Bid tab 190006

Let Apr 18, 2019 · Division 3 · Garvin Sign up free

‹ Apr 2019 results

BRIDGE AND APPROACHES SH -74: OVER UNNAMED CREEK, 6.4 MILES NORTH OF THE SH -29 JUNCTION NEAR ANTIOCH . PROJECT LENGTH = 0.056 MILE

Let date
Thursday, April 18, 2019
Contract
190006
J/P numbers
28938(04)
District
Division 3
County
Garvin
Highway
Limits
BRIDGE AND APPROACHES SH -74: OVER UNNAMED CREEK, 6.4 MILES NORTH OF THE SH -29 JUNCTION NEAR ANTIOCH . PROJECT LENGTH = 0.056 MILE
Project number
STP-225C(079)PM

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,721,774
1 BRIDGECO CONTRACTORS, INC. Low bidder $1,526,671 -11.3%
2 Redlands Contracting, LLC $1,555,498 -9.7% +1.9%
3 RRY SERVICES LLC $1,625,579 -5.6% +6.5%
4 CP3 ENTERPRISES, INC. $1,672,712 -2.8% +9.6%
5 C3 Construction, Inc. $1,719,075 -0.2% +12.6%
6 Silver Star Construction Company, Inc. $1,735,000 +0.8% +13.6%

Bid tab: unit prices 57 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 BRIDGECO CONTRA…#2 Redlands Contra…#3 RRY SERVICES LLC#4 CP3 ENTERPRISES…#5 C3 Construction…#6 Silver Star Con…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $15,000.00 $23,500.00 $46,000.00 $13,700.00 $21,315.00 $3,262.07 $55,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION10,483CY $8.00 $7.35 $6.90 $8.25 $9.14 $10.18 $8.50
3202(D) 0184 UNCLASSIFIED BORROW7,472CY $10.00 $8.48 $13.50 $11.75 $12.94 $11.87 $14.50
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $15,000.00 $10,500.00 $11,850.00 $8,500.00 $24,360.00 $7.83 $48,000.00
5221(C) 2801 TEMPORARY SILT FENCE1,822LF $2.00 $2.15 $2.10 $1.85 $6.19 $2.35 $1.95
6221(F) 0100 TEMPORARY SILT DIKE60LF $9.50 $7.50 $7.10 $12.88 $20.27 $8.48 $7.05
7221(G) 0153 TEMPORARY ROCK FILTER DAM TYPE 417CY $150.00 $80.00 $120.00 $145.00 $139.97 $152.99 $163.00
8230(A) 2806 SOLID SLAB SODDING17,878SY $4.00 $1.95 $2.15 $1.88 $2.44 $2.35 $1.95
9233(A) 2817 VEGETATIVE MULCHING4AC $1,000.00 $250.00 $250.00 $895.00 $1,090.11 $260.97 $218.00
10241 2832 MOWING8AC $120.00 $75.00 $60.00 $110.00 $133.98 $65.24 $54.30
11303(A) 2100 AGGREGATE BASE TYPE A1,215CY $65.00 $61.08 $68.00 $56.00 $41.73 $27.98 $59.45
12307(K) 4300 STABILIZED SUBGRADE4,573SY $8.00 $6.10 $6.50 $5.75 $12.47 $7.50 $6.90
13325 5271 SEPARATOR FABRIC1,678SY $3.00 $2.58 $2.40 $1.25 $4.41 $3.05 $2.40
14402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E134TON $36.00 $34.00 $32.00 $30.00 $48.57 $27.98 $67.50
15407(B) 0250 TACK COAT959GAL $4.00 $4.29 $2.50 $4.05 $5.48 $4.57 $2.50
16408 5774 PRIME COAT2,335GAL $6.00 $8.32 $2.50 $7.90 $9.74 $8.16 $3.00
17411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,612TON $85.00 $89.44 $95.00 $86.00 $99.51 $122.98 $74.70
18411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)856TON $95.00 $113.30 $99.25 $110.00 $127.28 $128.92 $93.65
19412 5267 COLD MILLING PAVEMENT2,532SY $8.00 $4.50 $6.50 $6.30 $6.46 $5.22 $6.50
20509(D) 0325 CLASS C CONCRETE10CY $400.00 $300.00 $350.00 $300.00 $304.50 $420.51 $570.50
21611(G) 6002 INLET (SMD-TYPE 2)1EA $2,600.00 $3,200.00 $4,800.00 $8,900.00 $4,713.96 $2,680.45 $4,292.00
22613(A) 0492 24" R.C.PIPE CLASS III181LF $75.00 $53.31 $54.00 $69.00 $55.86 $67.82 $108.60
23613(B) 0690 24" CORR. GALV. STEEL PIPE44LF $40.00 $31.54 $50.00 $36.00 $47.33 $55.58 $84.75
24613(B) 0693 42" CORR. GALV. STEEL PIPE166LF $70.00 $47.80 $70.00 $63.00 $79.45 $95.83 $81.50
25613(B) 0696 60" CORR. GALV. STEEL PIPE384LF $120.00 $103.45 $152.00 $185.00 $124.44 $130.47 $93.60
26613(L) 5730 24" PREFAB. CULVERT END SECTION, ROUND3EA $650.00 $1,850.00 $980.00 $893.00 $1,230.18 $1,101.80 $1,360.00
27613(M) 7187 TYPE B4 CULVERT END TREATMENT2EA $1,200.00 $1,250.00 $1,085.00 $1,800.00 $1,218.00 $880.85 $1,705.00
28613(M) 7189 TYPE D4 CULVERT END TREATMENT2EA $1,900.00 $2,500.00 $1,800.00 $2,400.00 $1,705.20 $889.39 $1,305.00
29619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $10,000.00 $5,600.00 $12,000.00 $13,700.00 $18,270.00 $8,481.39 $60,620.00
30619(B) 4728 REMOVAL OF ASPHALT PAVEMENT4,202SY $5.00 $4.25 $6.00 $6.50 $7.73 $5.22 $8.00
31619(C) 0924 SAWING PAVEMENT448LF $5.00 $12.00 $2.90 $5.50 $8.62 $6.20 $3.50
32624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)377LF $6.50 $15.00 $7.50 $14.00 $11.25 $5.87 $10.85
33629(E) 5048 REMOVE AND RESET MAILBOX1EA $180.00 $300.00 $350.00 $125.00 $609.00 $97.86 $163.00
34202(A) 1301 UNCLASSIFIED EXCAVATION4,960CY $8.00 $7.00 $7.50 $8.25 $10.96 $10.18 $9.30
35501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED940CY $12.00 $12.00 $35.00 $16.00 $12.18 $20.36 $13.05
36509(A) 1326 CLASS AA CONCRETE883.4CY $550.00 $429.50 $374.00 $500.00 $409.66 $491.54 $490.50
37511(A) 1332 REINFORCING STEEL156,050LB $1.10 $1.03 $1.00 $1.00 $0.9700 $1.10 $0.6300
38619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $20,000.00 $57,000.00 $38,000.00 $17,300.00 $37,961.00 $35,093.38 $25,500.00
39853 9030 DELINEATORS(TYPE 1, CODE 3)2EA $30.00 $28.00 $30.00 $26.00 $42.63 $32.62 $27.20
40855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)2,832LF $0.7000 $1.32 $1.25 $1.30 $1.34 $1.63 $1.35
41857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)4,996LF $0.4000 $0.2600 $0.1200 $0.2600 $0.3200 $0.3300 $0.3000
42857(E) 8887 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-11,000EA $1.00 $1.06 $0.6000 $1.04 $0.9100 $1.30 $1.10
43857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)750LF $0.6000 $1.05 $0.6000 $1.04 $2.80 $1.30 $1.10
44871(B) 8705 (SP)CONST.ZONE IMPACT ATTEN.240SD $7.00 $7.35 $12.00 $7.28 $7.31 $9.13 $7.60
45877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER2,337.5LF $25.00 $16.54 $15.00 $18.00 $15.96 $20.55 $17.10
46880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF1,440SD $0.4000 $1.05 $0.4500 $1.04 $2.74 $1.30 $1.10
47880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF960SD $1.00 $2.04 $1.20 $2.08 $2.74 $2.61 $2.20
48880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF1,520SD $1.50 $0.5700 $2.50 $0.5200 $2.74 $0.6500 $0.5500
49880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)240SD $1.50 $4.20 $3.75 $4.16 $6.09 $5.22 $4.35
50880(C) 8848 WING BARRICADES480SD $1.10 $1.06 $3.75 $1.04 $0.3000 $1.30 $1.10
51880(E) 8860 WARNING LIGHTS(TYPE A)480SD $0.5000 $1.06 $0.6000 $1.04 $0.9100 $1.30 $1.10
52880(F) 8878 DRUMS4,480SD $0.4000 $0.1700 $0.5000 $0.1000 $0.0700 $0.1300 $0.1100
53882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN240SD $15.00 $15.00 $19.00 $10.40 $13.40 $13.05 $10.90
54642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $12,000.00 $9,500.00 $10,500.00 $6,552.00 $9,135.00 $10,895.32 $35,000.00
55220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $8,000.00 $3,500.00 $8,500.00 $500.00 $6,450.53 $1,957.24 $18,000.00
56640(A) 1398 FIELD OFFICE1EA $10,000.00 $6,000.00 $12,000.00 $1,500.00 $6,236.16 $11,091.05 $15,000.00
57641 1399 MOBILIZATION1LSUM $110,000.00 $90,000.00 $70,000.00 $106,000.00 $82,609.63 $112,084.82 $112,973.05