| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$35,000.00 |
$4,737.04 |
$6,500.00 |
$2,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 1,694 | CY |
$12.80 |
$9.81 |
$16.35 |
$18.00 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 1,095 | CY |
$15.00 |
$12.52 |
$16.35 |
$18.00 |
| 4 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$46,700.00 |
$6,902.54 |
$6,500.00 |
$5,000.00 |
| 5 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,582 | LF |
$2.75 |
$5.40 |
$3.00 |
$4.00 |
| 6 | 221(F) 0100 |
TEMPORARY SILT DIKE | 150 | LF |
$11.00 |
$27.00 |
$15.00 |
$20.00 |
| 7 | 221(H) 0450 |
(PL)TEMPORARY INLET SEDIMENT FILTER | 4 | EA |
$400.00 |
$1,211.33 |
$350.00 |
$600.00 |
| 8 | 229 4318 |
DITCH LINER PROTECTION | 384 | LF |
$2.00 |
$13.47 |
$5.00 |
$6.00 |
| 9 | 230(A) 2806 |
SOLID SLAB SODDING | 7,434 | SY |
$4.25 |
$8.05 |
$7.25 |
$7.00 |
| 10 | 233(A) 2817 |
VEGETATIVE MULCHING | 1.9 | AC |
$1,935.00 |
$9,406.40 |
$50.00 |
$2,000.00 |
| 11 | 241 2832 |
MOWING | 3.2 | AC |
$114.75 |
$940.64 |
$50.00 |
$600.00 |
| 12 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 1,009 | CY |
$56.00 |
$49.68 |
$65.00 |
$50.00 |
| 13 | 325 5271 |
SEPARATOR FABRIC | 2,935 | SY |
$1.50 |
$1.40 |
$3.00 |
$3.00 |
| 14 | 326(B) 0100 |
GEOGRID REINFORCEMENT | 2,935 | SY |
$2.50 |
$2.84 |
$5.00 |
$3.00 |
| 15 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 261 | TON |
$33.50 |
$30.76 |
$35.00 |
$35.00 |
| 16 | 407(B) 0250 |
TACK COAT | 731 | GAL |
$3.25 |
$2.62 |
$2.50 |
$4.00 |
| 17 | 408 5774 |
PRIME COAT | 1,610 | GAL |
$3.70 |
$4.23 |
$3.38 |
$4.00 |
| 18 | 411(B) 5935 |
SUPERPAVE, TYPE S3(PG 76-28 OK) | 589 | TON |
$103.00 |
$137.97 |
$116.94 |
$150.00 |
| 19 | 411(C) 5950 |
SUPERPAVE, TYPE S4(PG 76-28 OK) | 850 | TON |
$105.00 |
$159.18 |
$132.61 |
$175.00 |
| 20 | 411(I) 6310 |
SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 100 | TON |
$155.00 |
$194.90 |
$159.37 |
$160.00 |
| 21 | 412 5267 |
COLD MILLING PAVEMENT | 3,200 | SY |
$5.50 |
$6.65 |
$5.91 |
$7.00 |
| 22 | 414(B) 5725 |
DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 865 | SY |
$53.00 |
$51.57 |
$55.00 |
$45.00 |
| 23 | 414(G) 5275 |
P.C. CONCRETE FOR PAVEMENT | 194 | CY |
$185.50 |
$233.27 |
$175.00 |
$175.00 |
| 24 | 501(G) 6315 |
CLSM BACKFILL | 18 | CY |
$145.00 |
$216.25 |
$125.00 |
$350.00 |
| 25 | 509(D) 0325 |
CLASS C CONCRETE | 41 | CY |
$366.00 |
$482.64 |
$350.00 |
$550.00 |
| 26 | 601(A) 0297 |
TYPE I PLAIN RIPRAP | 349 | TON |
$53.00 |
$48.95 |
$55.00 |
$70.00 |
| 27 | 609(A) 0380 |
CONCRETE CURB (8" BARRIER-INTEGRAL) | 900 | LF |
$12.00 |
$21.24 |
$25.75 |
$20.00 |
| 28 | 609(B) 0386 |
1'-8" COMB. CURB & GUTTER (6" MNTBLE-NOTCHED) | 753 | LF |
$30.00 |
$33.80 |
$25.75 |
$45.00 |
| 29 | 610(C) 0608 |
4" CONCRETE DIVIDING STRIP | 902 | SY |
$45.00 |
$66.71 |
$49.00 |
$80.00 |
| 30 | 611(G) 5125 |
INLET CI DES. 3 (2D) | 1 | EA |
$9,650.00 |
$11,764.09 |
$10,000.00 |
$12,000.00 |
| 31 | 611(H) 5330 |
ADD'L DEPTH IN INLET CI DES. 3 | 3 | VF |
$480.00 |
$573.86 |
$1,250.00 |
$500.00 |
| 32 | 613(A) 0583 |
24" R.C.PIPE CLASS IV | 104 | LF |
$85.00 |
$81.22 |
$135.00 |
$900.00 |
| 33 | 613(J) 5915 |
EDGE DRAIN CONDUIT-PERFORATED | 900 | LF |
$7.50 |
$10.39 |
$25.00 |
$25.00 |
| 34 | 613(K) 5916 |
EDGE DRAIN OUTLET LATERAL-NONPERFORATED | 86 | LF |
$10.50 |
$10.39 |
$25.00 |
$42.00 |
| 35 | 613(L) 5730 |
24" PREFAB. CULVERT END SECTION, ROUND | 1 | EA |
$900.00 |
$1,149.88 |
$3,500.00 |
$1,000.00 |
| 36 | 613(Q) 5946 |
OUTLET LATERAL HEADWALL | 2 | EA |
$915.00 |
$993.43 |
$500.00 |
$1,300.00 |
| 37 | 613(W) 4500 |
24" JACKED CONDUIT | 104 | LF |
$65.00 |
$67.08 |
$275.00 |
$525.00 |
| 38 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$19,000.00 |
$15,970.58 |
$12,500.00 |
$5,000.00 |
| 39 | 619(B) 4726 |
REMOVAL OF CURB AND GUTTER | 753 | LF |
$3.25 |
$3.72 |
$10.00 |
$15.00 |
| 40 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 2,598 | SY |
$6.00 |
$5.41 |
$6.00 |
$6.00 |
| 41 | 619(B) 4821 |
REMOVAL OF CONCRETE SLOPE PROTECTION | 226 | SY |
$12.00 |
$13.53 |
$6.00 |
$15.00 |
| 42 | 619(C) 0924 |
SAWING PAVEMENT | 1,759 | LF |
$3.50 |
$3.38 |
$7.50 |
$12.00 |
| 43 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 325 | LF |
$23.00 |
$24.36 |
$20.65 |
$18.00 |
| 44 | 623(F) 8300 |
GUARDRAIL TRAIL END TURNDOWN (31") | 2 | EA |
$890.00 |
$1,624.13 |
$775.00 |
$1,500.00 |
| 45 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 2 | EA |
$2,650.00 |
$2,977.57 |
$2,789.34 |
$2,500.00 |
| 46 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$1,965.00 |
$2,111.36 |
$2,121.00 |
$1,800.00 |
| 47 | 853 9024 |
DELINEATORS(TYPE 1, CODE 1) | 2 | EA |
$15.00 |
$20.31 |
$22.50 |
$20.00 |
| 48 | 871(A) 8325 |
(SP)IMPACT ATTENUATOR | 2 | EA |
$28,500.00 |
$35,223.24 |
$32,500.00 |
$28,000.00 |
| 49 | 202(D) 1302 |
UNCLASSIFIED BORROW | 485.08 | CY |
$12.00 |
$14.89 |
$16.35 |
$20.00 |
| 50 | 325 5271 |
SEPARATOR FABRIC | 389.09 | SY |
$2.25 |
$1.40 |
$5.00 |
$8.00 |
| 51 | 326(B) 0100 |
GEOGRID REINFORCEMENT | 1,033.45 | SY |
$3.20 |
$2.84 |
$5.00 |
$3.00 |
| 52 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 1,895.64 | CY |
$15.00 |
$21.66 |
$16.35 |
$20.00 |
| 53 | 501(F) 6352 |
GRANULAR BACKFILL | 1,358.08 | CY |
$60.00 |
$28.51 |
$65.00 |
$50.00 |
| 54 | 501(G) 6309 |
CLSM BACKFILL | 213.4 | CY |
$200.00 |
$216.25 |
$175.00 |
$300.00 |
| 55 | 502 1000 |
TEMPORARY EARTH RETAINAGE | 1 | LSUM |
$45,000.00 |
$64,559.03 |
$25,000.00 |
$60,000.00 |
| 56 | 504(A) 1304 |
APPROACH SLAB | 208.6 | SY |
$220.00 |
$237.21 |
$210.00 |
$285.00 |
| 57 | 504(B) 1305 |
SAW-CUT GROOVING | 180.6 | SY |
$11.50 |
$13.81 |
$22.00 |
$17.00 |
| 58 | 504(E) 1381 |
CONCRETE PARAPET | 152 | LF |
$230.00 |
$152.99 |
$230.00 |
$250.00 |
| 59 | 504(G) 6390 |
RAPID CURE JOINT SEALANT | 71 | LF |
$200.00 |
$83.51 |
$200.00 |
$28.00 |
| 60 | 509 6152 |
SPECIAL CONCRETE FINISH | 47 | SY |
$100.00 |
$101.51 |
$155.00 |
$65.00 |
| 61 | 509 6386 |
SILICONE CONSTRUCTION JOINT | 35.5 | LF |
$50.00 |
$30.48 |
$75.00 |
$25.00 |
| 62 | 509(B) 1328 |
CLASS A CONCRETE | 108 | CY |
$750.00 |
$753.15 |
$999.00 |
$850.00 |
| 63 | 509(D) 1331 |
CLASS C CONCRETE | 33.2 | CY |
$475.00 |
$511.33 |
$350.00 |
$550.00 |
| 64 | 510(A) 6334 |
RETAINING WALL | 410.7 | SY |
$625.00 |
$718.62 |
$625.00 |
$925.00 |
| 65 | 510(C) 6138 |
SLOPE WALL (5") | 485 | SY |
$125.00 |
$115.79 |
$125.00 |
$115.00 |
| 66 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 14,930 | LB |
$1.50 |
$1.21 |
$1.55 |
$2.00 |
| 67 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 142 | LF |
$35.00 |
$41.93 |
$55.00 |
$45.00 |
| 68 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 142 | LF |
$20.00 |
$16.24 |
$25.00 |
$45.00 |
| 69 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 70 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 558 | SY |
$4.50 |
$5.41 |
$10.00 |
$5.00 |
| 71 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 136 | LF |
$45.00 |
$56.84 |
$7.00 |
$27.00 |
| 72 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 4.8 | GAL |
$125.00 |
$135.34 |
$265.00 |
$100.00 |
| 73 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 70 | SY |
$700.00 |
$947.41 |
$750.00 |
$750.00 |
| 74 | 524(A) 6610 |
(SP)CARBON FIBER-REINFORCED POLYMER | 213.3 | SF |
$90.00 |
$87.97 |
$125.00 |
$110.00 |
| 75 | 535 6130 |
(SP)CORROSION INHIBITOR(SURFACE APPLIED) | 91.4 | SY |
$45.00 |
$43.31 |
$55.00 |
$50.00 |
| 76 | 540 4500 |
(PL)REPAIR BRIDGE ITEMS | 1 | LSUM |
$5,000.00 |
$12,180.95 |
$12,500.00 |
$5,000.00 |
| 77 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 405 | LF |
$40.00 |
$10.39 |
$45.00 |
$30.00 |
| 78 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 90 | LF |
$45.00 |
$10.63 |
$25.00 |
$10.00 |
| 79 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$10,000.00 |
$29,775.65 |
$10,000.00 |
$10,000.00 |
| 80 | 619(B) 2510 |
REMOVAL OF BRIDGE ITEM (TYPE A) | 1 | LSUM |
$20,000.00 |
$19,760.20 |
$10,000.00 |
$10,000.00 |
| 81 | 619(B) 2520 |
REMOVAL OF BRIDGE ITEM (TYPE B) | 1 | LSUM |
$5,000.00 |
$5,684.44 |
$10,000.00 |
$5,000.00 |
| 82 | 619(B) 2530 |
REMOVAL OF BRIDGE ITEM (TYPE C) | 1 | LSUM |
$10,000.00 |
$10,286.13 |
$10,000.00 |
$5,000.00 |
| 83 | 804(A) 2915 |
STRUCTURAL CONCRETE | 0.2 | CY |
$400.00 |
$676.70 |
$220.00 |
$1,000.00 |
| 84 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 15 | SF |
$25.00 |
$74.44 |
$20.00 |
$60.00 |
| 85 | 851(B) 3216 |
2"@3.65 GALV.STEEL PIPE POST | 26 | LF |
$16.00 |
$13.53 |
$20.00 |
$12.00 |
| 86 | 856(A) 8535 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 14,952 | LF |
$0.8500 |
$1.14 |
$0.9500 |
$0.8400 |
| 87 | 857(A) 8839 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 21,472 | LF |
$0.2000 |
$0.2300 |
$0.2500 |
$0.1700 |
| 88 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 21,472 | LF |
$0.2000 |
$0.3500 |
$0.2500 |
$0.2600 |
| 89 | 871(B) 8705 |
(SP)CONST.ZONE IMPACT ATTEN. | 180 | SD |
$2.25 |
$8.12 |
$17.50 |
$6.00 |
| 90 | 871(C) 8709 |
(SP) RELOCATION OF IMPACT ATTENUATOR | 2 | EA |
$575.00 |
$1,015.08 |
$150.00 |
$750.00 |
| 91 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 2,485 | LF |
$22.00 |
$17.80 |
$42.00 |
$15.00 |
| 92 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 2,485 | LF |
$3.60 |
$1.35 |
$10.00 |
$2.00 |
| 93 | 880(A) 8812 |
ARROW DISPLAY(TYPE C) | 180 | SD |
$2.00 |
$1.35 |
$22.00 |
$1.00 |
| 94 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 6,210 | SD |
$0.4000 |
$0.0300 |
$0.7500 |
$0.0200 |
| 95 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 1,080 | SD |
$0.6500 |
$3.38 |
$1.25 |
$2.50 |
| 96 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 1,260 | SD |
$2.25 |
$3.38 |
$2.25 |
$2.50 |
| 97 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 270 | SD |
$1.00 |
$2.71 |
$2.25 |
$2.00 |
| 98 | 880(C) 8848 |
WING BARRICADES | 360 | SD |
$1.75 |
$0.4100 |
$2.25 |
$0.3000 |
| 99 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 1,440 | SD |
$0.5000 |
$0.5400 |
$0.3300 |
$0.4000 |
| 100 | 880(F) 8878 |
DRUMS | 5,400 | SD |
$0.2500 |
$0.5400 |
$0.7500 |
$0.4000 |
| 101 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 180 | SD |
$12.00 |
$21.66 |
$50.00 |
$16.00 |
| 102 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$49,000.00 |
$13,534.39 |
$22,750.00 |
$6,500.00 |
| 103 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$4,500.00 |
$2,030.16 |
$2,250.00 |
$3,500.00 |
| 104 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$114,939.15 |
$164,848.82 |
$125,000.00 |
$100,000.00 |