| 10 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$10,000.00 |
$5,000.00 |
$10,550.00 |
$10,000.00 |
$15,000.00 |
$15,000.00 |
$23,500.00 |
$6,500.00 |
| 20 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$60,000.00 |
$35,000.00 |
$44,616.00 |
$50,000.00 |
$40,000.00 |
$35,000.00 |
$48,500.00 |
$8,500.00 |
| 30 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,910 | LF |
$2.75 |
$3.10 |
$1.55 |
$2.78 |
$3.00 |
$2.78 |
$3.78 |
$4.00 |
| 40 | 221(F) 0100 |
TEMPORARY SILT DIKE | 200 | LF |
$10.00 |
$20.50 |
$8.35 |
$18.89 |
$20.00 |
$18.89 |
$20.00 |
$20.00 |
| 50 | 230(A) 2806 |
SOLID SLAB SODDING | 7,890 | SY |
$3.00 |
$3.05 |
$3.08 |
$2.80 |
$2.95 |
$4.50 |
$3.92 |
$5.25 |
| 60 | 233(A) 2817 |
VEGETATIVE MULCHING | 1.63 | AC |
$1,000.00 |
$540.00 |
$250.00 |
$495.00 |
$495.00 |
$495.00 |
$550.00 |
$500.00 |
| 70 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 634 | TON |
$35.00 |
$38.00 |
$36.00 |
$35.00 |
$39.00 |
$28.00 |
$35.50 |
$45.00 |
| 80 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$350.00 |
$350.00 |
$285.00 |
$150.00 |
$300.00 |
$450.00 |
$300.00 |
$500.00 |
| 90 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 200 | CY |
$20.00 |
$10.00 |
$11.00 |
$100.00 |
$15.00 |
$8.00 |
$14.00 |
$20.00 |
| 100 | 501(F) 6352 |
GRANULAR BACKFILL | 82 | CY |
$75.00 |
$70.00 |
$70.00 |
$100.00 |
$82.00 |
$150.00 |
$92.34 |
$85.00 |
| 110 | 503(A) 1311 |
PRESTRESSED CONCRETE BEAMS (TYPE II) | 517 | LF |
$200.00 |
$225.00 |
$218.00 |
$200.00 |
$210.00 |
$280.00 |
$225.75 |
$220.00 |
| 120 | 504(C) 6250 |
SEALED EXPANSION JOINT | 35.5 | LF |
$225.00 |
$325.00 |
$295.00 |
$1,000.00 |
$375.00 |
$300.00 |
$305.06 |
$300.00 |
| 130 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 328.2 | LF |
$90.00 |
$80.00 |
$79.00 |
$40.00 |
$85.00 |
$90.00 |
$84.00 |
$125.00 |
| 140 | 506(A) 1322 |
STRUCTURAL STEEL | 1,420 | LB |
$4.00 |
$3.50 |
$4.00 |
$1.00 |
$3.50 |
$4.00 |
$3.89 |
$4.00 |
| 150 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 12 | EA |
$1,000.00 |
$800.00 |
$1,075.00 |
$1,000.00 |
$1,200.00 |
$1,100.00 |
$920.00 |
$1,500.00 |
| 160 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 12 | EA |
$1,100.00 |
$800.00 |
$1,075.00 |
$1,000.00 |
$1,200.00 |
$1,100.00 |
$920.00 |
$1,500.00 |
| 170 | 509(A) 1326 |
CLASS AA CONCRETE | 114.4 | CY |
$650.00 |
$575.00 |
$665.00 |
$500.00 |
$675.00 |
$750.00 |
$700.00 |
$600.00 |
| 180 | 509(B) 1328 |
CLASS A CONCRETE | 137 | CY |
$675.00 |
$575.00 |
$690.00 |
$500.00 |
$675.00 |
$700.00 |
$715.00 |
$650.00 |
| 190 | 511(A) 1332 |
REINFORCING STEEL | 52,450 | LB |
$1.10 |
$1.15 |
$1.10 |
$2.00 |
$1.20 |
$1.20 |
$1.18 |
$1.50 |
| 200 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 210 | LF |
$36.00 |
$32.00 |
$35.00 |
$30.00 |
$49.00 |
$31.00 |
$37.90 |
$45.00 |
| 210 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 525 | LF |
$45.00 |
$38.00 |
$42.00 |
$41.00 |
$58.00 |
$38.00 |
$45.15 |
$50.00 |
| 220 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 210 | LF |
$18.00 |
$16.00 |
$15.00 |
$8.00 |
$10.00 |
$13.25 |
$14.00 |
$25.00 |
| 230 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 525 | LF |
$20.00 |
$18.00 |
$18.00 |
$8.00 |
$10.00 |
$16.00 |
$14.00 |
$50.00 |
| 240 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 250 | 516(A) 6095 |
DRILLED SHAFTS 54" DIAMETER | 178 | LF |
$825.00 |
$750.00 |
$725.00 |
$600.00 |
$750.00 |
$775.00 |
$828.39 |
$600.00 |
| 260 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 2,108 | TON |
$48.00 |
$50.00 |
$52.20 |
$45.00 |
$52.00 |
$45.00 |
$50.00 |
$70.00 |
| 270 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 645 | TON |
$40.00 |
$41.00 |
$39.00 |
$45.00 |
$40.00 |
$32.00 |
$45.00 |
$45.00 |
| 280 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 64 | LF |
$30.00 |
$22.00 |
$28.00 |
$75.00 |
$35.00 |
$30.00 |
$30.00 |
$40.00 |
| 290 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 32 | LF |
$33.00 |
$22.00 |
$55.00 |
$75.00 |
$35.00 |
$33.00 |
$25.00 |
$50.00 |
| 300 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$10,000.00 |
$15,000.00 |
$12,000.00 |
$20,000.00 |
$15,000.00 |
$15,000.00 |
$23,500.00 |
$6,500.00 |
| 310 | 623(F) 6033 |
GUARDRAIL ANCHOR UNIT (TYPE II) | 4 | EA |
$2,800.00 |
$3,850.00 |
$3,675.00 |
$3,500.00 |
$3,500.00 |
$3,500.00 |
$3,850.00 |
$3,600.00 |
| 320 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 960 | SD |
$0.4000 |
$0.1100 |
$0.1100 |
$0.1000 |
$0.1500 |
$0.1000 |
$0.1200 |
$0.0200 |
| 330 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 1,200 | SD |
$0.9000 |
$0.1100 |
$0.1100 |
$0.1000 |
$0.1500 |
$0.1000 |
$0.1200 |
$0.0200 |
| 340 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 1,200 | SD |
$0.5000 |
$1.95 |
$1.95 |
$1.75 |
$2.00 |
$1.75 |
$1.79 |
$3.00 |
| 350 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 2,880 | SD |
$0.2000 |
$0.5500 |
$0.5500 |
$0.5000 |
$0.5500 |
$0.5000 |
$0.5400 |
$0.5000 |
| 360 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$7,500.00 |
$5,800.00 |
$6,300.00 |
$6,300.00 |
$5,300.00 |
$5,000.00 |
$7,800.00 |
$7,000.00 |
| 370 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$2,500.00 |
$1,800.00 |
$1,000.00 |
$1,500.00 |
$2,500.00 |
$3,000.00 |
$2,500.00 |
| 380 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$72,500.00 |
$44,600.00 |
$55,000.00 |
$80,000.00 |
$76,000.00 |
$70,000.00 |
$53,000.00 |
$85,000.00 |