Sample data. This job, estimate, costs and market are made up so you can see a finished review. Live reviews are open to pilot teams and paid plans.
$3,168,000Current bid total
All 11 lines priced
$2,800,000Estimated total cost
incl. $150,000 overhead, contingency and other
$2,947,368.43Minimum bid at 5% margin
Bid total clears it by $220,632
$2,950,000Your target bid
5.08% margin at this price
At $2,900,000
- Price used
- $2,900,000.00 (your scenario price)
- Margin at this price
- 3.45% target 5%
- Max allowable cost
- $2,755,000.00 = price × (1 − margin)
- Cost reduction needed
- $45,000.00
Minimum bid = estimated cost ÷ (1 − target margin), rounded up to the cent. Margin is measured on revenue.
Review items, by dollar impact 11
Market variance is your unit price minus the quantity-weighted average low bid, times the job quantity. It is a pricing difference, not a verified cost saving. Priced below your unit cost uses your own costs.
| # | Item | Qty | Your price | Reference | $ impact | Evidence |
|---|---|---|---|---|---|---|
| 1 | 432-6002 RIPRAP (CONC)(5 IN)Market variance · row 9 | 1,250 CY | $690.00 | $612.00avg low | +$97,500above +12.7% | 46 low bids, newest Oct 7, 2026 SAMPLE-1042 Oct 7, 2026 @ $612.00 SAMPLE-0977 Aug 5, 2026 @ $980.00 |
| 2 | 247-6041 FL BS (CMP IN PLC)(TY A GR 1-2)(FNAL POS)Market variance · row 6 | 9,500 CY | $48.00 | $44.20avg low | +$36,100above +8.6% | 27 low bids, newest Oct 7, 2026 SAMPLE-1042 Oct 7, 2026 @ $44.20 SAMPLE-0977 Aug 5, 2026 @ $66.00 |
| 3 | 341-6070 D-GR HMA TY-B PG64-22Market variance · row 7 | 6,200 TONS | $78.00 | $83.50avg low | -$34,100below -6.6% | 19 low bids, newest Aug 5, 2026 SAMPLE-1042 Oct 7, 2026 @ $83.50 SAMPLE-0977 Aug 5, 2026 @ $104.00 |
| 4 | 132-6006 EMBANKMENT (FINAL)(DENS CONT)(TY C)Market variance · row 5 | 22,000 CY | $11.25 | $12.40avg low | -$25,300below -9.3% | 33 low bids, newest Sep 2, 2026 SAMPLE-1042 Oct 7, 2026 @ $12.40 SAMPLE-0977 Aug 5, 2026 @ $24.00 |
| 5 | 360-6003 CONC PVMT (CONT REINF - CRCP)(10")Market variance · row 8 | 4,800 SY | $92.00 | $88.10avg low | +$18,720above +4.4% | 12 low bids, newest Jun 3, 2026 SAMPLE-1042 Oct 7, 2026 @ $88.10 SAMPLE-0977 Aug 5, 2026 @ $121.00 |
| 6 | 110-6001 EXCAVATION (ROADWAY)Market variance · row 4 | 18,000 CY | $9.50 | $8.75avg low | +$13,500above +8.6% | 52 low bids, newest Oct 7, 2026 SAMPLE-1042 Oct 7, 2026 @ $8.75 SAMPLE-0977 Aug 5, 2026 @ $19.00 |
| 7 | 6185-6002 TMA (STATIONARY)Market variance · row 12 | 220 DAY | $410.00 | $465.00avg low | -$12,100below -11.8% | 3 low bids, newest May 1, 2024 thin data SAMPLE-1042 Oct 7, 2026 @ $465.00 SAMPLE-0977 Aug 5, 2026 @ $520.00 |
| 8 | 500-6001 MOBILIZATIONMarket variance · row 2 | 1 LS | $150,000.00 | $138,000.00avg low | +$12,000above +8.7% | 41 low bids, newest Oct 7, 2026 SAMPLE-1042 Oct 7, 2026 @ $138,000.00 SAMPLE-0977 Aug 5, 2026 @ $410,000.00 |
| 9 | 464-6003 RC PIPE (CL III)(18 IN)Market variance · row 10 | 2,100 LF | $82.00 | $79.40avg low | +$5,460above +3.3% | 30 low bids, newest Sep 2, 2026 SAMPLE-1042 Oct 7, 2026 @ $79.40 SAMPLE-0977 Aug 5, 2026 @ $130.00 |
| 10 | 502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLINGMarket variance · row 3 | 12 MO | $6,500.00 | $6,100.00avg low | +$4,800above +6.6% | 38 low bids, newest Oct 7, 2026 SAMPLE-1042 Oct 7, 2026 @ $6,100.00 SAMPLE-0977 Aug 5, 2026 @ $14,000.00 |
| 11 | 666-6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL)Market variance · row 11 | 14,000 LF | $1.10 | $0.9200avg low | +$2,520above +19.6% | 61 low bids, newest Oct 7, 2026 SAMPLE-1042 Oct 7, 2026 @ $0.9200 SAMPLE-0977 Aug 5, 2026 @ $1.80 |
Estimate lines 11
Blank prices stay blank and are counted as unpriced, never as $0.| Row | Bid code | Description | Qty | Unit price | Amount | Unit cost | Market | Status |
|---|---|---|---|---|---|---|---|---|
| 2 | 500-6001 | MOBILIZATIONCSJ 9999-01-001 · seq 1 | 1 LS | $150,000.00 | $150,000 | $140,500.00 | $138,000.00 | Matched |
| 3 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLINGCSJ 9999-01-001 · seq 2 | 12 MO | $6,500.00 | $78,000 | $6,000.00 | $6,100.00 | Matched |
| 4 | 110-6001 | EXCAVATION (ROADWAY)CSJ 9999-01-001 · seq 3 | 18,000 CY | $9.50 | $171,000 | $8.10 | $8.75 | Quantity differs from the schedule |
| 5 | 132-6006 | EMBANKMENT (FINAL)(DENS CONT)(TY C)CSJ 9999-01-001 · seq 4 | 22,000 CY | $11.25 | $247,500 | $8.40 | $12.40 | Matched |
| 6 | 247-6041 | FL BS (CMP IN PLC)(TY A GR 1-2)(FNAL POS)CSJ 9999-01-001 · seq 5 | 9,500 CY | $48.00 | $456,000 | $37.00 | $44.20 | Matched |
| 7 | 341-6070 | D-GR HMA TY-B PG64-22CSJ 9999-01-001 · seq 6 | 6,200 TONS | $78.00 | $483,600 | $64.50 | $83.50 | Matched |
| 8 | 360-6003 | CONC PVMT (CONT REINF - CRCP)(10")CSJ 9999-01-001 · seq 7 | 4,800 SY | $92.00 | $441,600 | $84.00 | $88.10 | Matched |
| 9 | 432-6002 | RIPRAP (CONC)(5 IN)CSJ 9999-01-001 · seq 8 | 1,250 CY | $690.00 | $862,500 | $560.00 | $612.00 | Matched |
| 10 | 464-6003 | RC PIPE (CL III)(18 IN)CSJ 9999-01-001 · seq 9 | 2,100 LF | $82.00 | $172,200 | $74.00 | $79.40 | Matched |
| 11 | 666-6036 | REFL PAV MRK TY I (W)8"(SLD)(100MIL)CSJ 9999-01-001 · seq 1 | 14,000 LF | $1.10 | $15,400 | $0.9500 | $0.9200 | Matched |
| 12 | 6185-6002 | TMA (STATIONARY)CSJ 9999-01-001 · seq 11 | 220 DAY | $410.00 | $90,200 | $380.00 | $465.00thin | Unit does not match |
| Included lines: 11 (11 priced) | $3,168,000 | $3,048,900 | ||||||