(022)SR | Beaver Division 6 |
RESURFACE (ASPHALT ) US-270: FROM 12.00 MILES WEST OF THE HARPER COUNTY LINE , EXTEND EAST NEAR SLAPOUT . PROJECT LENGTH = 4.700 MILES · | — | $1,287,937 | J & R SAND COMPANY, INC. | 3 | |
| Jan 19, 2017 | 170010CIRB-212C(028)RB | Choctaw Division 2 |
RESURFACE (ASPHALT ) COUNTY ROAD (NS-436): FROM US-70, EXTEND NORTH IN FORT TOWSON . PROJECT LENGTH = 3.00 MILES · | $1,360,875 | $1,283,916 | THE CUMMINS CONSTRUCTION CO., INC. | -5.7% | 2 |
| Jan 19, 2017 | 170025SSR-234N(040)SR | Jefferson |
RESURFACE (ASPHALT ) US-81: FROM THE US -70 JUNCTION, EXTEND NORTH IN WAURIKA . PROJECT LENGTH = 5.00 MILES · | $1,726,378 | $1,267,428 | OVERLAND CORPORATION | -26.6% | 3 |
| Jan 19, 2017 | 170020SSR-231B(028)SR | Haskell Division 1 |
RESURFACE (ASPHALT ) SH-9: FROM 5.48 MILES EAST OF SH -2, EXTEND EAST NEAR STIGLER . PROJECT LENGTH = 3.062 MILES · | — | $1,261,310 | JOB CONSTRUCTION CO., INC. | 2 | |
| Jan 19, 2017 | 170026STP-239C(026)CI | Latimer Division 2 |
GRADE, DRAIN, AND SURFACE COUNTY ROAD (DRUMB ROAD): FROM THE PITTSBURG COUNTY LINE, EXTEND NORTHEAST NEAR WILBURTON . PROJECT LENGTH = 1.174 MILES · | — | $1,055,045 | GLOVER & ASSOCIATES, INC. | 3 | |
| Jan 19, 2017 | 170016STP-221D(001)CI | Delaware Division 8 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-462/CHEROKEE STREET): OVER WOLF CREEK, 1.94 MILES NORTH OF SH -10/SH-25 IN GROVE. PROJECT LENGTH = 0.369 MILE · | $1,183,224 | $1,043,965 | RRY SERVICES LLC | -11.8% | 4 |
| Jan 19, 2017 | 170028STP-243C(021)SS | Love Division 7 |
BRIDGE AND APPROACHES US -77: OVER CLOUDS BRANCH CREEK, 3.7 MILES SOUTH OF THE SH-32 JUNCTION NEAR MARIETTA . PROJECT LENGTH = 0.043 MILE · | $1,251,115 | $1,038,300 | Silver Star Construction Company, Inc. | -17.0% | 5 |
| Jan 19, 2017 | 170027STP-142D(045)CI | Logan Division 4 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-69/W. 92ND STREET): OVER BEAVER CREEK , 0.6 MILES WEST OF THE PAYNE COUNTY LINE . PROJECT LENGTH = 0.302 MILE · | $1,048,101 | $1,015,191 | K & R BUILDERS, INC. | -3.1% | 7 |
| Jan 19, 2017 | 170057STP-277C(033)CI | Woodward Division 6 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-21): OVER TRADERS CREEK , 3.5 MILES EAST OF THE HARPER COUNTY LINE . PROJECT LENGTH = 0.331 MILE · | $1,033,881 | $1,000,551 | SEWELL BROS., INC. | -3.2% | 6 |
| Jan 19, 2017 | 170045STP-265C(016)CI | Roger Mills Division 5 |
RESURFACE (ASPHALT ) COUNTY ROAD (NS-182/EW-093): FROM SH-47, EXTEND NORTH ON NS-182 THEN WEST ON EW -093 NEAR CHEYENNE. PROJECT LENGTH = 3.030 MILES · | $1,318,611 | $968,211 | CASWELL CONSTRUCTION, INC. | -26.6% | 3 |
| Jan 19, 2017 | 170044SSR-258C(025)SR | Ottawa Division 8 |
RESURFACE (ASPHALT ) SH-10: FROM 0.1 MILES SOUTH OF US-60, EXTEND SOUTH NEAR WYANDOTTE . PROJECT LENGTH = 5.280 MILES · | — | $928,218 | APAC-CENTRAL, INC. | 4 | |
| Jan 19, 2017 | 170034SSR-252C(001)SR | Noble Division 4 |
RESURFACE (ASPHALT ) SH-164: FROM THE GARFIELD COUNTY LINE , EXTEND EAST NEAR LUCIEN . PROJECT LENGTH = 5.020 MILES · | — | $915,057 | Evans & Associates Construction Co., Inc. | 4 | |
| Jan 19, 2017 | 170002SSR-203C(062)SR | Atoka Division 2 |
RESURFACE (ASPHALT ) SH-7: FROM THE JOHNSTON COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 5.790 MILES · | $1,199,720 | $733,183 | OVERLAND CORPORATION | -38.9% | 3 |
| Jan 19, 2017 | 170060HSIP-261N(064)TR | Hsip-261n(065)tr |
PITTSBURG TRAFFIC SIGNALS US-270: FROM 'A' STREET, EXTEND EAST IN THE CITY OF MCALESTER . PROJECT LENGTH = 1.628 MILES · | $771,142 | $732,269 | TRAFFIC & LIGHTING SYSTEMS, LLC | -5.0% | 3 |
| Jan 19, 2017 | 170059STP-208C(055)CI | Caddo Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-114): OVER SUGAR CREEK, 0.5 MILES EAST OF US-281/SH-8 IN LOOKEBA. PROJECT LENGTH = 0.217 MILE · | — | $679,231 | K & R BUILDERS, INC. | 5 | |
| Jan 19, 2017 | 170017SSR-225C(065)SR | Garvin Division 3 |
RESURFACE (ASPHALT ) SH-17A: FROM I-35, EXTEND EAST NEAR WYNNEWOOD . PROJECT LENGTH = 3.171 MILES · | — | $668,334 | Pavers, Inc. | 6 | |
| Jan 19, 2017 | 170006CIRB-207C(055)RB | Bryan Division 2 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-3710/BRYAN ROAD ): OVER LITTLE BLUE RIVER, 1.2 MILES SOUTH OF SH-78 NEAR DURANT. PROJECT LENGTH = 0.227 MILE · | $782,247 | $648,552 | HUB Construction, Inc. | -17.1% | 7 |
| Jan 19, 2017 | 170058SSR-277B(037)SR | Woodward Division 6 |
RESURFACE (ASPHALT ) SH-34: FROM 2.70 MILES NORTH OF THE DEWEY COUNTY LINE EXTEND NORTH NEAR WOODWARD . PROJECT LENGTH = 5.80 MILES · | $763,945 | $632,094 | CASWELL CONSTRUCTION, INC. | -17.3% | 3 |
| Jan 19, 2017 | 170043SSR-258N(024)SR | Ottawa Division 8 |
RESURFACE (ASPHALT ) US-69NW/US-69NE: FROM THE SH -10 JCT, EXTEND NORTH IN MIAMI . SH-10: FROM 0.25 MILES WEST OF US -69 EXTEND EAST IN MIAMI . PROJECT LENGTH = 5.28 MILES · | $658,273 | $598,895 | Paragon Contractors, LLC | -9.0% | 4 |
| Jan 19, 2017 | 170039HSIPIG-299I(132)TR | Oklahoma Division 4 |
SAFETY IMPROVEMENT (SIGNING) I-35: FROM THE TEXAS STATE LINE , EXTEND NORTH . I-40: FROM THE TEXAS STATE LINE , EXTEND EAST. · | $632,838 | $536,000 | Direct Traffic Control, Inc. | -15.3% | 4 |
| Jan 19, 2017 | 170049SSR-268C(039)SR | Sequoyah Division 1 |
SHOULDER REHABILITATION (ASPHALT ) US-64/SH-10: FROM THE SH -100 JUNCTION, EXTEND EAST NEAR GORE. PROJECT LENGTH = 9.784 MILES · | $648,673 | $505,271 | GLOVER & ASSOCIATES, INC. | -22.1% | 3 |
| Jan 19, 2017 | 170008SSR-208B(054)SR | Caddo Division 7 |
RESURFACE (ASPHALT ) US-62: FROM 0.86 MILES SOUTH OF SH-19, EXTEND EAST IN APACHE . PROJECT LENGTH = 1.410 MILES · | — | $499,747 | MARKWELL PAVING COMPANY, INC. | 3 | |
| Jan 19, 2017 | 170041NHPP-257N(053)SS | Osage Division 8 |
BRIDGE REPAIR US -60: OVER UNNAMED CREEK, 2.0 MILES EAST OF THE SH -18 JUNCTION NEAR BURBANK. · | $374,035 | $424,987 | B & B BRIDGE COMPANY, LLC | +13.6% | 6 |
| Jan 19, 2017 | 170046STP-266C(047)CI | Rogers Division 8 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-46): OVER TRIBUTARY TO SEMINOLE CREEK , 0.4 MILES WEST OF THE MAYES COUNTY LINE . PROJECT LENGTH = 0.160 MILE · | $474,973 | $415,934 | RRY SERVICES LLC | -12.4% | 6 |
| Jan 19, 2017 | 170024SSR-233C(030)SR | Jackson Division 5 |
RESURFACE (ASPHALT ) SH-19: FROM US-283/SH-6, EXTEND EAST IN THE TOWN OF BLAIR . PROJECT LENGTH = 1.60 MILES · | $413,893 | $362,213 | CASWELL CONSTRUCTION, INC. | -12.5% | 6 |
| Jan 19, 2017 | 170036NHPPI-2400-(002)SS | Oklahoma Division 4 |
BRIDGE REHABILITATION I -240: OVER CROOKED OAK CREEK, 0.8 MILES EAST OF THE I -35 INTERCHANGE IN OKLAHOMA CITY . PROJECT LENGTH = 0.025 MILE · | $396,300 | $345,585 | Redlands Contracting, LLC | -12.8% | 8 |
| Jan 19, 2017 | 170055SBR-273C(037)SB | Wagoner Division 1 |
BRIDGE REHABILITATION US -64: OVER MOUNTAIN CREEK , 0.4 MILES SOUTHEAST OF THE TULSA COUNTY LINE NEAR BIXBY . · | $532,175 | $336,315 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION | -36.8% | 4 |
| Jan 19, 2017 | 170019STP-230F(018)3B | Harper, Major |
JOINT SEAL/REPAIR US-270/SH-58: AT MULTIPLE LOCATIONS IN DIVISION VI. · | $204,080 | $289,492 | PBX Corporation | +41.9% | 2 |
| Jan 19, 2017 | 170005STP-207D(029)CI | Bryan Division 2 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-200): OVER STRAIGHT CREEK , 3.5 MILES EAST OF SH-22 NEAR CADDO. PROJECT LENGTH = 0.082 MILE · | $392,022 | $268,608 | HUB Construction, Inc. | -31.5% | 7 |
| Jan 19, 2017 | 170030SSP-245N(048)RW | Mccurtain Division 2 |
RIGHT-OF-WAY CLEARANCE US-70: FROM 2.5 MILES EAST OF THE CHOCTAW COUNTY LINE , EXTEND EAST NEAR VALIANT . PROJECT LENGTH = 4.60 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE . · | $178,000 | $122,222 | Robin Hausner Demolition, LLC | -31.3% | 7 |
1–42 of 42
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.