$9.86Avg low bid / CY
$10.33Avg of all bids
$10.73Avg engineer's estimate
117Jobs · 301,081.95 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 22 | 54,453 | $8.03 | $9.66 |
| 2020 | 31 | 74,328.85 | $10.50 | $10.38 |
| 2019 | 35 | 109,179.8 | $11.36 | $11.23 |
| 2018 | 29 | 63,120.3 | $8.09 | $9.83 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Oct 14, 2021 | 210273 | EllisDivision 6 | 1,993 CY | $6.50 | Lopp Construction, LLC |
| Sep 16, 2021 | 210253 | MayesDivision 8 | 1,312 CY | $8.00 | RRY SERVICES LLC |
| Aug 19, 2021 | 210241 | SequoyahDivision 1 | 1,266 CY | $12.60 | Treas Construction Inc |
| Jul 15, 2021 | 210216 | OkmulgeeDivision 1 | 2,900 CY | $6.00 | H & H BRIDGE COMPANY |
| Jun 17, 2021 | 210172 | DeweyDivision 5 | 1,265 CY | $4.00 | Wyatt Contracting |
| May 20, 2021 | 210143 | MurrayDivision 7 | 2,700 CY | $7.70 | OVERLAND CORPORATION |
| May 20, 2021 | 210082 | McclainDivision 3 | 5,030 CY | $8.00 | Silver Star Construction Company, Inc. |
| May 20, 2021 | 200338 | BeckhamDivision 5 | 1,690 CY | $17.00 | OBC, INC. |
| May 20, 2021 | 210143 | MurrayDivision 7 | 306 CY | $16.50 | OVERLAND CORPORATION |
| May 20, 2021 | 210129 | BryanDivision 2 | 740 CY | $30.00 | L & N BRIDGE, LLC |
| May 20, 2021 | 210143 | MurrayDivision 7 | 760 CY | $10.30 | OVERLAND CORPORATION |
| May 20, 2021 | 210133 | EllisDivision 6 | 360 CY | $12.75 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210155 | PushmatahaDivision 2 | 50 CY | $20.00 | B & B CONSTRUCTION SERVICE J.T., INC. |
| May 20, 2021 | 210133 | EllisDivision 6 | 540 CY | $12.70 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 1,590 CY | $8.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Apr 15, 2021 | 210117 | Nhpp-255n(535)pm | 290 CY | $16.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Apr 15, 2021 | 210117 | Nhpp-255n(535)pm | 270 CY | $16.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Apr 15, 2021 | 210102 | CoalDivision 3 | 880 CY | $10.00 | L & N BRIDGE, LLC |
| Apr 15, 2021 | 210115 | NobleDivision 4 | 2,575 CY | $7.00 | SEWELL BROS., INC. |
| Mar 18, 2021 | 210072 | CaddoDivision 7 | 4,179 CY | $2.00 | OVERLAND CORPORATION |
| Mar 18, 2021 | 210086 | PittsburgDivision 2 | 2,450 CY | $20.00 | Robinson Construction, LLC |
| Mar 18, 2021 | 210072 | CaddoDivision 7 | 839 CY | $2.00 | OVERLAND CORPORATION |
| Mar 18, 2021 | 210072 | CaddoDivision 7 | 553 CY | $2.00 | OVERLAND CORPORATION |
| Feb 18, 2021 | 210043 | AlfalfaDivision 6 | 520 CY | $20.00 | K & R BUILDERS, INC. |
| Feb 18, 2021 | 210045 | ClevelandDivision 3 | 9,350 CY | $1.50 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Jan 21, 2021 | 210025 | KingfisherDivision 4 | 4,470 CY | $12.95 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 210005 | AlfalfaDivision 6 | 361 CY | $7.00 | K & R BUILDERS, INC. |
| Jan 21, 2021 | 210005 | AlfalfaDivision 6 | 559 CY | $6.00 | K & R BUILDERS, INC. |
| Jan 21, 2021 | 210008 | CaddoDivision 7 | 3,005 CY | $5.50 | Treas Construction Inc |
| Jan 21, 2021 | 210025 | KingfisherDivision 4 | 200 CY | $18.65 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 210025 | KingfisherDivision 4 | 1,450 CY | $14.35 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 19, 2020 | 200347 | CreekDivision 8 | 110 CY | $15.00 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| Nov 19, 2020 | 200349 | GarvinDivision 3 | 9,993.97 CY | $5.00 | Treas Construction Inc |
| Oct 15, 2020 | 200326 | PushmatahaDivision 2 | 612 CY | $8.00 | L & N BRIDGE, LLC |
| Oct 15, 2020 | 200312 | GreerDivision 5 | 522 CY | $6.15 | K & R BUILDERS, INC. |
| Oct 15, 2020 | 200077 | PottawatomieDivision 3 | 7,450 CY | $5.20 | OVERLAND CORPORATION |
| Oct 15, 2020 | 200316 | Grady, Mcclain | 598 CY | $20.00 | Treas Construction Inc |
| Oct 15, 2020 | 200077 | PottawatomieDivision 3 | 5,450 CY | $5.20 | OVERLAND CORPORATION |
| Oct 15, 2020 | 200321 | OklahomaDivision 4 | 60 CY | $15.00 | Built Right Construction, LLC |
| Sep 17, 2020 | 200280 | JacksonDivision 5 | 1,516 CY | $10.00 | SEWELL BROS., INC. |
| Sep 17, 2020 | 200290 | OsageDivision 8 | 1,330 CY | $6.00 | BRIDGECO CONTRACTORS, INC. |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 498.6 CY | $9.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200265 | LoganDivision 4 | 5,510 CY | $5.00 | Wyatt Contracting |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 825.18 CY | $9.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 2,451.6 CY | $9.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 1,286.97 CY | $9.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 421.69 CY | $9.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200225 | GradyDivision 7 | 3,557 CY | $8.50 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 1,099.71 CY | $9.00 | SEWELL BROS., INC. |
| Jul 23, 2020 | 200248 | Cotton | 455 CY | $10.00 | SEWELL BROS., INC. |
| Jul 23, 2020 | 200251 | HarmonDivision 5 | 264 CY | $9.45 | Frontier Bridge, Inc. |
| Jul 23, 2020 | 200061 | DeweyDivision 5 | 1,887 CY | $4.00 | J & R SAND COMPANY, INC. |
| Jul 23, 2020 | 200260 | AtokaDivision 2 | 4,870 CY | $33.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jul 23, 2020 | 200260 | AtokaDivision 2 | 2,040 CY | $33.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jun 18, 2020 | 200235 | OklahomaDivision 4 | 70 CY | $305.00 | K & R BUILDERS, INC. |
| May 14, 2020 | 200203 | MuskogeeDivision 1 | 1,300 CY | $7.86 | Treas Construction Inc |
| May 14, 2020 | 190376 | WashingtonDivision 8 | 31 CY | $53.00 | Paragon Contractors, LLC |
| May 14, 2020 | 200203 | MuskogeeDivision 1 | 510 CY | $10.70 | Treas Construction Inc |
| May 14, 2020 | 200213 | TexasDivision 6 | 468 CY | $10.00 | KLAVER CONSTRUCTION COMPANY, INC. |
| May 14, 2020 | 200214 | Stp-266d(065)ci | 640 CY | $15.00 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| May 14, 2020 | 200190 | Cirb-210d(071)rb | 1,790 CY | $3.68 | Treas Construction Inc |
| May 14, 2020 | 200201 | MurrayDivision 7 | 980 CY | $12.00 | Redlands Contracting, LLC |
| Mar 19, 2020 | 200133 | HaskellDivision 1 | 160 CY | $12.66 | C3 Construction, Inc. |
| Mar 19, 2020 | 200133 | HaskellDivision 1 | 160 CY | $12.66 | C3 Construction, Inc. |
| Feb 20, 2020 | 200062 | EllisDivision 6 | 390 CY | $6.50 | J & R SAND COMPANY, INC. |
| Feb 20, 2020 | 200062 | EllisDivision 6 | 240 CY | $6.50 | J & R SAND COMPANY, INC. |
| Feb 20, 2020 | 200073 | MarshallDivision 2 | 220 CY | $14.00 | HUB Construction, Inc. |
| Feb 20, 2020 | 200062 | EllisDivision 6 | 730 CY | $6.50 | J & R SAND COMPANY, INC. |
| Feb 20, 2020 | 200062 | EllisDivision 6 | 460 CY | $6.50 | J & R SAND COMPANY, INC. |
| Jan 16, 2020 | 200092 | TulsaDivision 8 | 620 CY | $28.00 | APAC-CENTRAL, INC. |
| Jan 16, 2020 | 200018 | McintoshDivision 1 | 7,455 CY | $7.35 | L & N BRIDGE, LLC |
| Jan 16, 2020 | 200092 | TulsaDivision 8 | 1,910 CY | $28.00 | APAC-CENTRAL, INC. |
| Jan 16, 2020 | 200043 | HaskellDivision 1 | 1,976.13 CY | $10.43 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Jan 16, 2020 | 190214 | LoveDivision 7 | 760 CY | $9.00 | Silver Star Construction Company, Inc. |
| Jan 16, 2020 | 200001 | AlfalfaDivision 6 | 650 CY | $23.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 14, 2019 | 190364 | MayesDivision 8 | 136 CY | $7.50 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Nov 14, 2019 | 190349 | DeweyDivision 5 | 2,800 CY | $10.00 | SEWELL BROS., INC. |
| Nov 14, 2019 | 190309 | WashingtonDivision 8 | 670 CY | $15.00 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION |
| Nov 14, 2019 | 190109 | CanadianDivision 4 | 130 CY | $30.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Nov 14, 2019 | 190351 | GarfieldDivision 4 | 10 CY | $315.00 | LOGOS CONSTRUCTION CO., LLC |
| Oct 17, 2019 | 190323 | Nhpp-255n(489)eh | 25,584.1 CY | $16.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Oct 17, 2019 | 190323 | Nhpp-255n(489)eh | 4,911.7 CY | $14.50 | CROSSLAND HEAVY CONTRACTORS INC. |
| Oct 17, 2019 | 190380 | BeckhamDivision 5 | 2,650 CY | $8.40 | Frontier Bridge, Inc. |
| Oct 17, 2019 | 190335 | TulsaDivision 8 | 4,930 CY | $15.60 | Tri Star Construction Arkansas, LLC |
| Oct 17, 2019 | 190264 | Stp-264c(063)pm | 3,740 CY | $13.00 | HUB Construction, Inc. |
| Oct 17, 2019 | 190316 | GreerDivision 5 | 1,791 CY | $7.00 | KLAVER CONSTRUCTION COMPANY, INC. |
| Oct 17, 2019 | 190264 | Stp-264c(063)pm | 1,560 CY | $13.08 | HUB Construction, Inc. |
| Sep 19, 2019 | 190224 | OklahomaDivision 4 | 1,795 CY | $12.30 | Silver Star Construction Company, Inc. |
| Aug 22, 2019 | 190245 | EllisDivision 6 | 880 CY | $5.00 | Wyatt Contracting |
| Aug 22, 2019 | 190250 | OklahomaDivision 4 | 300 CY | $5.00 | Wyatt Contracting |
| Aug 22, 2019 | 190258 | TillmanDivision 5 | 267 CY | $15.00 | Wyatt Contracting |
| Jul 25, 2019 | 190234 | Jefferson | 536 CY | $31.00 | OVERLAND CORPORATION |
| Jul 25, 2019 | 190265 | BeckhamDivision 5 | 610 CY | $7.00 | CASWELL CONSTRUCTION, INC. |
| Jul 25, 2019 | 190269 | Roger MillsDivision 5 | 1,890 CY | $11.00 | SEWELL BROS., INC. |
| Jul 25, 2019 | 190270 | AlfalfaDivision 6 | 70 CY | $5.50 | Venture Corporation dba VCO Paving |
| Jun 20, 2019 | 190149 | CusterDivision 5 | 4,145 CY | $8.56 | Treas Construction Inc |
| Jun 20, 2019 | 190125 | OkmulgeeDivision 1 | 820 CY | $8.00 | RRY SERVICES LLC |
| Jun 20, 2019 | 190125 | OkmulgeeDivision 1 | 1,180 CY | $8.00 | RRY SERVICES LLC |
| Jun 20, 2019 | 190204 | KayDivision 4 | 530 CY | $15.00 | Evans & Associates Construction Co., Inc. |
| Jun 20, 2019 | 190056 | OttawaDivision 8 | 1,122 CY | $11.00 | RRY SERVICES LLC |
| Jun 20, 2019 | 190142 | Jefferson | 2,424 CY | $8.00 | OVERLAND CORPORATION |
| Jun 20, 2019 | 190149 | CusterDivision 5 | 480 CY | $7.49 | Treas Construction Inc |
| May 16, 2019 | 190081 | JohnstonDivision 3 | 1,885 CY | $25.75 | Treas Construction Inc |
| May 16, 2019 | 190173 | CanadianDivision 4 | 1,410 CY | $10.00 | SEWELL BROS., INC. |
| May 16, 2019 | 190023 | PottawatomieDivision 3 | 14,500 CY | $5.84 | CP3 ENTERPRISES, INC. |
| May 16, 2019 | 190027 | WashingtonDivision 8 | 1,780 CY | $20.00 | BECCO CONTRACTORS, INC. |
| May 16, 2019 | 190004 | ChoctawDivision 2 | 1,050 CY | $10.00 | HUB Construction, Inc. |
| May 16, 2019 | 190117 | KiowaDivision 5 | 1,840 CY | $10.00 | SEWELL BROS., INC. |
| Apr 18, 2019 | 190006 | GarvinDivision 3 | 4,960 CY | $7.00 | BRIDGECO CONTRACTORS, INC. |
| Apr 18, 2019 | 190087 | NowataDivision 8 | 560 CY | $7.90 | Tri Star Construction Arkansas, LLC |
| Mar 14, 2019 | 190141 | Jefferson | 2,350 CY | $12.00 | SEWELL BROS., INC. |
| Feb 14, 2019 | 190100 | Stp-205b(076)pm | 6,940 CY | $3.18 | Frontier Bridge, Inc. |
| Feb 14, 2019 | 190100 | Stp-205b(076)pm | 2,600 CY | $16.05 | Frontier Bridge, Inc. |
| Feb 14, 2019 | 190080 | JacksonDivision 5 | 1,760 CY | $5.00 | Wyatt Contracting |
| Jan 17, 2019 | 180191 | Cotton | 763 CY | $8.00 | SEWELL BROS., INC. |
| Jan 17, 2019 | 180191 | Cotton | 820 CY | $8.00 | SEWELL BROS., INC. |
| Nov 15, 2018 | 180245 | MurrayDivision 7 | 2,080 CY | $5.00 | Wyatt Contracting |
| Nov 15, 2018 | 180260 | ChoctawDivision 2 | 983 CY | $10.00 | H & H BRIDGE COMPANY |
| Nov 15, 2018 | 180264 | HaskellDivision 1 | 1,543 CY | $8.40 | B & B BRIDGE COMPANY, LLC |
| Sep 20, 2018 | 180278 | BlaineDivision 5 | 2,558 CY | $5.00 | Wyatt Contracting |
| Sep 20, 2018 | 180285 | GreerDivision 5 | 337 CY | $8.00 | KLAVER CONSTRUCTION COMPANY, INC. |
| Sep 20, 2018 | 180313 | SeminoleDivision 3 | 1,910 CY | $6.45 | B & B BRIDGE COMPANY, LLC |
| Aug 16, 2018 | 180267 | OklahomaDivision 4 | 3,000 CY | $15.00 | PBX Corporation |
| Aug 16, 2018 | 180269 | OklahomaDivision 4 | 1,565 CY | $7.00 | KLAVER CONSTRUCTION COMPANY, INC. |
| Jul 19, 2018 | 180192 | Cotton | 282 CY | $15.12 | BREWER CONSTRUCTION OKLAHOMA, LLC |
| Jun 14, 2018 | 180225 | Stp-231c(033)ci | 1,350 CY | $14.00 | T. McDonald Construction, Inc. |
| Jun 14, 2018 | 180231 | WashitaDivision 5 | 4,232 CY | $5.25 | CASWELL CONSTRUCTION, INC. |
| Jun 14, 2018 | 180189 | CimarronDivision 6 | 250 CY | $17.08 | KLAVER CONSTRUCTION COMPANY, INC. |
| May 17, 2018 | 180190 | ClevelandDivision 3 | 6,008.3 CY | $12.00 | Silver Star Construction Company, Inc. |
| May 17, 2018 | 180154 | BlaineDivision 5 | 1,300 CY | $6.06 | FRONTIER BRIDGE, INC. / BRIDGECO CONTRACTORS, INC. |
| May 17, 2018 | 180211 | StephensDivision 7 | 935 CY | $7.75 | OVERLAND CORPORATION |
| Mar 15, 2018 | 180131 | DeweyDivision 5 | 1,104 CY | $5.25 | J & R SAND COMPANY, INC. |
| Mar 15, 2018 | 180142 | PawneeDivision 8 | 2,500 CY | $7.50 | T. McDonald Construction, Inc. |
| Mar 15, 2018 | 180147 | TexasDivision 6 | 1,810 CY | $6.09 | HIGHWAY CONTRACTORS, INC. |
| Mar 15, 2018 | 180151 | WashingtonDivision 8 | 570 CY | $30.00 | BECCO CONTRACTORS, INC. |
| Mar 15, 2018 | 180122 | Acstp-277d(044)ur | 1,595 CY | $20.50 | THE CUMMINS CONSTRUCTION CO., INC. |
| Feb 15, 2018 | 180111 | OsageDivision 8 | 1,860 CY | $10.00 | B & B BRIDGE COMPANY, LLC |
| Feb 15, 2018 | 180113 | Roger MillsDivision 5 | 450 CY | $5.20 | CASWELL CONSTRUCTION, INC. |
| Feb 15, 2018 | 180113 | Roger MillsDivision 5 | 1,130 CY | $5.20 | CASWELL CONSTRUCTION, INC. |
| Feb 15, 2018 | 180120 | WashitaDivision 5 | 1,869 CY | $12.25 | C-GAWF CONSTRUCTION, INC. |
| Feb 15, 2018 | 180081 | Cotton | 5,735 CY | $7.80 | SAC Services, Inc. |
| Feb 15, 2018 | 180081 | Cotton | 540 CY | $7.90 | SAC Services, Inc. |
| Feb 15, 2018 | 180010 | Stp-238c(046)ss | 1,510 CY | $7.25 | RRY SERVICES LLC |
| Jan 18, 2018 | 180011 | LatimerDivision 2 | 990 CY | $10.40 | HUB Construction, Inc. |
| Jan 18, 2018 | 180032 | SeminoleDivision 3 | 9,180 CY | $3.00 | T. McDonald Construction, Inc. |
| Jan 18, 2018 | 180045 | Ellis, Woodward | 1,250 CY | $6.10 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 18, 2018 | 180006 | CreekDivision 8 | 1,255 CY | $6.00 | BRIDGECO CONTRACTORS, INC. |
| Jan 18, 2018 | 180006 | CreekDivision 8 | 1,439 CY | $6.00 | BRIDGECO CONTRACTORS, INC. |