Bid tab 190059

Let Jan 17, 2019 · Division 1 · Sequoyah Sign up free

‹ Jan 2019 results

GRADE, DRAIN, BRIDGE, AND SURFACE COUNTY ROAD (EW-1090): OVER SALLISAW CREEK , 2.6 MILES WEST OF THE US -59 JUNCTION NEAR SALLISAW . PROJECT LENGTH = 0.370 MILE

Let date
Thursday, January 17, 2019
Contract
190059
J/P numbers
28501(04)
District
Division 1
County
Sequoyah
Highway
Limits
GRADE, DRAIN, BRIDGE, AND SURFACE COUNTY ROAD (EW-1090): OVER SALLISAW CREEK , 2.6 MILES WEST OF THE US -59 JUNCTION NEAR SALLISAW . PROJECT LENGTH = 0.370 MILE
Project number
CIRB-268D(058)RB

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,361,800
1 T. McDonald Construction, Inc. Low bidder $2,096,175 -11.2%
2 C3 Construction, Inc. $2,230,381 -5.6% +6.4%
3 L & N BRIDGE, LLC $2,296,493 -2.8% +9.6%
4 RRY SERVICES LLC $2,605,683 +10.3% +24.3%
5 B & B BRIDGE COMPANY, LLC $3,381,901 +43.2% +61.3%

Bid tab: unit prices 49 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 T. McDonald Con…#2 C3 Construction…#3 L & N BRIDGE, L…#4 RRY SERVICES LLC#5 B & B BRIDGE CO…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $20,000.00 $25,000.00 $14,143.26 $33,000.00 $235,000.00 $30,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION7,300CY $10.00 $6.25 $7.31 $7.10 $7.25 $8.25
3202(B) 0105 MUCK EXCAVATION32,500CY $11.00 $9.50 $7.64 $6.35 $6.80 $11.50
4202(D) 0184 UNCLASSIFIED BORROW12,000CY $9.50 $8.50 $7.98 $8.85 $8.85 $10.50
5205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $13,050.00 $2,500.00 $10,634.03 $25,000.00 $25,000.00 $3,000.00
6221(C) 2801 TEMPORARY SILT FENCE918LF $2.50 $1.25 $6.63 $2.00 $5.50 $7.00
7221(F) 0100 TEMPORARY SILT DIKE448LF $9.00 $7.00 $33.23 $8.00 $25.00 $25.00
8230(A) 2806 SOLID SLAB SODDING12,030SY $2.50 $7.30 $9.24 $4.00 $7.00 $7.00
9233(A) 2817 VEGETATIVE MULCHING1.4AC $900.00 $5,500.00 $6,579.81 $6,000.00 $4,950.00 $5,000.00
10303(A) 2100 AGGREGATE BASE TYPE A846CY $50.00 $32.00 $26.03 $64.00 $50.00 $35.00
11325 5271 SEPARATOR FABRIC4,600SY $1.61 $2.50 $1.60 $0.7000 $1.50 $3.00
12407(B) 0250 TACK COAT900GAL $4.00 $2.00 $2.41 $1.81 $3.50 $3.50
13408 5774 PRIME COAT900GAL $5.00 $3.00 $5.41 $4.07 $5.00 $5.00
14411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)462TON $95.00 $77.00 $95.30 $87.96 $80.00 $72.00
15411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)693TON $106.00 $80.00 $92.16 $85.06 $80.00 $79.80
16623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE500LF $20.00 $20.00 $23.93 $18.00 $18.00 $18.00
17623(F) 4446 GUARDRAIL ANCHOR UNIT (TYPE A)4EA $1,264.99 $2,000.00 $2,459.12 $1,850.00 $1,850.00 $1,850.00
18623(F) 5686 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $1,392.03 $1,500.00 $1,728.03 $1,300.00 $1,300.00 $1,300.00
19624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)3,480LF $5.80 $7.50 $10.57 $4.85 $5.00 $4.85
20501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON190CY $12.66 $25.20 $14.62 $15.00 $15.00 $50.00
21501(G) 6309 CLSM BACKFILL88CY $150.00 $150.15 $128.94 $130.00 $140.00 $150.00
22503(A) 1313 PRESTRESSED CONCRETE BEAMS (TYPE IV)1,570LF $250.00 $230.00 $253.67 $288.00 $270.00 $490.00
23504(A) 1304 APPROACH SLAB57.8SY $195.31 $186.90 $374.09 $175.00 $235.00 $350.00
24504(B) 1305 SAW-CUT GROOVING1,336.3SY $5.00 $5.00 $4.98 $4.05 $4.05 $4.05
25504(C) 6250 SEALED EXPANSION JOINT58.3LF $250.00 $252.00 $404.09 $250.00 $310.00 $400.00
26504(D) 6239 CONCRETE RAIL (TR3)1,116.4LF $75.00 $75.00 $95.04 $80.00 $75.00 $160.00
27506(A) 1322 STRUCTURAL STEEL2,120LB $4.00 $2.10 $6.91 $2.10 $2.50 $8.00
28507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY12EA $1,000.00 $735.00 $1,173.73 $1,000.00 $1,000.00 $800.00
29507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY18EA $1,000.00 $840.00 $1,173.73 $1,000.00 $1,000.00 $800.00
30509(A) 1326 CLASS AA CONCRETE404.9CY $625.00 $410.00 $526.52 $700.00 $750.00 $800.00
31509(B) 1328 CLASS A CONCRETE169.8CY $600.00 $455.00 $459.46 $700.00 $750.00 $800.00
32511(A) 1332 REINFORCING STEEL122,660LB $1.00 $0.8400 $1.01 $1.00 $1.25 $1.00
33514(A) 6010 PILES, FURNISHED (HP 10X42)98LF $35.00 $47.25 $43.84 $36.00 $42.00 $30.00
34514(A) 6011 PILES, FURNISHED (HP 12X53)287LF $40.00 $47.25 $42.72 $45.00 $52.00 $35.00
35514(B) 6292 PILES, DRIVEN (HP 10X42)98LF $10.00 $31.50 $21.27 $15.50 $10.00 $15.00
36514(B) 6294 PILES, DRIVEN (HP 12X53)287LF $15.00 $31.50 $21.27 $19.30 $10.00 $17.50
37514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
38516(A) 6094 DRILLED SHAFTS 48" DIAMETER146LF $750.00 $1,050.00 $851.11 $900.00 $850.00 $2,000.00
39516(C) 6200 CROSSHOLE SONIC LOGGING4EA $3,200.00 $2,100.00 $2,459.12 $1,850.00 $1,500.00 $5,000.00
40601(B) 1353 TYPE I-A PLAIN RIPRAP2,992TON $50.00 $37.70 $28.84 $38.00 $34.00 $40.00
41601(C) 1355 TYPE I-A FILTER BLANKET591TON $40.00 $26.70 $18.21 $28.00 $29.00 $30.00
42613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND52LF $23.00 $6.00 $18.05 $24.00 $30.00 $6.50
43613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.54LF $20.00 $6.00 $18.05 $19.00 $30.00 $6.50
44619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $12,500.00 $30,000.00 $9,304.78 $20,000.00 $45,000.00 $35,000.00
45856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)7,824LF $0.7500 $0.7000 $0.8000 $0.6000 $0.6000 $0.6000
46880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,000.00 $4,500.00 $4,984.70 $3,750.00 $3,750.00 $3,750.00
47642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $13,000.00 $14,000.00 $15,602.45 $15,000.00 $10,520.00 $8,500.00
48220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $3,000.00 $1,242.86 $2,500.00 $1,000.00 $5,100.00
49641 1552 MOBILIZATION1LSUM $130,380.00 $80,000.00 $126,146.18 $125,000.00 $150,000.00 $332,000.00