BRIDGE AND APPROACHES SH -66B:OVER CAPTAIN CREEK , 1.6 MILES NORTHEAST OF THE SH -66 JUNCTION IN WELLSTON . PROJECT LENGTH = 0.352 MILE

Let date
Thursday, June 18, 2020
Contract
200229
J/P numbers
28034(04)
District
Division 3
County
Lincoln
Highway
Limits
BRIDGE AND APPROACHES SH -66B:OVER CAPTAIN CREEK , 1.6 MILES NORTHEAST OF THE SH -66 JUNCTION IN WELLSTON . PROJECT LENGTH = 0.352 MILE
Project number
STP-241C(059)PM

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,820,934
1 L & N BRIDGE, LLC Low bidder $2,372,504 -15.9%
2 BRIDGECO CONTRACTORS, INC. $2,498,926 -11.4% +5.3%
3 HASKELL LEMON CONSTRUCTION CO. $2,557,000 -9.4% +7.8%
4 K & R BUILDERS, INC. $2,598,967 -7.9% +9.5%
5 SEWELL BROS., INC. $2,763,040 -2.1% +16.5%
6 C3 Construction, Inc. $2,777,176 -1.6% +17.1%
8 Frontier Bridge, Inc. $3,109,402 +10.2% +31.1%

Bid tab: unit prices 80 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 L & N BRIDGE, L…#2 BRIDGECO CONTRA…#3 HASKELL LEMON C…#4 K & R BUILDERS,…#5 SEWELL BROS., I…#6 C3 Construction…#8 Frontier Bridge…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $16,174.50 $7,500.00 $17,600.00 $29,260.00 $18,000.00 $10,000.00 $12,610.73 $11,550.00
2202(A) 0183 UNCLASSIFIED EXCAVATION3,120CY $10.20 $10.00 $8.00 $7.15 $10.05 $8.00 $8.73 $8.67
3205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $11,597.60 $7,500.00 $8,000.00 $18,565.00 $11,150.00 $17,500.00 $10,895.67 $8,800.00
4221(C) 2801 TEMPORARY SILT FENCE2,930LF $2.40 $1.95 $2.15 $2.00 $2.20 $2.15 $1.97 $4.35
5221(F) 0100 TEMPORARY SILT DIKE56LF $11.10 $7.99 $30.00 $8.15 $9.00 $8.80 $8.06 $26.95
6221(K) 0600 TEMPORARY FIBER LOG70LF $6.70 $6.75 $12.00 $6.90 $7.70 $7.40 $6.81 $20.85
7230(A) 2806 SOLID SLAB SODDING9,565SY $2.70 $2.30 $2.50 $2.35 $2.85 $2.65 $2.32 $2.75
8233(A) 2817 VEGETATIVE MULCHING1.98AC $1,086.40 $650.00 $750.00 $662.00 $675.00 $700.00 $655.76 $3,245.00
9241 2832 MOWING3.96AC $137.30 $225.00 $300.00 $229.00 $235.00 $245.00 $226.99 $544.50
10303(A) 2100 AGGREGATE BASE TYPE A1,057CY $66.50 $65.00 $78.75 $76.40 $95.00 $119.00 $121.02 $119.65
11307(K) 4300 STABILIZED SUBGRADE5,805SY $6.30 $4.50 $6.30 $5.85 $6.60 $7.00 $7.64 $6.60
12326(A) 0100 GEOTEXTILE REINFORCEMENT5,209SY $2.80 $4.00 $3.35 $2.30 $5.50 $6.00 $6.37 $6.16
13402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E929TON $36.30 $30.00 $42.00 $40.70 $39.20 $55.00 $40.38 $55.26
14407(B) 0250 TACK COAT762GAL $4.10 $2.50 $5.25 $3.55 $5.50 $2.75 $6.37 $2.75
15408 5774 PRIME COAT3,597GAL $4.80 $6.50 $6.30 $4.00 $6.60 $7.00 $7.64 $7.15
16411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,596TON $100.10 $78.25 $109.20 $82.20 $104.50 $88.00 $121.02 $86.08
17411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)560TON $128.30 $99.25 $120.75 $127.00 $126.50 $115.00 $146.49 $109.18
18509(D) 0325 CLASS C CONCRETE5CY $355.00 $750.00 $300.00 $846.00 $400.00 $500.00 $386.63 $715.18
19613(A) 0491 18" R.C.PIPE CLASS III70LF $53.30 $50.00 $46.00 $46.90 $78.00 $35.00 $54.67 $73.28
20613(L) 5726 18" PREFAB. CULVERT END SECTION, ROUND2EA $776.30 $600.00 $1,100.00 $1,120.00 $1,150.00 $600.00 $963.31 $1,043.26
21619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $6,382.00 $3,000.00 $2,500.00 $2,546.00 $8,000.00 $3,000.00 $6,114.52 $5,500.00
22619(B) 4728 REMOVAL OF ASPHALT PAVEMENT4,370SY $6.50 $3.50 $6.30 $7.65 $7.85 $9.00 $8.28 $8.80
23619(B) 4780 REMOVAL OF GUARDRAIL560LF $4.20 $3.00 $4.00 $4.00 $3.30 $3.50 $3.03 $3.30
24619(C) 0924 SAWING PAVEMENT204LF $6.40 $4.00 $8.00 $9.10 $11.00 $5.00 $4.54 $6.60
25623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE350LF $22.00 $20.00 $22.00 $18.80 $22.00 $22.00 $20.18 $22.00
26623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $2,724.70 $2,200.00 $2,500.00 $2,648.00 $2,420.00 $2,420.00 $2,219.49 $2,420.00
27623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $2,190.10 $1,800.00 $2,000.00 $1,732.00 $1,980.00 $1,980.00 $1,815.95 $2,035.00
28624(C) 4458 FENCE-STYLE SWF (4 BARBED WIRE)469LF $5.40 $10.00 $14.00 $8.30 $11.00 $11.00 $10.09 $16.50
29853 9069 GUARDRAIL DELINEATORS(TYPE 2, CODE 1)14EA $13.10 $20.00 $25.00 $15.30 $22.00 $22.00 $20.18 $22.00
30501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON175CY $23.00 $10.00 $10.00 $17.70 $12.00 $15.00 $22.93 $22.00
31501(G) 6309 CLSM BACKFILL149.9CY $150.00 $175.00 $216.00 $181.00 $170.00 $150.00 $189.20 $180.25
32504 6179 BRIDGE TRAFFIC RAIL671.1LF $120.00 $165.00 $130.00 $177.50 $155.00 $220.00 $368.33 $159.12
33504(A) 1304 APPROACH SLAB204.6SY $200.00 $200.00 $270.00 $256.50 $245.00 $210.00 $192.05 $292.46
34504(B) 1305 SAW-CUT GROOVING820.3SY $6.00 $4.80 $5.10 $4.90 $5.28 $5.30 $6.62 $5.28
35504(C) 6250 SEALED EXPANSION JOINT58.22LF $275.00 $275.00 $253.00 $314.50 $325.00 $280.00 $293.57 $285.30
36506(A) 4050 STRUCTURAL STEEL M270 GRADE 50W288,860LB $2.30 $1.79 $1.70 $1.59 $1.76 $1.85 $1.51 $2.01
37507(A) 6170 STAINLESS STEEL FIXED BEARING ASSEMBLY4EA $2,500.00 $2,000.00 $1,675.00 $1,969.00 $1,860.00 $2,000.00 $2,370.38 $1,965.54
38507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY12EA $2,200.00 $2,000.00 $1,675.00 $1,969.00 $1,860.00 $2,000.00 $2,370.38 $1,965.54
39509(A) 1326 CLASS AA CONCRETE170.9CY $650.00 $800.00 $675.00 $699.00 $675.00 $600.00 $774.56 $726.90
40509(B) 1328 CLASS A CONCRETE218.3CY $610.00 $800.00 $675.00 $582.50 $697.50 $600.00 $630.32 $721.04
41509(D) 1331 CLASS C CONCRETE20CY $550.00 $600.00 $375.00 $520.50 $650.00 $500.00 $403.47 $622.75
42511 6306 MECHANICAL SPLICES64EA $35.00 $35.00 $38.94 $64.60 $55.00 $45.00 $35.06 $52.69
43511(A) 1332 REINFORCING STEEL630LB $1.20 $1.00 $2.00 $3.75 $1.55 $1.00 $1.06 $1.34
44511(B) 6010 EPOXY COATED REINFORCING STEEL99,910LB $1.30 $1.20 $1.14 $1.15 $1.20 $1.25 $0.8000 $1.24
45512 6280 CLEANING AND PAINTING BRIDGE METAL RAIL200LF $15.00 $14.60 $16.00 $14.90 $16.25 $75.00 $18.60 $55.00
46512(A) 1323 PAINTING EXISTING STRUCTURES1LSUM $75,000.00 $79,820.00 $84,900.00 $81,300.00 $88,000.00 $210,000.00 $101,679.37 $220,000.00
47512(B) 6303 COLLECTION AND HANDLING OF WASTE1LSUM $25,000.00 $18,681.00 $21,500.00 $20,000.00 $21,000.00 $16,500.00 $23,796.95 $51,024.33
48514(A) 6010 PILES, FURNISHED (HP 10X42)211LF $34.00 $33.00 $22.45 $31.80 $30.10 $25.00 $35.59 $32.42
49514(A) 6011 PILES, FURNISHED (HP 12X53)704LF $39.00 $40.00 $28.00 $34.20 $32.90 $30.00 $37.79 $38.48
50514(B) 6292 PILES, DRIVEN (HP 10X42)211LF $14.00 $14.25 $15.00 $30.10 $12.90 $20.00 $20.38 $24.20
51514(B) 6294 PILES, DRIVEN (HP 12X53)704LF $14.00 $17.25 $14.00 $19.40 $14.10 $20.00 $20.38 $22.00
52514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
53515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)871SY $4.20 $4.00 $4.40 $4.05 $4.40 $3.50 $4.54 $4.40
54516(A) 6095 DRILLED SHAFTS 54" DIAMETER252LF $750.00 $700.00 $856.46 $948.50 $750.00 $800.00 $820.22 $950.56
55516(C) 6200 CROSSHOLE SONIC LOGGING6EA $2,600.00 $1,575.00 $1,735.00 $2,744.00 $2,500.00 $2,000.00 $2,006.33 $4,950.00
56523(A) 6550 SEALER CRACK PREPARATION113LF $4.40 $6.00 $7.00 $6.10 $6.60 $6.00 $7.64 $6.60
57523(B) 6560 SEALER RESIN1.3GAL $130.00 $150.00 $175.00 $153.00 $165.00 $150.00 $191.08 $165.00
58542 4610 (PL)INSTALLATION OF BRIDGE ITEMS(TYPE A)1LSUM $80,000.00 $3,500.00 $47,500.00 $55,000.00 $44,500.00 $75,000.00 $12,738.58 $110,000.00
59542 4625 (PL)INSTALLATION OF BRIDGE ITEMS(TYPE B)10EA $750.00 $1,000.00 $1,219.00 $1,196.00 $1,415.00 $900.00 $900.44 $2,093.19
60601(B) 1353 TYPE I-A PLAIN RIPRAP1,950TON $42.00 $45.00 $48.80 $50.30 $53.75 $55.00 $45.45 $51.07
61601(C) 1355 TYPE I-A FILTER BLANKET280TON $39.00 $35.00 $48.00 $40.60 $41.70 $45.00 $34.71 $40.32
62613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND64LF $32.00 $28.00 $45.00 $58.40 $28.00 $35.00 $11.16 $27.22
63613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.50LF $25.00 $28.00 $50.00 $28.30 $33.00 $35.00 $12.15 $36.87
64619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $85,000.00 $40,000.00 $81,000.00 $88,500.00 $57,500.00 $75,000.00 $57,323.62 $104,500.00
65623 0100 (PL)GUARDRAIL CURBING2EA $900.00 $750.00 $3,000.00 $834.50 $1,500.00 $1,000.00 $20.46 $1,508.61
66104 0955 (SP) RAILROAD FLAGGING(NON-BIDDABLE)10DAY $600.00 $600.00 $600.00 $600.00 $600.00 $600.00 $600.00 $600.00
67880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF1,800SD $0.5000 $0.2500 $0.3000 $0.5100 $0.2800 $0.2700 $0.2500 $0.2800
68880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF3,060SD $0.3000 $0.2500 $0.3000 $0.5100 $0.2800 $0.2700 $0.2500 $0.2800
69880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF360SD $1.00 $0.2500 $0.3000 $2.55 $0.2800 $0.2700 $0.2500 $0.2800
70880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)1,620SD $0.5000 $0.2500 $0.3000 $1.00 $0.2800 $0.2700 $0.2500 $0.2800
71880(E) 8860 WARNING LIGHTS(TYPE A)3,240SD $0.2000 $3.00 $3.30 $0.3600 $6.00 $3.05 $3.03 $3.30
72882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN582SD $11.50 $5.00 $6.00 $12.20 $5.50 $5.05 $5.04 $5.50
73805(A) 8724 (PL)REMOVAL OF EXISTING SIGNS12EA $58.10 $50.00 $100.00 $25.50 $55.00 $55.00 $50.44 $55.00
74850(A) 8110 SHEET ALUMINUM SIGNS65SF $21.10 $15.00 $16.00 $15.30 $16.50 $15.25 $15.13 $16.50
75851(C) 8324 2" SQUARE TUBE POST172LF $8.50 $8.00 $9.00 $3.55 $8.80 $8.40 $8.07 $8.80
76855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)7,796LF $0.9000 $0.5000 $0.6000 $0.8700 $0.5500 $0.5200 $0.5000 $0.5500
77642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $11,000.00 $16,000.00 $14,200.00 $22,500.00 $12,500.00 $9,500.00 $13,375.51 $9,460.00
78220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,500.00 $3,000.00 $3,300.00 $5,000.00 $4,500.00 $4,000.00 $1,910.79 $3,300.00
79640(A) 1398 FIELD OFFICE1EA $10,000.00 $7,500.00 $9,000.00 $2,546.00 $10,000.00 $7,500.00 $764.31 $10,560.00
80641 1399 MOBILIZATION1LSUM $150,000.00 $142,500.00 $97,000.00 $154,922.57 $129,252.00 $100,000.00 $259,357.55 $176,110.92