Bid tab 180142

Let Mar 15, 2018 · Division 8 · Pawnee Sign up free

‹ Mar 2018 results

BRIDGE AND APPROACHES COUNTY ROAD (E0510): OVER UNNAMED CREEK, 0.6 MILES EAST OF THE SH-18 JUNCTION NEAR PAWNEE . PROJECT LENGTH = 0.05 MILE

Let date
Thursday, March 15, 2018
Contract
180142
J/P numbers
29930(04)
District
Division 8
County
Pawnee
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (E0510): OVER UNNAMED CREEK, 0.6 MILES EAST OF THE SH-18 JUNCTION NEAR PAWNEE . PROJECT LENGTH = 0.05 MILE
Project number
ACSTP-259D(044)CI

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$674,437
1 T. McDonald Construction, Inc. Low bidder $581,427 -13.8%
3 B & B BRIDGE COMPANY, LLC $612,351 -9.2% +5.3%
4 K & R BUILDERS, INC. $632,184 -6.3% +8.7%
5 RRY SERVICES LLC $671,366 -0.5% +15.5%
6 EARTH SMART CONSTRUCTION INC. $745,766 +10.6% +28.3%

Bid tab: unit prices 23 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 T. McDonald Con…#3 B & B BRIDGE CO…#4 K & R BUILDERS,…#5 RRY SERVICES LLC#6 EARTH SMART CON…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $5,000.00 $5,343.00 $6,750.00 $8,900.00 $19,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION43CY $20.00 $70.00 $75.00 $20.00 $75.00 $30.00
3205(A) 4230 TYPE A-SALVAGED TOPSOIL72CY $25.00 $55.56 $50.00 $33.50 $50.00 $50.00
4221(C) 2801 TEMPORARY SILT FENCE238LF $2.75 $1.75 $8.95 $2.50 $8.95 $9.00
5230(A) 2806 SOLID SLAB SODDING100SY $3.40 $25.00 $25.00 $40.00 $25.00 $45.00
6232(B) 2814 SEEDING METHOD B0.5AC $694.29 $10,000.00 $9,750.00 $11,000.00 $9,750.00 $11,500.00
7233(A) 2817 VEGETATIVE MULCHING0.5AC $249.15 $4,000.00 $9,750.00 $11,000.00 $9,750.00 $3,900.00
8310(B) 0149 SUBGRADE, METHOD B414SY $5.00 $10.00 $2.00 $7.50 $5.00 $9.00
9402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E181TON $30.00 $43.00 $32.31 $48.00 $40.00 $80.00
10619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $6,250.00 $7,500.00 $1,000.00 $4,250.00 $3,000.00 $28,000.00
11202(A) 1301 UNCLASSIFIED EXCAVATION2,500CY $8.00 $7.50 $4.50 $8.00 $12.00 $30.00
12202(C) 0182 ROCK EXCAVATION100CY $30.00 $52.00 $50.00 $63.50 $100.00 $60.00
13303(A) 2100 AGGREGATE BASE TYPE A1,835CY $52.00 $46.00 $50.00 $77.25 $70.00 $60.00
14508 6359 PRECAST ARCH CULVERT38LF $10,500.00 $8,350.00 $8,850.00 $9,131.50 $9,000.00 $8,200.00
15509(A) 1326 CLASS AA CONCRETE43CY $700.00 $495.00 $700.00 $350.00 $700.00 $700.00
16511(A) 0332 REINFORCING STEEL926LB $1.25 $3.00 $5.00 $1.33 $1.00 $3.00
17601(B) 1353 TYPE I-A PLAIN RIPRAP218TON $45.00 $47.00 $48.00 $54.00 $50.00 $80.00
18601(I) 6312 FILTER FABRIC (RIPRAP)277SY $3.25 $4.00 $3.00 $10.00 $4.00 $30.00
19619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $25,000.00 $7,000.00 $25,000.00 $7,000.00 $9,000.00 $20,000.00
20880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $1,773.00 $4,000.00 $2,276.54 $3,000.00 $2,276.54 $6,000.00
21642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $10,000.00 $5,000.00 $3,300.00 $4,000.00 $4,940.00 $9,000.00
22220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,400.00 $3,000.00 $2,500.00 $2,600.00 $1,250.00 $3,000.00
23641 1399 MOBILIZATION1LSUM $45,000.00 $60,000.00 $54,725.00 $28,000.00 $58,000.00 $62,000.00