Bid tab 180083

Let Feb 15, 2018 · Division 8 · Creek Sign up free

‹ Feb 2018 results

RESURFACE (ASPHALT ) SH-99: FROM THE SH -51 JUNCTION, EXTEND NORTH NEAR OILTON . PROJECT LENGTH = 3.02 MILES

Let date
Thursday, February 15, 2018
Contract
180083
J/P numbers
31356(04)
District
Division 8
County
Creek
Highway
Limits
RESURFACE (ASPHALT ) SH-99: FROM THE SH -51 JUNCTION, EXTEND NORTH NEAR OILTON . PROJECT LENGTH = 3.02 MILES
Project number
STP-219B(062)3P

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$621,938
1 THE QUAPAW COMPANY Low bidder $565,377 -9.1%
2 BECCO CONTRACTORS, INC. $569,000 -8.5% +0.6%
3 SHERWOOD CONSTRUCTION CO., INC. $577,596 -7.1% +2.2%
4 APAC-CENTRAL, INC. $579,659 -6.8% +2.5%
5 Paragon Contractors, LLC $683,683 +9.9% +20.9%
6 GLOVER & ASSOCIATES, INC. $694,096 +11.6% +22.8%
7 HASKELL LEMON CONSTRUCTION CO. $882,557 +41.9% +56.1%

Bid tab: unit prices 12 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 THE QUAPAW COMP…#2 BECCO CONTRACTO…#3 SHERWOOD CONSTR…#4 APAC-CENTRAL, I…#5 Paragon Contrac…#6 GLOVER & ASSOCI…#7 HASKELL LEMON C…
1303(A) 2100 AGGREGATE BASE TYPE A186CY $50.00 $75.00 $25.00 $50.52 $40.00 $90.00 $52.25 $279.00
2407(B) 0250 TACK COAT3,904GAL $2.60 $3.00 $2.00 $4.19 $1.90 $2.15 $1.90 $4.30
3411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)5,703TON $68.00 $67.15 $67.00 $71.20 $77.00 $85.00 $86.00 $89.50
4411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)133TON $58.00 $110.00 $67.00 $70.50 $77.00 $144.00 $90.00 $100.00
5411(H) 6210 SUPERPAVE, TYPE S3(PATCH)(PG64-22OK)141TON $120.00 $140.00 $50.00 $104.36 $70.00 $119.00 $150.00 $350.00
6411(I) 6310 SUPERPAVE, TYPE S4(PATCH)(PG64-22OK)94TON $120.00 $140.00 $55.00 $115.46 $77.00 $139.00 $170.00 $450.00
7412 5267 COLD MILLING PAVEMENT50,555SY $2.00 $1.25 $1.30 $1.16 $1.10 $1.50 $1.50 $2.15
8856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)59,400LF $0.7500 $0.4700 $0.3500 $0.3700 $0.3500 $0.3500 $0.4500 $0.3500
9856(A) 8555 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE)64LF $10.30 $24.00 $9.00 $8.88 $20.50 $8.50 $11.71 $8.40
10856(B) 8860 TRAFFIC STRIPE(MULTI-POLY.)(ARROWS)3EA $150.00 $210.00 $150.00 $111.02 $203.00 $106.00 $175.67 $105.00
11880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $12,000.00 $5,071.00 $12,322.50 $3,330.69 $8,000.00 $5,000.00 $5,562.85 $12,000.00
12641 1552 MOBILIZATION1LSUM $20,000.00 $10,880.00 $53,450.00 $25,989.85 $12,000.00 $22,312.90 $28,000.00 $56,171.45