| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$10,000.00 |
$10,000.00 |
$12,500.00 |
$25,000.00 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$60,000.00 |
$65,000.00 |
$34,926.62 |
$40,000.00 |
| 3 | 221(C) 2801 |
TEMPORARY SILT FENCE | 200 | LF |
$2.00 |
$1.20 |
$3.10 |
$3.00 |
| 4 | 221(F) 0100 |
TEMPORARY SILT DIKE | 200 | LF |
$7.50 |
$8.00 |
$7.89 |
$7.00 |
| 5 | 230(A) 2806 |
SOLID SLAB SODDING | 4,075 | SY |
$2.50 |
$1.95 |
$2.75 |
$2.40 |
| 6 | 233(A) 2817 |
VEGETATIVE MULCHING | 0.84 | AC |
$600.00 |
$275.00 |
$750.00 |
$200.00 |
| 7 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 318 | CY |
$68.00 |
$54.00 |
$69.03 |
$45.00 |
| 8 | 311(A) 0151 |
PROCESSING EXISTING BASE & SURFACE, METHOD A | 631 | LF |
$7.50 |
$11.00 |
$30.25 |
$10.00 |
| 9 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$350.00 |
$400.00 |
$300.00 |
$500.00 |
| 10 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 230.6 | CY |
$15.00 |
$20.00 |
$14.00 |
$25.00 |
| 11 | 501(F) 6352 |
GRANULAR BACKFILL | 109.6 | CY |
$65.00 |
$60.00 |
$81.49 |
$65.00 |
| 12 | 503(A) 1313 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 359 | LF |
$230.00 |
$220.00 |
$243.20 |
$240.00 |
| 13 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 261.3 | LF |
$75.00 |
$80.00 |
$79.00 |
$120.00 |
| 14 | 506(A) 1322 |
STRUCTURAL STEEL | 660 | LB |
$3.00 |
$4.00 |
$4.29 |
$5.00 |
| 15 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 4 | EA |
$825.00 |
$900.00 |
$1,045.00 |
$1,200.00 |
| 16 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 4 | EA |
$825.00 |
$900.00 |
$1,045.00 |
$1,200.00 |
| 17 | 509(A) 1326 |
CLASS AA CONCRETE | 81.3 | CY |
$680.00 |
$700.00 |
$625.00 |
$600.00 |
| 18 | 509(B) 1328 |
CLASS A CONCRETE | 83.2 | CY |
$700.00 |
$700.00 |
$655.00 |
$600.00 |
| 19 | 511(A) 1332 |
REINFORCING STEEL | 32,852 | LB |
$1.00 |
$1.00 |
$1.04 |
$1.20 |
| 20 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 90 | LF |
$35.00 |
$35.00 |
$35.00 |
$30.00 |
| 21 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 280 | LF |
$42.00 |
$40.00 |
$38.57 |
$40.00 |
| 22 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 90 | LF |
$18.00 |
$15.00 |
$20.00 |
$35.00 |
| 23 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 280 | LF |
$18.00 |
$15.00 |
$18.00 |
$35.00 |
| 24 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 25 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 2,650 | TON |
$47.00 |
$40.00 |
$41.00 |
$55.00 |
| 26 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 730 | TON |
$37.00 |
$30.00 |
$37.00 |
$40.00 |
| 27 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 66 | LF |
$30.00 |
$30.00 |
$35.00 |
$25.00 |
| 28 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 34 | LF |
$30.00 |
$35.00 |
$30.00 |
$25.00 |
| 29 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$10,000.00 |
$15,000.00 |
$25,000.00 |
$50,000.00 |
| 30 | 623(A) 1418 |
BEAM GUARDRAIL W-BEAM SINGLE | 37.5 | LF |
$22.00 |
$33.00 |
$32.63 |
$32.00 |
| 31 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 1 | EA |
$2,200.00 |
$2,200.00 |
$2,200.00 |
$2,200.00 |
| 32 | 623(F) 6033 |
GUARDRAIL ANCHOR UNIT (TYPE II) | 3 | EA |
$2,800.00 |
$3,200.00 |
$3,200.00 |
$3,200.00 |
| 33 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$7,500.00 |
$3,300.00 |
$4,000.00 |
$4,500.00 |
| 34 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$7,500.00 |
$5,300.00 |
$6,500.00 |
$10,000.00 |
| 35 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$7,500.00 |
$3,000.00 |
$3,500.00 |
$2,500.00 |
| 36 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$53,000.00 |
$50,000.00 |
$37,200.00 |
$57,000.00 |