BRIDGE AND APPROACHES COUNTY ROAD (EW-112): OVER ARAPAHO CREEK , 2.0 MILES WEST OF THE US-81 JUNCTION NEAR UNION CITY. PROJECT LENGTH = 0.378 MILE

Let date
Thursday, May 16, 2019
Contract
190173
J/P numbers
31181(04)
District
Division 4
County
Canadian
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-112): OVER ARAPAHO CREEK , 2.0 MILES WEST OF THE US-81 JUNCTION NEAR UNION CITY. PROJECT LENGTH = 0.378 MILE
Project number
STP-209C(071)CI

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,258,097
1 SEWELL BROS., INC. Low bidder $1,473,205 +17.1%
2 RRY SERVICES LLC $1,499,512 +19.2% +1.8%

Bid tab: unit prices 58 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 SEWELL BROS., I…#2 RRY SERVICES LLC
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $25,000.00 $10,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION11,445CY $9.00 $10.00 $8.00
3202(D) 0184 UNCLASSIFIED BORROW6,375CY $10.00 $10.00 $12.00
4210 0121 OBLITERATING ABANDONED ROAD200LF $6.00 $15.00 $15.00
5221(C) 2801 TEMPORARY SILT FENCE2,750LF $2.00 $3.30 $2.00
6221(F) 0100 TEMPORARY SILT DIKE500LF $10.00 $16.50 $7.00
7228 4170 NYLON EROSION CONTROL MAT1,650SY $3.00 $11.00 $2.80
8230(A) 2806 SOLID SLAB SODDING33,154SY $2.00 $2.20 $1.80
9233(A) 2817 VEGETATIVE MULCHING17.5AC $800.00 $1,100.00 $300.00
10307(K) 4300 STABILIZED SUBGRADE5,580SY $5.00 $10.00 $5.95
11402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E1,438TON $30.00 $32.00 $39.00
12411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,203TON $70.00 $120.00 $111.00
13411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)671TON $80.00 $123.00 $113.00
14509(D) 0325 CLASS C CONCRETE10CY $375.00 $400.00 $275.00
15613(A) 0492 24" R.C.PIPE CLASS III52LF $65.00 $60.00 $70.00
16613(B) 0690 24" CORR. GALV. STEEL PIPE78LF $40.00 $35.00 $50.00
17613(B) 0693 42" CORR. GALV. STEEL PIPE48LF $55.00 $65.00 $120.00
18613(B) 4528 28" X 20" CORR. GALV. STEEL PIPE ARCH126LF $50.00 $40.00 $50.00
19613(L) 4516 28" X 20" PREFAB. CULVERT END SECTION, ARCH2EA $800.00 $200.00 $500.00
20613(L) 5730 24" PREFAB. CULVERT END SECTION, ROUND4EA $1,000.00 $1,050.00 $1,000.00
21613(L) 5736 42" PREFAB. CULVERT END SECTION, ROUND2EA $2,300.00 $1,050.00 $1,300.00
22619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $10,000.00 $12,000.00 $5,000.00
23202(A) 1301 UNCLASSIFIED EXCAVATION1,410CY $10.00 $10.00 $8.00
24501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED25CY $20.00 $50.00 $25.00
25535 6950 CORRUGATED STEEL ARCH CULVERT100.5LF $1,200.00 $1,705.00 $2,250.00
26601(B) 1353 TYPE I-A PLAIN RIPRAP810TON $45.00 $47.00 $52.00
27601(C) 1355 TYPE I-A FILTER BLANKET236TON $45.00 $37.00 $38.00
28501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON220CY $25.00 $25.00 $20.00
29501(F) 6352 GRANULAR BACKFILL102CY $80.00 $65.00 $80.00
30503(A) 1313 PRESTRESSED CONCRETE BEAMS (TYPE IV)299LF $230.00 $228.00 $260.00
31504(B) 1305 SAW-CUT GROOVING254.4SY $4.00 $12.00 $10.80
32504(D) 6239 CONCRETE RAIL (TR3)281.3LF $75.00 $80.00 $85.00
33506(A) 1322 STRUCTURAL STEEL590LB $2.50 $4.50 $3.00
34507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY3EA $750.00 $900.00 $1,100.00
35507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY3EA $850.00 $900.00 $1,100.00
36509(A) 1326 CLASS AA CONCRETE81.4CY $525.00 $600.00 $685.00
37509(B) 1328 CLASS A CONCRETE79.4CY $575.00 $600.00 $685.00
38511(A) 1332 REINFORCING STEEL32,440LB $1.00 $1.00 $1.10
39514(A) 6010 PILES, FURNISHED (HP 10X42)276LF $30.00 $30.00 $40.00
40514(A) 6011 PILES, FURNISHED (HP 12X53)904LF $33.00 $35.00 $50.00
41514(B) 6292 PILES, DRIVEN (HP 10X42)276LF $15.00 $15.00 $10.00
42514(B) 6294 PILES, DRIVEN (HP 12X53)904LF $20.00 $15.00 $10.00
43514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00
44601(B) 1353 TYPE I-A PLAIN RIPRAP2,190TON $45.00 $47.00 $52.00
45601(C) 1355 TYPE I-A FILTER BLANKET455TON $40.00 $37.00 $38.00
46613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND60LF $28.00 $35.00 $35.00
47613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.40LF $28.00 $40.00 $35.00
48619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $15,000.00 $12,000.00 $5,000.00
49623(A) 1418 BEAM GUARDRAIL W-BEAM SINGLE285.13LF $18.00 $32.00 $22.00
50623(F) 5686 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $1,750.00 $1,925.00 $1,900.00
51623(F) 6029 GUARDRAIL ANCHOR UNIT (TYPE A)3EA $1,600.00 $1,820.00 $1,800.00
52805(D) 8756 (PL)REMOVE & RESET EXISTING SIGNS1EA $200.00 $220.00 $250.00
53850(A) 8110 SHEET ALUMINUM SIGNS25SF $25.00 $17.00 $20.00
54851(C) 8327 2 1/4" SQUARE TUBE POST60LF $13.00 $12.00 $10.00
55880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $7,500.00 $7,700.00 $7,630.00
56642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $10,000.00 $9,250.00 $8,400.00
57220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $7,500.00 $3,500.00 $1,275.00
58641 1399 MOBILIZATION1LSUM $83,325.00 $60,000.00 $100,000.00