RESURFACE (ASPHALT ) SH-30: FROM THE US -62 JUNCTION, EXTEND NORTH IN HOLLIS . PROJECT LENGTH = 8.00 MILES
- Let date
- Thursday, January 19, 2017
- Contract
- 170018
- J/P numbers
- 27542(04)
- District
- Division 5
- County
- Harmon
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-30: FROM THE US -62 JUNCTION, EXTEND NORTH IN HOLLIS . PROJECT LENGTH = 8.00 MILES
- Project number
- SSR-129C(045)SR
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,721,365 | ||
| 1 | OVERLAND CORPORATION Low bidder | $1,447,468 | -15.9% | |
| 2 | CASWELL CONSTRUCTION, INC. | $1,493,082 | -13.3% | +3.2% |
| 3 | CORNELL CONSTRUCTION COMPANY, INC. | $1,591,738 | -7.5% | +10.0% |
| 4 | APAC-CENTRAL, INC. | $1,817,599 | +5.6% | +25.6% |
| 5 | RK Hall Construction | $2,128,328 | +23.6% | +47.0% |
| 6 | MARKWELL PAVING COMPANY, INC. | $2,256,000 | +31.1% | +55.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 OVERLAND CORPOR… | #2 CASWELL CONSTRU… | #3 CORNELL CONSTRU… | #4 APAC-CENTRAL, I… | #5 RK Hall Constru… | #6 MARKWELL PAVING… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 411(C) 5950 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 17,822 | TON | $85.00 | $72.75 | $76.57 | $83.61 | $95.00 | $112.18 | $100.00 |
| 2 | 412 5267 | COLD MILLING PAVEMENT | 21,920 | SY | $6.00 | $1.35 | $3.48 | $1.67 | $2.65 | $3.80 | $10.00 |
| 3 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 107,500 | LF | $0.6500 | $0.3500 | $0.4200 | $0.3600 | $0.3500 | $0.3700 | $1.00 |
| 4 | 856(A) 8555 | TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 120 | LF | $5.00 | $10.00 | $17.36 | $15.00 | $10.80 | $10.50 | $17.50 |
| 5 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $4,500.00 | $82,500.00 | $4,936.87 | $24,534.60 | $27,500.00 | $4,725.00 | $145,000.00 |