Sample data: a made-up job, estimate and market so you can see a finished review Sign up free
Sample data. This job, estimate, costs and market are made up so you can see a finished review. Live reviews are open to pilot teams and paid plans.

Excel review packet

$3,168,000Current bid total All 11 lines priced
$2,800,000Estimated total cost incl. $150,000 overhead, contingency and other
$2,947,368.43Minimum bid at 5% margin Bid total clears it by $220,632
$2,950,000Your target bid 5.08% margin at this price

Cost, margin and scenario

Reviewed Nov 20, 2026
Only used with "One total cost". Line costs so far: $2,650,000 on 11 of 11 lines.
Bond, insurance, home office: anything not already in a line.
Blank uses your target bid, then your bid total.

At $2,900,000

Price used
$2,900,000.00 (your scenario price)
Margin at this price
3.45% target 5%
Max allowable cost
$2,755,000.00 = price × (1 − margin)
Cost reduction needed
$45,000.00

Minimum bid = estimated cost ÷ (1 − target margin), rounded up to the cent. Margin is measured on revenue.

Schedule check 3

All resolved

Your estimate against the SAMPLE-0001 schedule (12 rows). Ambiguous and unit-mismatch rows are held out of the totals until you decide. Agency line numbers and alternates are kept.

ExceptionBid codeDetailDecision and note
Unit does not matchRow 12 6185-6002TMA (STATIONARY) Estimate unit EA, schedule unit DAY.
On the schedule, not in the estimateAlternate A1 464-6005RC PIPE (CL III)(24 IN) 1,000 LF · CSJ 9999-01-001 · alternate A1
Quantity differs from the scheduleRow 4 110-6001EXCAVATION (ROADWAY) Estimate 18,000, schedule 18,450 CY.

Review items, by dollar impact 11

Market variance is your unit price minus the quantity-weighted average low bid, times the job quantity. It is a pricing difference, not a verified cost saving. Priced below your unit cost uses your own costs.

#ItemQtyYour priceReference$ impactEvidence
1 432-6002 RIPRAP (CONC)(5 IN)Market variance · row 9 1,250 CY $690.00 $612.00avg low +$97,500above +12.7% 46 low bids, newest Oct 7, 2026
SAMPLE-1042 Oct 7, 2026 @ $612.00
SAMPLE-0977 Aug 5, 2026 @ $980.00
2 247-6041 FL BS (CMP IN PLC)(TY A GR 1-2)(FNAL POS)Market variance · row 6 9,500 CY $48.00 $44.20avg low +$36,100above +8.6% 27 low bids, newest Oct 7, 2026
SAMPLE-1042 Oct 7, 2026 @ $44.20
SAMPLE-0977 Aug 5, 2026 @ $66.00
3 341-6070 D-GR HMA TY-B PG64-22Market variance · row 7 6,200 TONS $78.00 $83.50avg low -$34,100below -6.6% 19 low bids, newest Aug 5, 2026
SAMPLE-1042 Oct 7, 2026 @ $83.50
SAMPLE-0977 Aug 5, 2026 @ $104.00
4 132-6006 EMBANKMENT (FINAL)(DENS CONT)(TY C)Market variance · row 5 22,000 CY $11.25 $12.40avg low -$25,300below -9.3% 33 low bids, newest Sep 2, 2026
SAMPLE-1042 Oct 7, 2026 @ $12.40
SAMPLE-0977 Aug 5, 2026 @ $24.00
5 360-6003 CONC PVMT (CONT REINF - CRCP)(10")Market variance · row 8 4,800 SY $92.00 $88.10avg low +$18,720above +4.4% 12 low bids, newest Jun 3, 2026
SAMPLE-1042 Oct 7, 2026 @ $88.10
SAMPLE-0977 Aug 5, 2026 @ $121.00
6 110-6001 EXCAVATION (ROADWAY)Market variance · row 4 18,000 CY $9.50 $8.75avg low +$13,500above +8.6% 52 low bids, newest Oct 7, 2026
SAMPLE-1042 Oct 7, 2026 @ $8.75
SAMPLE-0977 Aug 5, 2026 @ $19.00
7 6185-6002 TMA (STATIONARY)Market variance · row 12 220 DAY $410.00 $465.00avg low -$12,100below -11.8% 3 low bids, newest May 1, 2024 thin data
SAMPLE-1042 Oct 7, 2026 @ $465.00
SAMPLE-0977 Aug 5, 2026 @ $520.00
8 500-6001 MOBILIZATIONMarket variance · row 2 1 LS $150,000.00 $138,000.00avg low +$12,000above +8.7% 41 low bids, newest Oct 7, 2026
SAMPLE-1042 Oct 7, 2026 @ $138,000.00
SAMPLE-0977 Aug 5, 2026 @ $410,000.00
9 464-6003 RC PIPE (CL III)(18 IN)Market variance · row 10 2,100 LF $82.00 $79.40avg low +$5,460above +3.3% 30 low bids, newest Sep 2, 2026
SAMPLE-1042 Oct 7, 2026 @ $79.40
SAMPLE-0977 Aug 5, 2026 @ $130.00
10 502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLINGMarket variance · row 3 12 MO $6,500.00 $6,100.00avg low +$4,800above +6.6% 38 low bids, newest Oct 7, 2026
SAMPLE-1042 Oct 7, 2026 @ $6,100.00
SAMPLE-0977 Aug 5, 2026 @ $14,000.00
11 666-6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL)Market variance · row 11 14,000 LF $1.10 $0.9200avg low +$2,520above +19.6% 61 low bids, newest Oct 7, 2026
SAMPLE-1042 Oct 7, 2026 @ $0.9200
SAMPLE-0977 Aug 5, 2026 @ $1.80

Estimate lines 11

Blank prices stay blank and are counted as unpriced, never as $0.
RowBid codeDescriptionQtyUnit priceAmountUnit costMarketStatus
2 500-6001 MOBILIZATIONCSJ 9999-01-001 · seq 1 1 LS $150,000.00 $150,000 $140,500.00 $138,000.00 Matched
3 502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLINGCSJ 9999-01-001 · seq 2 12 MO $6,500.00 $78,000 $6,000.00 $6,100.00 Matched
4 110-6001 EXCAVATION (ROADWAY)CSJ 9999-01-001 · seq 3 18,000 CY $9.50 $171,000 $8.10 $8.75 Quantity differs from the schedule
5 132-6006 EMBANKMENT (FINAL)(DENS CONT)(TY C)CSJ 9999-01-001 · seq 4 22,000 CY $11.25 $247,500 $8.40 $12.40 Matched
6 247-6041 FL BS (CMP IN PLC)(TY A GR 1-2)(FNAL POS)CSJ 9999-01-001 · seq 5 9,500 CY $48.00 $456,000 $37.00 $44.20 Matched
7 341-6070 D-GR HMA TY-B PG64-22CSJ 9999-01-001 · seq 6 6,200 TONS $78.00 $483,600 $64.50 $83.50 Matched
8 360-6003 CONC PVMT (CONT REINF - CRCP)(10")CSJ 9999-01-001 · seq 7 4,800 SY $92.00 $441,600 $84.00 $88.10 Matched
9 432-6002 RIPRAP (CONC)(5 IN)CSJ 9999-01-001 · seq 8 1,250 CY $690.00 $862,500 $560.00 $612.00 Matched
10 464-6003 RC PIPE (CL III)(18 IN)CSJ 9999-01-001 · seq 9 2,100 LF $82.00 $172,200 $74.00 $79.40 Matched
11 666-6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL)CSJ 9999-01-001 · seq 1 14,000 LF $1.10 $15,400 $0.9500 $0.9200 Matched
12 6185-6002 TMA (STATIONARY)CSJ 9999-01-001 · seq 11 220 DAY $410.00 $90,200 $380.00 $465.00thin Unit does not match
Included lines: 11 (11 priced)$3,168,000$3,048,900