RESURFACE (ASPHALT ) SH-19: FROM US-283/SH-6, EXTEND EAST IN THE TOWN OF BLAIR . PROJECT LENGTH = 1.60 MILES
- Let date
- Thursday, January 19, 2017
- Contract
- 170024
- J/P numbers
- 29644(04)
- District
- Division 5
- County
- Jackson
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-19: FROM US-283/SH-6, EXTEND EAST IN THE TOWN OF BLAIR . PROJECT LENGTH = 1.60 MILES
- Project number
- SSR-233C(030)SR
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $413,893 | ||
| 1 | CASWELL CONSTRUCTION, INC. Low bidder | $362,213 | -12.5% | |
| 2 | APAC-CENTRAL, INC. | $429,807 | +3.8% | +18.7% |
| 3 | CORNELL CONSTRUCTION COMPANY, INC. | $452,013 | +9.2% | +24.8% |
| 4 | T & G CONSTRUCTION, INC. | $481,514 | +16.3% | +32.9% |
| 5 | MARKWELL PAVING COMPANY, INC. | $616,025 | +48.8% | +70.1% |
| 6 | RK Hall Construction | $636,733 | +53.8% | +75.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CASWELL CONSTRU… | #2 APAC-CENTRAL, I… | #3 CORNELL CONSTRU… | #4 T & G CONSTRUCT… | #5 MARKWELL PAVING… | #6 RK Hall Constru… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 411(C) 5950 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 4,103 | TON | $85.00 | $80.14 | $94.00 | $99.50 | $100.00 | $115.00 | $141.90 |
| 2 | 412 5267 | COLD MILLING PAVEMENT | 7,658 | SY | $6.00 | $2.18 | $2.85 | $2.28 | $5.50 | $10.00 | $5.25 |
| 3 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 22,600 | LF | $0.6500 | $0.5600 | $0.5000 | $0.5000 | $0.7500 | $1.00 | $0.4800 |
| 4 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $4,500.00 | $4,047.85 | $11,000.00 | $15,004.04 | $12,145.00 | $45,000.00 | $3,465.00 |