Bid tab 190314

Let Oct 17, 2019 · Division 7 · Grady Sign up free

‹ Oct 2019 results

BRIDGE AND APPROACHES COUNTY ROAD (NS-2760): OVER LAKE LOUIS BURTSCHI , 2.4 MILES NORTH OF THE US -277 JUNCTION NEAR CEMENT. PROJECT LENGTH = 0.387 MILE

Let date
Thursday, October 17, 2019
Contract
190314
J/P numbers
30462(04)
District
Division 7
County
Grady
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (NS-2760): OVER LAKE LOUIS BURTSCHI , 2.4 MILES NORTH OF THE US -277 JUNCTION NEAR CEMENT. PROJECT LENGTH = 0.387 MILE
Project number
CIRB-226C(085)RB

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$758,958
1 Central Bridge Company Low bidder $925,000 +21.9%
2 K & R BUILDERS, INC. $1,147,462 +51.2% +24.0%
3 HASKELL LEMON CONSTRUCTION CO. $1,248,942 +64.6% +35.0%

Bid tab: unit prices 53 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Central Bridge …#2 K & R BUILDERS,…#3 HASKELL LEMON C…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $2,500.00 $10,000.00 $12,000.00 $11,640.00
2202(A) 0183 UNCLASSIFIED EXCAVATION38CY $15.00 $26.33 $68.50 $16.50
3202(D) 0184 UNCLASSIFIED BORROW50CY $20.00 $17.99 $94.00 $22.00
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $2,500.00 $8,000.00 $11,000.00 $2,752.00
5221(C) 2801 TEMPORARY SILT FENCE2,044LF $2.00 $2.15 $2.25 $1.95
6221(F) 0100 TEMPORARY SILT DIKE30LF $10.00 $35.00 $40.00 $36.20
7230(A) 2806 SOLID SLAB SODDING500SY $2.00 $8.39 $12.00 $8.65
8233(A) 2817 VEGETATIVE MULCHING0.5AC $300.00 $3,100.00 $3,000.00 $3,192.00
9307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE2,369SY $2.75 $9.25 $7.20 $16.00
10325 5271 SEPARATOR FABRIC765SY $2.50 $1.50 $5.25 $5.50
11402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E341TON $35.00 $36.62 $53.60 $46.90
12407(B) 0250 TACK COAT1,210GAL $3.50 $3.99 $4.40 $3.85
13408 5774 PRIME COAT827GAL $4.75 $6.34 $6.70 $7.65
14409(A) 4242 FABRIC REINFORCEMENT739SY $3.00 $3.45 $4.10 $9.05
15411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)456TON $75.00 $92.23 $108.00 $96.50
16411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)1,313TON $80.00 $88.02 $108.00 $90.30
17412 5267 COLD MILLING PAVEMENT888SY $3.50 $9.59 $16.00 $11.70
18501(G) 6315 CLSM BACKFILL68CY $200.00 $201.65 $420.00 $392.00
19509(D) 0325 CLASS C CONCRETE10CY $350.00 $240.29 $415.00 $400.00
20601(B) 0536 TYPE I-A PLAIN RIPRAP2,477TON $40.00 $43.02 $51.90 $30.80
21613(EE) 5610 (SP) 18" CORRUGATED POLYPROPYLENE PIPE100LF $50.00 $37.35 $38.00 $34.40
22613(L) 5726 18" PREFAB. CULVERT END SECTION, ROUND2EA $800.00 $494.80 $314.00 $1,055.00
23619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $3,500.00 $1,500.00 $7,250.00 $9,640.00
24619(B) 4728 REMOVAL OF ASPHALT PAVEMENT366SY $5.00 $8.11 $20.00 $33.20
25619(C) 0924 SAWING PAVEMENT1,710LF $5.00 $4.25 $6.00 $4.15
26501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON120CY $25.00 $27.28 $31.00 $26.60
27501(D) 6353 UNCLASSIFIED BACKFILL30CY $25.00 $84.46 $40.00 $123.00
28501(G) 6309 CLSM BACKFILL70CY $185.00 $189.85 $268.00 $259.50
29502(A) 6173 ENGINEERED FALSEWORK1LSUM $10,000.00 $40,000.00 $81,000.00 $166,010.00
30504(B) 1305 SAW-CUT GROOVING129.1SY $6.00 $20.30 $25.00 $21.20
31504(D) 6245 CONCRETE RAIL (TR4)135LF $95.00 $176.69 $255.00 $301.00
32506(A) 1322 STRUCTURAL STEEL2,850LB $3.00 $7.27 $9.00 $5.65
33509(A) 1326 CLASS AA CONCRETE148.9CY $650.00 $726.66 $1,000.00 $667.50
34509(B) 1328 CLASS A CONCRETE51CY $650.00 $815.95 $1,137.50 $1,282.00
35510(C) 6137 SLOPE WALL (4")26.5SY $125.00 $271.49 $390.00 $595.50
36511(A) 1332 REINFORCING STEEL26,090LB $1.00 $1.23 $1.08 $1.85
37514(A) 6010 PILES, FURNISHED (HP 10X42)1,288LF $30.00 $36.82 $37.10 $34.80
38514(B) 6292 PILES, DRIVEN (HP 10X42)1,288LF $20.00 $35.48 $15.90 $16.90
39514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00
40619(B) 2500 REMOVAL OF BRIDGE ITEMS1LSUM $15,000.00 $25,000.00 $22,000.00 $59,015.00
41623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE1,381.25LF $30.00 $14.70 $20.00 $15.40
42623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $2,700.00 $2,940.00 $3,277.50 $3,082.00
43623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $2,250.00 $2,782.50 $3,000.00 $2,917.00
44805(A) 8722 (PL)REMOVAL OF EXISTING SIGNS1LSUM $500.00 $1,575.00 $1,700.00 $1,651.00
45850(A) 8110 SHEET ALUMINUM SIGNS95SF $23.00 $27.30 $28.75 $28.60
46851(C) 8324 2" SQUARE TUBE POST228LF $8.00 $12.60 $14.00 $13.20
47853 9069 GUARDRAIL DELINEATORS(TYPE 2, CODE 1)35EA $15.00 $13.88 $16.00 $14.50
48856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)7,432LF $0.5000 $0.8300 $0.9500 $0.8700
49856(A) 8555 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE)50LF $2.50 $3.23 $3.60 $3.30
50880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $7,500.00 $7,000.00 $8,900.00 $13,245.00
51642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $7,500.00 $10,000.00 $9,000.00 $15,490.00
52220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,500.00 $2,500.00 $3,700.00 $3,852.00
53641 1399 MOBILIZATION1LSUM $60,500.00 $50,000.00 $61,000.00 $133,983.36