Bid tab 200073

Let Feb 20, 2020 · Division 2 · Marshall Sign up free

‹ Feb 2020 results

BRIDGE AND APPROACHES COUNTY ROAD (JOE JOHNSON ROAD/PURSER ROAD): OVER UNNAMED CREEK, 0.8 MILES WEST OF THE SH -99C JUNCTION NEAR OAKLAND. PROJECT LENGTH = 0.112 MILE

Let date
Thursday, February 20, 2020
Contract
200073
J/P numbers
28623(04)
District
Division 2
County
Marshall
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (JOE JOHNSON ROAD/PURSER ROAD): OVER UNNAMED CREEK, 0.8 MILES WEST OF THE SH -99C JUNCTION NEAR OAKLAND. PROJECT LENGTH = 0.112 MILE
Project number
STP-248D(049)CI

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$343,041
1 HUB Construction, Inc. Low bidder $300,482 -12.4%
2 Built Right Construction, LLC $372,318 +8.5% +23.9%
3 RRY SERVICES LLC $412,884 +20.4% +37.4%

Bid tab: unit prices 24 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 HUB Constructio…#2 Built Right Con…#3 RRY SERVICES LLC
1201(A) 0102 CLEARING AND GRUBBING1LSUM $5,000.00 $5,500.00 $7,500.00 $7,500.00
2202(A) 0183 UNCLASSIFIED EXCAVATION510CY $7.50 $13.40 $30.00 $25.00
3202(D) 0184 UNCLASSIFIED BORROW505CY $9.75 $15.00 $25.00 $30.00
4221(C) 2801 TEMPORARY SILT FENCE674LF $4.25 $3.94 $5.00 $6.88
5221(F) 0100 TEMPORARY SILT DIKE63LF $14.50 $12.00 $20.00 $29.88
6230(A) 2806 SOLID SLAB SODDING378SY $3.50 $4.00 $8.00 $23.00
7303(A) 2100 AGGREGATE BASE TYPE A300CY $54.25 $134.00 $120.00 $117.20
8411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)362TON $150.00 $160.00 $158.00 $154.40
9613(B) 4527 21" X 15" CORR. GALV. STEEL PIPE ARCH48LF $70.25 $38.88 $50.00 $85.00
10613(P) 7025 21" X 15" GALV. STEEL CULVERT END SECTION ARCH2EA $350.00 $370.95 $350.00 $675.00
11623(F) 4446 GUARDRAIL ANCHOR UNIT (TYPE A)4EA $2,000.00 $2,349.34 $1,850.00 $2,100.00
12623(F) 5686 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $2,000.00 $1,669.27 $1,850.00 $1,500.00
13202(A) 1301 UNCLASSIFIED EXCAVATION220CY $7.50 $14.00 $20.00 $25.00
14501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED26CY $20.00 $22.00 $35.00 $35.00
15504(D) 6239 CONCRETE RAIL (TR3)62LF $85.00 $100.00 $195.00 $200.00
16509(A) 1326 CLASS AA CONCRETE87.5CY $650.00 $623.00 $790.00 $1,185.00
17511(A) 1332 REINFORCING STEEL14,210LB $1.25 $1.30 $1.75 $1.50
18601(B) 1353 TYPE I-A PLAIN RIPRAP450TON $42.00 $48.00 $60.00 $70.00
19601(C) 1355 TYPE I-A FILTER BLANKET150TON $34.75 $46.00 $35.00 $50.00
20619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $30,000.00 $6,000.00 $10,000.00 $10,000.00
21880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $15,000.00 $3,709.00 $6,000.00 $7,300.00
22642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $15,000.00 $5,000.00 $7,000.00 $5,000.00
23220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,400.00 $2,800.00 $3,500.00 $1,275.00
24641 1399 MOBILIZATION1LSUM $63,954.34 $30,000.00 $48,000.00 $45,000.00