| 1 | 202(D) 0184 |
UNCLASSIFIED BORROW | 20 | CY |
$40.00 |
$150.00 |
$106.00 |
$40.00 |
$83.00 |
$26.00 |
$330.00 |
| 2 | 230(A) 2806 |
SOLID SLAB SODDING | 500 | SY |
$5.00 |
$7.00 |
$7.37 |
$7.00 |
$3.95 |
$4.11 |
$4.25 |
| 3 | 407(B) 0250 |
TACK COAT | 146 | GAL |
$10.00 |
$8.00 |
$5.30 |
$5.50 |
$5.00 |
$5.20 |
$4.95 |
| 4 | 411(C) 5955 |
SUPERPAVE, TYPE S4(PG 70-28 OK) | 239 | TON |
$175.00 |
$215.00 |
$162.18 |
$224.07 |
$153.00 |
$159.12 |
$215.50 |
| 5 | 412 5267 |
COLD MILLING PAVEMENT | 1,890 | SY |
$9.00 |
$16.70 |
$14.84 |
$20.75 |
$26.00 |
$10.40 |
$10.00 |
| 6 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 454 | LF |
$4.00 |
$6.00 |
$4.24 |
$5.00 |
$6.00 |
$4.00 |
$7.85 |
| 7 | 619(B) 5881 |
REMOVAL OF CONCRETE DITCH LINER | 136 | LF |
$10.00 |
$45.00 |
$9.54 |
$20.00 |
$16.67 |
$10.00 |
$44.30 |
| 8 | 623 0100 |
(PL)GUARDRAIL CURBING | 2 | EA |
$1,500.00 |
$2,000.00 |
$1,800.08 |
$1,603.00 |
$1,500.00 |
$2,500.00 |
$2,027.00 |
| 9 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 325 | LF |
$19.00 |
$22.00 |
$21.20 |
$22.00 |
$20.00 |
$23.00 |
$16.50 |
| 10 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 2 | EA |
$2,250.00 |
$3,900.00 |
$3,710.00 |
$3,850.00 |
$3,500.00 |
$3,400.00 |
$2,457.00 |
| 11 | 623(I) 8675 |
GUARDRAIL BRIDGE CONNECTION-TYPE A | 2 | EA |
$1,800.00 |
$3,000.00 |
$2,862.00 |
$2,970.00 |
$2,700.00 |
$2,300.00 |
$2,160.00 |
| 12 | 623(I) 8690 |
GUARDRAIL BRIDGE CONN-TRAIL END (31") | 2 | EA |
$1,300.00 |
$1,200.00 |
$954.00 |
$990.00 |
$900.00 |
$715.00 |
$1,793.00 |
| 13 | 501(G) 6309 |
CLSM BACKFILL | 83.6 | CY |
$275.00 |
$240.00 |
$228.70 |
$214.00 |
$270.00 |
$300.00 |
$232.50 |
| 14 | 504(A) 1304 |
APPROACH SLAB | 195.6 | SY |
$200.00 |
$269.70 |
$290.58 |
$295.00 |
$266.68 |
$175.00 |
$466.50 |
| 15 | 504(B) 1305 |
SAW-CUT GROOVING | 843.8 | SY |
$5.00 |
$5.75 |
$5.56 |
$5.72 |
$5.20 |
$5.00 |
$5.60 |
| 16 | 504(C) 6250 |
SEALED EXPANSION JOINT | 90 | LF |
$300.00 |
$269.00 |
$382.30 |
$350.00 |
$465.00 |
$474.50 |
$325.50 |
| 17 | 504(D) 6245 |
CONCRETE RAIL (TR4) | 363 | LF |
$125.00 |
$94.00 |
$110.87 |
$97.00 |
$153.48 |
$215.00 |
$148.00 |
| 18 | 506(A) 1322 |
STRUCTURAL STEEL | 13,260 | LB |
$4.00 |
$9.50 |
$7.07 |
$9.44 |
$5.00 |
$9.72 |
$9.25 |
| 19 | 509 5000 |
ELASTOMERIC COATING | 992 | SF |
$15.00 |
$15.00 |
$14.98 |
$15.40 |
$12.50 |
$12.00 |
$15.10 |
| 20 | 509(A) 1326 |
CLASS AA CONCRETE | 162.6 | CY |
$700.00 |
$870.00 |
$891.63 |
$891.00 |
$970.00 |
$1,245.20 |
$961.50 |
| 21 | 509(D) 1331 |
CLASS C CONCRETE | 47.9 | CY |
$560.00 |
$400.00 |
$560.01 |
$560.00 |
$900.00 |
$932.00 |
$772.50 |
| 22 | 511 6306 |
MECHANICAL SPLICES | 478 | EA |
$35.00 |
$31.50 |
$44.26 |
$31.00 |
$40.00 |
$32.00 |
$46.90 |
| 23 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 37,860 | LB |
$1.30 |
$1.15 |
$1.25 |
$1.20 |
$2.00 |
$1.56 |
$2.10 |
| 24 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$25,000.00 |
$60,070.00 |
$38,398.02 |
$39,475.00 |
$30,000.00 |
$37,321.93 |
$38,750.00 |
| 25 | 512(B) 6303 |
COLLECTION AND HANDLING OF WASTE | 1 | LSUM |
$4,000.00 |
$3,350.00 |
$3,290.25 |
$3,400.00 |
$5,000.00 |
$3,198.58 |
$3,321.00 |
| 26 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 246 | SY |
$6.00 |
$6.00 |
$5.35 |
$5.50 |
$5.00 |
$4.00 |
$5.40 |
| 27 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 50 | LF |
$36.00 |
$44.00 |
$42.80 |
$44.00 |
$32.00 |
$32.00 |
$43.20 |
| 28 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 4 | GAL |
$100.00 |
$150.00 |
$53.50 |
$55.00 |
$100.00 |
$80.00 |
$54.00 |
| 29 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 37 | SY |
$700.00 |
$760.00 |
$759.70 |
$799.00 |
$650.00 |
$600.00 |
$766.50 |
| 30 | 523(A) 6550 |
SEALER CRACK PREPARATION | 142 | LF |
$4.50 |
$6.00 |
$5.35 |
$5.50 |
$5.00 |
$4.50 |
$5.40 |
| 31 | 523(B) 6560 |
SEALER RESIN | 1.6 | GAL |
$140.00 |
$230.00 |
$214.00 |
$220.00 |
$200.00 |
$80.00 |
$216.00 |
| 32 | 535 6130 |
(SP)CORROSION INHIBITOR(SURFACE APPLIED) | 90 | SY |
$48.00 |
$50.00 |
$52.43 |
$55.00 |
$42.00 |
$32.00 |
$52.90 |
| 33 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$150,000.00 |
$48,000.00 |
$119,840.00 |
$121,000.00 |
$170,000.00 |
$139,850.00 |
$88,585.00 |
| 34 | 857(A) 8839 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 1,600 | LF |
$0.6000 |
$0.1500 |
$10.60 |
$0.1100 |
$0.1000 |
$0.1500 |
$0.7600 |
| 35 | 857(C) 8851 |
REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 1,000 | LF |
$1.20 |
$1.10 |
$1.06 |
$1.10 |
$1.00 |
$1.20 |
$2.15 |
| 36 | 857(E) 8887 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 1,000 | EA |
$0.7500 |
$1.00 |
$0.8000 |
$0.8300 |
$0.7500 |
$0.7500 |
$1.10 |
| 37 | 871(B) 8705 |
(SP)CONST.ZONE IMPACT ATTEN. | 180 | SD |
$12.00 |
$6.00 |
$5.30 |
$5.50 |
$5.00 |
$5.00 |
$27.00 |
| 38 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 490 | LF |
$31.00 |
$41.00 |
$26.50 |
$42.50 |
$35.00 |
$35.00 |
$21.60 |
| 39 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 490 | LF |
$8.00 |
$5.00 |
$4.24 |
$4.00 |
$2.50 |
$5.00 |
$3.65 |
| 40 | 880(A) 8812 |
ARROW DISPLAY(TYPE C) | 180 | SD |
$10.00 |
$6.00 |
$5.30 |
$5.50 |
$5.00 |
$5.00 |
$9.70 |
| 41 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 2,520 | SD |
$0.9500 |
$1.10 |
$1.06 |
$1.10 |
$1.00 |
$1.00 |
$0.4300 |
| 42 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 2,340 | SD |
$1.25 |
$1.10 |
$1.06 |
$1.10 |
$1.00 |
$1.00 |
$0.4900 |
| 43 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 1,980 | SD |
$2.00 |
$1.15 |
$1.06 |
$1.10 |
$1.00 |
$1.00 |
$1.10 |
| 44 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 900 | SD |
$2.00 |
$0.5000 |
$0.2700 |
$0.2800 |
$0.2500 |
$0.2500 |
$3.25 |
| 45 | 880(C) 8848 |
WING BARRICADES | 360 | SD |
$1.05 |
$0.5000 |
$0.2700 |
$0.2800 |
$0.2500 |
$0.2500 |
$4.30 |
| 46 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 3,240 | SD |
$0.6500 |
$0.2000 |
$0.1100 |
$0.1100 |
$0.1000 |
$0.1000 |
$0.8100 |
| 47 | 880(F) 8878 |
DRUMS | 6,660 | SD |
$0.7500 |
$0.6000 |
$0.5300 |
$0.5500 |
$0.5000 |
$0.5000 |
$0.2200 |
| 48 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 187 | SD |
$20.00 |
$11.00 |
$10.60 |
$11.00 |
$10.00 |
$10.00 |
$21.60 |
| 49 | 413(B) 4863 |
RUMBLE STRIP-METHOD HMA-CYC | 800 | LF |
$1.50 |
$4.00 |
$3.45 |
$3.58 |
$3.25 |
$3.25 |
$2.15 |
| 50 | 853 9066 |
GUARDRAIL DELINEATORS(TYPE 1, CODE 1) | 10 | EA |
$15.50 |
$17.00 |
$15.90 |
$16.50 |
$15.00 |
$15.50 |
$14.30 |
| 51 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 1,340 | LF |
$2.10 |
$2.75 |
$2.65 |
$2.75 |
$2.50 |
$2.50 |
$2.90 |
| 52 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$20,000.00 |
$6,300.00 |
$6,380.00 |
$7,800.00 |
$5,600.00 |
$14,248.00 |
$13,380.00 |
| 53 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$66,119.00 |
$65,000.00 |
$71,648.50 |
$72,500.00 |
$105,000.00 |
$75,089.89 |
$165,127.15 |