$44.03Avg low bid / LF
$47.42Avg of all bids
$39.07Avg engineer's estimate
60Jobs · 12,013 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 12 | 2,774 | $48.22 | $53.08 |
| 2020 | 21 | 3,112 | $42.81 | $46.71 |
| 2019 | 12 | 2,496 | $41.88 | $48.64 |
| 2018 | 15 | 3,631 | $43.34 | $43.95 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 15, 2021 | 210200 | BeckhamDivision 5 | 130 LF | $45.00 | SEWELL BROS., INC. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 42 LF | $50.85 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210148 | PayneDivision 4 | 186 LF | $65.00 | BECCO CONTRACTORS, INC. |
| Apr 15, 2021 | 210114 | NobleDivision 4 | 406 LF | $72.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Mar 18, 2021 | 210072 | CaddoDivision 7 | 152 LF | $60.00 | OVERLAND CORPORATION |
| Feb 18, 2021 | 210062 | Pontotoc | 312 LF | $46.40 | HASKELL LEMON CONSTRUCTION CO. |
| Jan 21, 2021 | 210025 | KingfisherDivision 4 | 512 LF | $42.25 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 210030 | McclainDivision 3 | 250 LF | $46.47 | IHC Scott, INC. |
| Jan 21, 2021 | 210035 | Pontotoc | 60 LF | $36.30 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 210010 | ClevelandDivision 3 | 356 LF | $39.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Jan 21, 2021 | 210014 | GarfieldDivision 4 | 56 LF | $29.00 | K & R BUILDERS, INC. |
| Jan 21, 2021 | 210018 | HarperDivision 6 | 312 LF | $31.80 | THE CUMMINS CONSTRUCTION CO., INC. |
| Oct 15, 2020 | 200315 | MajorDivision 6 | 40 LF | $51.35 | THE CUMMINS CONSTRUCTION CO., INC. |
| Oct 15, 2020 | 200316 | Grady, Mcclain | 142 LF | $29.30 | Treas Construction Inc |
| Oct 15, 2020 | 200329 | StephensDivision 7 | 56 LF | $71.48 | BRIDGECO CONTRACTORS, INC. |
| Oct 15, 2020 | 200312 | GreerDivision 5 | 78 LF | $48.60 | K & R BUILDERS, INC. |
| Sep 17, 2020 | 200280 | JacksonDivision 5 | 72 LF | $35.00 | SEWELL BROS., INC. |
| Sep 17, 2020 | 200292 | PottawatomieDivision 3 | 116 LF | $51.50 | Silver Star Construction Company, Inc. |
| Sep 17, 2020 | 200294 | SequoyahDivision 1 | 90 LF | $75.00 | Rosscon, LLC |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 70 LF | $35.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200265 | LoganDivision 4 | 84 LF | $35.00 | Wyatt Contracting |
| Aug 20, 2020 | 200150 | EllisDivision 6 | 452 LF | $32.00 | J & R SAND COMPANY, INC. |
| Aug 20, 2020 | 200225 | GradyDivision 7 | 82 LF | $32.00 | SEWELL BROS., INC. |
| Jul 23, 2020 | 200261 | Pontotoc | 550 LF | $35.85 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 14, 2020 | 200193 | EllisDivision 6 | 84 LF | $33.60 | J & R SAND COMPANY, INC. |
| May 14, 2020 | 200022 | OttawaDivision 8 | 268 LF | $55.00 | APAC-CENTRAL, INC. |
| May 14, 2020 | 200208 | PittsburgDivision 2 | 49 LF | $40.00 | DUIT CONSTRUCTION COMPANY, INC. |
| Apr 16, 2020 | 200079 | SeminoleDivision 3 | 46 LF | $67.50 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 19, 2020 | 200125 | Jackson, Tillman | 54 LF | $43.00 | BRIDGECO CONTRACTORS, INC. |
| Feb 20, 2020 | 200057 | ClevelandDivision 3 | 378 LF | $45.30 | Silver Star Construction Company, Inc. |
| Jan 16, 2020 | 200020 | NobleDivision 4 | 186 LF | $53.23 | Evans & Associates Construction Co., Inc. |
| Jan 16, 2020 | 190356 | KayDivision 4 | 52 LF | $54.00 | Evans & Associates Construction Co., Inc. |
| Jan 16, 2020 | 200001 | AlfalfaDivision 6 | 163 LF | $43.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 14, 2019 | 190349 | DeweyDivision 5 | 172 LF | $40.00 | SEWELL BROS., INC. |
| Nov 14, 2019 | 190378 | WashitaDivision 5 | 72 LF | $35.00 | SEWELL BROS., INC. |
| Oct 17, 2019 | 190316 | GreerDivision 5 | 50 LF | $55.00 | KLAVER CONSTRUCTION COMPANY, INC. |
| Sep 19, 2019 | 190272 | AlfalfaDivision 6 | 120 LF | $41.20 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jul 25, 2019 | 190269 | Roger MillsDivision 5 | 110 LF | $40.00 | SEWELL BROS., INC. |
| Jun 20, 2019 | 190204 | KayDivision 4 | 160 LF | $48.57 | Evans & Associates Construction Co., Inc. |
| Jun 20, 2019 | 190142 | Jefferson | 570 LF | $51.75 | OVERLAND CORPORATION |
| May 16, 2019 | 190173 | CanadianDivision 4 | 126 LF | $40.00 | SEWELL BROS., INC. |
| Apr 18, 2019 | 190169 | GrantDivision 4 | 140 LF | $32.00 | Venture Corporation dba VCO Paving |
| Feb 14, 2019 | 190101 | Pontotoc | 194 LF | $33.30 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 17, 2019 | 190001 | AtokaDivision 2 | 332 LF | $42.29 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 17, 2019 | 180191 | Cotton | 450 LF | $35.00 | SEWELL BROS., INC. |
| Nov 15, 2018 | 180161 | CusterDivision 5 | 70 LF | $43.00 | SEWELL BROS., INC. |
| Nov 15, 2018 | 180286 | JacksonDivision 5 | 72 LF | $40.00 | SEWELL BROS., INC. |
| Oct 18, 2018 | 180188 | CarterDivision 7 | 484 LF | $34.80 | OVERLAND CORPORATION |
| Sep 20, 2018 | 180285 | GreerDivision 5 | 120 LF | $28.00 | KLAVER CONSTRUCTION COMPANY, INC. |
| Jul 19, 2018 | 180214 | WoodsDivision 6 | 114 LF | $34.71 | B & B BRIDGE COMPANY, LLC |
| Jul 19, 2018 | 180184 | TillmanDivision 5 | 220 LF | $40.00 | SEWELL BROS., INC. |
| May 17, 2018 | 180233 | Stp-267c(071)ss | 42 LF | $38.64 | FRONTIER BRIDGE, INC. / BRIDGECO CONTRACTORS, INC. |
| May 17, 2018 | 180211 | StephensDivision 7 | 554 LF | $34.85 | OVERLAND CORPORATION |
| Mar 15, 2018 | 180137 | NobleDivision 4 | 136 LF | $56.00 | Evans & Associates Construction Co., Inc. |
| Mar 15, 2018 | 180151 | WashingtonDivision 8 | 549 LF | $63.00 | BECCO CONTRACTORS, INC. |
| Feb 15, 2018 | 180070 | SequoyahDivision 1 | 120 LF | $39.00 | B & B BRIDGE COMPANY, LLC |
| Feb 15, 2018 | 180113 | Roger MillsDivision 5 | 790 LF | $41.60 | CASWELL CONSTRUCTION, INC. |
| Feb 15, 2018 | 180005 | ComancheDivision 7 | 78 LF | $33.65 | T & G CONSTRUCTION, INC. |
| Jan 18, 2018 | 180030 | RogersDivision 8 | 222 LF | $60.00 | BECCO CONTRACTORS, INC. |
| Jan 18, 2018 | 180045 | Ellis, Woodward | 60 LF | $31.80 | THE CUMMINS CONSTRUCTION CO., INC. |