| 10 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 345 | CY |
$10.00 |
$15.60 |
$15.00 |
$25.00 |
$10.22 |
$20.00 |
$27.45 |
$19.86 |
| 20 | 202(D) 0184 |
UNCLASSIFIED BORROW | 1,608 | CY |
$12.00 |
$15.60 |
$15.00 |
$14.00 |
$12.27 |
$20.00 |
$33.93 |
$22.19 |
| 30 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$10,000.00 |
$2,080.00 |
$2,000.00 |
$12,500.00 |
$5,520.28 |
$2,600.00 |
$8,570.79 |
$3,204.10 |
| 40 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,408 | LF |
$2.00 |
$4.11 |
$4.35 |
$5.00 |
$4.04 |
$2.00 |
$10.54 |
$4.21 |
| 50 | 221(F) 0100 |
TEMPORARY SILT DIKE | 40 | LF |
$15.00 |
$31.08 |
$33.00 |
$24.50 |
$30.55 |
$15.00 |
$9.44 |
$31.82 |
| 60 | 230(A) 2806 |
SOLID SLAB SODDING | 3,021 | SY |
$2.50 |
$2.08 |
$2.48 |
$4.00 |
$2.04 |
$2.05 |
$6.47 |
$2.13 |
| 70 | 307(K) 4300 |
STABILIZED SUBGRADE | 1,077 | SY |
$10.00 |
$9.36 |
$10.00 |
$12.00 |
$9.20 |
$10.00 |
$12.16 |
$10.68 |
| 80 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 10 | TON |
$50.00 |
$119.45 |
$75.00 |
$60.30 |
$15.72 |
$48.00 |
$23.97 |
$70.40 |
| 90 | 407(B) 0250 |
TACK COAT | 400.4 | GAL |
$4.00 |
$4.16 |
$4.40 |
$5.20 |
$5.06 |
$5.00 |
$6.42 |
$5.27 |
| 100 | 408 5774 |
PRIME COAT | 674 | GAL |
$6.00 |
$6.24 |
$6.60 |
$6.50 |
$7.59 |
$6.00 |
$7.78 |
$6.39 |
| 110 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 944 | TON |
$100.00 |
$109.20 |
$127.00 |
$122.96 |
$132.81 |
$160.00 |
$201.60 |
$165.61 |
| 120 | 412 5267 |
COLD MILLING PAVEMENT | 1,033 | SY |
$6.50 |
$18.72 |
$20.00 |
$17.00 |
$16.44 |
$18.00 |
$22.94 |
$18.85 |
| 130 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 993 | SY |
$5.00 |
$5.20 |
$25.00 |
$8.50 |
$13.29 |
$3.50 |
$30.08 |
$19.56 |
| 140 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 592 | LF |
$4.50 |
$2.08 |
$5.00 |
$6.00 |
$4.09 |
$3.00 |
$3.85 |
$3.71 |
| 150 | 619(C) 0924 |
SAWING PAVEMENT | 922 | LF |
$5.00 |
$3.12 |
$5.00 |
$12.00 |
$3.22 |
$3.30 |
$2.20 |
$7.84 |
| 160 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 375 | LF |
$20.00 |
$19.08 |
$20.00 |
$19.26 |
$18.76 |
$19.00 |
$23.79 |
$19.54 |
| 170 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 4 | EA |
$2,400.00 |
$2,496.00 |
$2,640.00 |
$2,550.00 |
$2,453.46 |
$2,450.00 |
$3,111.63 |
$2,556.00 |
| 180 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$2,400.00 |
$1,872.00 |
$1,980.00 |
$2,150.00 |
$1,840.09 |
$2,850.00 |
$2,333.72 |
$1,917.00 |
| 190 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 144 | CY |
$25.00 |
$15.75 |
$20.00 |
$18.00 |
$18.40 |
$60.00 |
$20.58 |
$60.00 |
| 200 | 501(G) 6309 |
CLSM BACKFILL | 126 | CY |
$220.00 |
$153.34 |
$200.00 |
$201.27 |
$190.11 |
$175.00 |
$263.04 |
$220.00 |
| 210 | 504(A) 1304 |
APPROACH SLAB | 307.8 | SY |
$200.00 |
$222.23 |
$220.00 |
$231.23 |
$229.53 |
$210.00 |
$260.72 |
$250.00 |
| 220 | 504(B) 1305 |
SAW-CUT GROOVING | 2,994.1 | SY |
$4.00 |
$4.04 |
$4.25 |
$4.35 |
$4.87 |
$3.90 |
$4.99 |
$4.10 |
| 230 | 504(C) 6250 |
SEALED EXPANSION JOINT | 94.3 | LF |
$275.00 |
$245.90 |
$190.00 |
$291.49 |
$281.52 |
$275.00 |
$284.01 |
$270.00 |
| 240 | 504(D) 6245 |
CONCRETE RAIL (TR4) | 1,224.5 | LF |
$75.00 |
$82.98 |
$85.00 |
$81.50 |
$123.49 |
$62.00 |
$91.81 |
$105.00 |
| 250 | 506(A) 4050 |
STRUCTURAL STEEL M270 GRADE 50W | 679,590 | LB |
$1.75 |
$1.46 |
$1.50 |
$1.84 |
$1.77 |
$2.22 |
$1.79 |
$2.07 |
| 260 | 507(A) 6170 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 18 | EA |
$2,400.00 |
$2,000.85 |
$2,100.00 |
$2,180.63 |
$3,256.90 |
$2,300.00 |
$2,345.22 |
$3,400.00 |
| 270 | 507(B) 6174 |
STAINLESS STEEL EXPANSION BEARING ASSEMBLY | 30 | EA |
$2,400.00 |
$2,000.85 |
$2,100.00 |
$2,180.63 |
$3,256.90 |
$2,300.00 |
$2,345.22 |
$3,400.00 |
| 280 | 509 6152 |
SPECIAL CONCRETE FINISH | 249 | SY |
$100.00 |
$105.00 |
$170.00 |
$126.11 |
$123.96 |
$100.00 |
$127.05 |
$112.52 |
| 290 | 509(A) 1326 |
CLASS AA CONCRETE | 648.3 | CY |
$750.00 |
$648.76 |
$750.00 |
$675.00 |
$787.40 |
$500.00 |
$1,040.05 |
$750.00 |
| 300 | 509(B) 1328 |
CLASS A CONCRETE | 408 | CY |
$750.00 |
$625.01 |
$800.00 |
$800.00 |
$718.10 |
$950.00 |
$1,429.00 |
$1,300.00 |
| 310 | 509(D) 1331 |
CLASS C CONCRETE | 14 | CY |
$650.00 |
$477.34 |
$600.00 |
$350.00 |
$490.37 |
$650.00 |
$664.40 |
$1,350.00 |
| 320 | 511 6306 |
MECHANICAL SPLICES | 2,380 | EA |
$15.00 |
$34.81 |
$17.00 |
$47.62 |
$26.84 |
$35.00 |
$34.88 |
$35.00 |
| 330 | 511(A) 1332 |
REINFORCING STEEL | 9,065 | LB |
$1.00 |
$0.9200 |
$0.9500 |
$1.15 |
$0.9000 |
$1.30 |
$1.03 |
$4.00 |
| 340 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 212,125 | LB |
$1.25 |
$1.02 |
$1.25 |
$1.20 |
$1.10 |
$1.40 |
$1.23 |
$1.30 |
| 350 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 208 | LF |
$35.00 |
$32.25 |
$35.00 |
$33.34 |
$31.44 |
$32.00 |
$27.41 |
$35.00 |
| 360 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 396 | LF |
$45.00 |
$37.25 |
$45.00 |
$35.50 |
$38.80 |
$35.00 |
$34.61 |
$45.00 |
| 370 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 208 | LF |
$15.00 |
$26.25 |
$15.00 |
$16.00 |
$18.21 |
$12.00 |
$53.79 |
$30.00 |
| 380 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 396 | LF |
$15.00 |
$26.25 |
$15.00 |
$14.00 |
$18.37 |
$15.00 |
$28.88 |
$30.00 |
| 390 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 400 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 1,103 | SY |
$5.00 |
$4.20 |
$3.25 |
$4.25 |
$4.09 |
$4.20 |
$5.19 |
$4.26 |
| 410 | 516(A) 6096 |
DRILLED SHAFTS 60" DIAMETER | 356 | LF |
$700.00 |
$890.59 |
$900.00 |
$1,071.72 |
$1,260.82 |
$1,250.00 |
$1,098.89 |
$1,000.00 |
| 420 | 516(C) 6200 |
CROSSHOLE SONIC LOGGING | 10 | EA |
$3,000.00 |
$2,651.25 |
$2,000.00 |
$2,150.00 |
$1,928.93 |
$2,200.00 |
$2,174.89 |
$1,704.00 |
| 430 | 535 6130 |
(SP)CORROSION INHIBITOR(SURFACE APPLIED) | 240 | SY |
$50.00 |
$53.55 |
$60.00 |
$58.00 |
$25.30 |
$48.00 |
$81.14 |
$58.58 |
| 440 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 200 | TON |
$50.00 |
$38.29 |
$41.00 |
$46.50 |
$30.74 |
$36.00 |
$53.87 |
$45.00 |
| 450 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 35 | TON |
$45.00 |
$27.09 |
$41.00 |
$44.00 |
$19.48 |
$26.00 |
$30.19 |
$35.00 |
| 460 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$200,000.00 |
$183,750.00 |
$250,000.00 |
$183,500.00 |
$280,036.18 |
$350,000.00 |
$122,669.96 |
$303,500.00 |
| 470 | 805(D) 8756 |
(PL)REMOVE & RESET EXISTING SIGNS | 2 | EA |
$250.00 |
$104.00 |
$120.00 |
$150.00 |
$102.23 |
$104.00 |
$129.65 |
$106.50 |
| 480 | 823 8478 |
(SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 330 | SD |
$110.00 |
$78.00 |
$82.00 |
$78.75 |
$76.67 |
$77.00 |
$97.24 |
$79.88 |
| 490 | 853 9069 |
GUARDRAIL DELINEATORS(TYPE 2, CODE 1) | 18 | EA |
$20.00 |
$15.60 |
$17.00 |
$16.00 |
$15.33 |
$15.60 |
$19.44 |
$15.98 |
| 500 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 9,040 | LF |
$0.7500 |
$0.7400 |
$0.7300 |
$0.7500 |
$0.7300 |
$0.7500 |
$0.9200 |
$0.7600 |
| 510 | 857(A) 8839 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 2,000 | LF |
$0.1500 |
$0.2600 |
$0.2700 |
$0.2600 |
$0.2600 |
$0.2700 |
$0.3200 |
$0.2700 |
| 520 | 857(C) 8851 |
REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 2,000 | LF |
$1.25 |
$1.04 |
$1.05 |
$1.05 |
$1.02 |
$1.05 |
$1.30 |
$1.07 |
| 530 | 857(E) 8887 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 1,282 | EA |
$1.00 |
$1.04 |
$1.05 |
$1.05 |
$1.02 |
$1.05 |
$1.30 |
$1.07 |
| 540 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 8,800 | LF |
$0.3500 |
$0.1600 |
$0.1700 |
$0.1800 |
$0.1500 |
$0.1700 |
$0.1900 |
$0.1600 |
| 550 | 871(B) 8705 |
(SP)CONST.ZONE IMPACT ATTEN. | 660 | SD |
$12.50 |
$2.60 |
$2.55 |
$2.64 |
$2.56 |
$2.55 |
$3.24 |
$2.66 |
| 560 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 1,700 | LF |
$20.00 |
$23.92 |
$30.00 |
$54.50 |
$25.56 |
$35.00 |
$31.32 |
$19.95 |
| 570 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 1,700 | LF |
$4.25 |
$3.12 |
$3.00 |
$3.50 |
$2.04 |
$3.25 |
$4.32 |
$7.35 |
| 580 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 3,960 | SD |
$0.2500 |
$1.04 |
$1.10 |
$1.05 |
$1.02 |
$1.05 |
$1.30 |
$1.07 |
| 590 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 1,980 | SD |
$1.00 |
$1.04 |
$1.10 |
$1.05 |
$1.02 |
$1.05 |
$1.30 |
$1.07 |
| 600 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 6,270 | SD |
$1.50 |
$0.5200 |
$0.5200 |
$0.5300 |
$0.5100 |
$0.5300 |
$0.6500 |
$0.5300 |
| 610 | 880(C) 8848 |
WING BARRICADES | 1,320 | SD |
$1.50 |
$1.04 |
$1.05 |
$1.05 |
$1.02 |
$1.05 |
$1.30 |
$1.07 |
| 620 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 5,280 | SD |
$0.2500 |
$0.7800 |
$0.7800 |
$0.7900 |
$0.7700 |
$0.7700 |
$0.9700 |
$0.8000 |
| 630 | 880(F) 8878 |
DRUMS | 6,600 | SD |
$0.3000 |
$0.2600 |
$0.2700 |
$0.2800 |
$0.2600 |
$0.2700 |
$0.3200 |
$0.2700 |
| 640 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 990 | SD |
$12.00 |
$5.20 |
$5.20 |
$5.25 |
$5.11 |
$5.20 |
$6.48 |
$5.33 |
| 650 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$30,000.00 |
$8,800.00 |
$7,400.00 |
$10,500.00 |
$8,474.45 |
$16,210.00 |
$42,946.91 |
$7,135.50 |
| 660 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$4,000.00 |
$2,912.00 |
$5,000.00 |
$4,500.00 |
$1,897.26 |
$1,850.86 |
$3,241.27 |
$5,000.00 |
| 670 | 640(A) 1398 |
FIELD OFFICE | 1 | EA |
$5,000.00 |
$10,400.00 |
$7,000.00 |
$12,500.00 |
$3,478.32 |
$13,100.00 |
$8,000.00 |
$24,300.00 |
| 680 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$215,000.00 |
$198,104.92 |
$175,000.00 |
$235,000.00 |
$390,665.65 |
$245,000.00 |
$210,369.06 |
$256,000.00 |