Bid tab 210273

Let Oct 14, 2021 · Division 6 · Ellis Sign up free

‹ Oct 2021 results

BRIDGE AND APPROACHES COUNTY ROAD (NS-181): OVER OTTER CREEK, 0.7 MILES SOUTH OF THE HARPER COUNTY LINE . PROJECT LENGTH = 0.208 MILE

Let date
Thursday, October 14, 2021
Contract
210273
J/P numbers
31128(04)
District
Division 6
County
Ellis
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (NS-181): OVER OTTER CREEK, 0.7 MILES SOUTH OF THE HARPER COUNTY LINE . PROJECT LENGTH = 0.208 MILE
Project number
STP-223D(022)CI

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$934,802
1 Lopp Construction, LLC Low bidder $686,856 -26.5%
2 SEWELL BROS., INC. $854,731 -8.6% +24.4%
3 K & R BUILDERS, INC. $859,330 -8.1% +25.1%
4 RRY SERVICES LLC $885,895 -5.2% +29.0%
5 HASKELL LEMON CONSTRUCTION CO. $925,226 -1.0% +34.7%
6 Wyatt Contracting $975,197 +4.3% +42.0%
7 DOWNEY CONTRACTING, LLC $2,087,478 +123.3% +203.9%

Bid tab: unit prices 30 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Lopp Constructi…#2 SEWELL BROS., I…#3 K & R BUILDERS,…#4 RRY SERVICES LLC#5 HASKELL LEMON C…#6 Wyatt Contracti…#7 DOWNEY CONTRACT…
10201(A) 0102 CLEARING AND GRUBBING1LSUM $8,000.00 $6,500.00 $5,000.00 $6,500.00 $3,500.00 $16,580.00 $32,000.00 $201,000.00
20202(A) 0183 UNCLASSIFIED EXCAVATION1,070CY $8.00 $6.50 $10.00 $8.65 $8.00 $6.95 $12.00 $45.00
30202(D) 0184 UNCLASSIFIED BORROW2,148CY $10.00 $6.70 $10.00 $1.00 $12.00 $7.15 $15.00 $50.00
40205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $6,000.00 $6,700.00 $5,000.00 $6,500.00 $3,500.00 $11,980.00 $20,000.00 $12,000.00
50221(C) 2801 TEMPORARY SILT FENCE2,200LF $2.80 $2.78 $3.00 $2.85 $2.85 $2.95 $2.97 $3.55
60221(F) 0100 TEMPORARY SILT DIKE168LF $17.00 $14.88 $16.00 $15.00 $15.50 $15.90 $15.92 $27.30
70230(A) 2806 SOLID SLAB SODDING8,679SY $5.00 $2.98 $3.50 $3.30 $3.20 $3.20 $3.19 $7.28
80233(A) 2817 VEGETATIVE MULCHING1.79AC $950.00 $2,885.00 $3,000.00 $1,200.00 $2,885.00 $3,087.00 $3,086.95 $2,184.00
90402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E769TON $55.00 $48.00 $51.00 $55.85 $68.00 $50.30 $65.00 $118.30
100509(D) 0325 CLASS C CONCRETE10CY $375.00 $300.00 $350.00 $410.00 $350.00 $622.50 $500.00 $819.00
110601(B) 0536 TYPE I-A PLAIN RIPRAP355TON $70.00 $62.00 $65.00 $75.00 $82.00 $68.80 $65.00 $136.50
120601(C) 0538 TYPE I-A FILTER BLANKET119TON $55.00 $50.00 $55.00 $60.00 $70.00 $52.90 $55.00 $118.30
130613(B) 0689 18" CORR. GALV. STEEL PIPE104LF $42.00 $49.00 $50.00 $45.00 $85.00 $54.90 $60.00 $222.83
140613(M) 7150 TYPE A3 CULVERT END TREATMENT4EA $1,200.00 $1,400.00 $1,200.00 $1,450.00 $1,750.00 $2,162.00 $2,500.00 $3,185.00
150619(B) 4725 REMOVAL OF FENCE2,171LF $3.00 $3.00 $1.00 $3.25 $1.50 $1.60 $2.75 $5.36
160624(C) 7181 FENCE-STYLE SWF (6 BARBED WIRE)2,205LF $10.00 $12.75 $12.50 $8.80 $10.75 $9.40 $9.42 $20.64
170202(A) 1301 UNCLASSIFIED EXCAVATION1,993CY $10.00 $6.50 $10.00 $12.60 $10.00 $6.95 $11.00 $45.00
180501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED314CY $12.00 $20.00 $15.00 $16.00 $15.00 $21.50 $35.00 $55.00
190509(A) 1326 CLASS AA CONCRETE623CY $700.00 $406.50 $600.00 $605.00 $585.00 $604.00 $565.00 $1,301.02
200511(A) 1332 REINFORCING STEEL126,144LB $1.23 $1.16 $1.40 $1.26 $1.25 $1.20 $1.50 $2.28
210601(B) 1353 TYPE I-A PLAIN RIPRAP264TON $60.00 $62.00 $65.00 $75.00 $82.00 $68.80 $65.00 $154.70
220601(C) 1355 TYPE I-A FILTER BLANKET88TON $50.00 $50.00 $55.00 $60.00 $70.00 $52.90 $55.00 $136.50
230619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $8,000.00 $5,000.00 $5,000.00 $6,750.00 $11,000.00 $34,410.00 $25,000.00 $32,500.00
240880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF2,400SD $0.4000 $0.1000 $0.3500 $0.1000 $0.1100 $0.5400 $0.1100 $0.9100
250880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF240SD $2.20 $2.00 $4.35 $4.00 $2.25 $3.20 $2.14 $5.46
260880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)1,920SD $0.3000 $0.1000 $0.4000 $0.1000 $0.1100 $1.05 $0.1100 $1.82
270880(E) 8860 WARNING LIGHTS(TYPE A)4,800SD $0.1500 $0.1000 $0.2500 $0.1000 $0.1100 $0.1100 $0.1100 $0.1800
280642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $7,500.00 $5,500.00 $6,050.00 $7,900.00 $5,940.00 $11,555.00 $7,490.00 $10,010.00
290220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,000.00 $3,000.00 $3,500.00 $2,500.00 $1,650.00 $3,673.00 $5,000.00 $1,365.00
300641 1399 MOBILIZATION1LSUM $65,000.00 $45,000.00 $40,000.00 $67,500.00 $72,000.00 $91,897.02 $73,000.00 $75,000.00