$102.09Avg low bid / LF
$108.70Avg of all bids
$97.40Avg engineer's estimate
96Jobs · 28,509.4 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 13 | 3,340.6 | $94.44 | $128.73 |
| 2020 | 34 | 12,021.3 | $99.49 | $106.68 |
| 2019 | 23 | 7,045.5 | $102.23 | $106.95 |
| 2018 | 21 | 5,462 | $112.49 | $103.51 |
| 2017 | 5 | 640 | $100.80 | $94.61 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 19, 2021 | 210149 | Nhpp-260n(054)pm | 49.6 LF | $97.67 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Aug 19, 2021 | 210149 | Nhpp-260n(054)pm | 876 LF | $106.80 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Jul 15, 2021 | 210211 | LoganDivision 4 | 640 LF | $100.00 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| May 20, 2021 | 210127 | BlaineDivision 5 | 410 LF | $70.55 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210139 | McclainDivision 3 | 252 LF | $83.00 | Silver Star Construction Company, Inc. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 482 LF | $99.90 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210143 | MurrayDivision 7 | 90 LF | $121.00 | OVERLAND CORPORATION |
| Apr 15, 2021 | 210114 | NobleDivision 4 | 52 LF | $100.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Apr 15, 2021 | 210102 | CoalDivision 3 | 80 LF | $60.00 | L & N BRIDGE, LLC |
| Feb 18, 2021 | 210062 | Pontotoc | 48 LF | $72.10 | HASKELL LEMON CONSTRUCTION CO. |
| Jan 21, 2021 | 210018 | HarperDivision 6 | 33 LF | $121.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 101 LF | $106.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 210025 | KingfisherDivision 4 | 54 LF | $62.20 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 210035 | Pontotoc | 173 LF | $73.35 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 19, 2020 | 200339 | BlaineDivision 5 | 130 LF | $96.50 | CORNELL CONSTRUCTION COMPANY, INC. |
| Nov 19, 2020 | 200346 | ClevelandDivision 3 | 608 LF | $114.25 | Redlands Contracting, LLC |
| Nov 19, 2020 | 200348 | CusterDivision 5 | 18 LF | $132.16 | Frontier Bridge, Inc. |
| Nov 19, 2020 | 200355 | RogersDivision 8 | 755 LF | $76.00 | EMERY SAPP & SONS, INC. |
| Nov 19, 2020 | 200357 | SequoyahDivision 1 | 72 LF | $95.80 | APAC-CENTRAL, INC. |
| Oct 15, 2020 | 200077 | PottawatomieDivision 3 | 108 LF | $75.00 | OVERLAND CORPORATION |
| Oct 15, 2020 | 200303 | BeaverDivision 6 | 380 LF | $82.00 | J & R SAND COMPANY, INC. |
| Sep 17, 2020 | 200273 | Stp-208b(091)pm | 743 LF | $69.35 | OVERLAND CORPORATION |
| Sep 17, 2020 | 200291 | PittsburgDivision 2 | 382 LF | $76.46 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Sep 17, 2020 | 200292 | PottawatomieDivision 3 | 484 LF | $93.00 | Silver Star Construction Company, Inc. |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 521.3 LF | $130.98 | SHERWOOD CONSTRUCTION CO., INC. |
| Aug 20, 2020 | 200225 | GradyDivision 7 | 84 LF | $95.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 105 LF | $99.87 | SHERWOOD CONSTRUCTION CO., INC. |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 72 LF | $80.00 | SEWELL BROS., INC. |
| Jul 23, 2020 | 200251 | HarmonDivision 5 | 100 LF | $86.10 | Frontier Bridge, Inc. |
| Jul 23, 2020 | 200061 | DeweyDivision 5 | 440 LF | $106.10 | J & R SAND COMPANY, INC. |
| Jun 18, 2020 | 200222 | CanadianDivision 4 | 72 LF | $100.62 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200126 | TulsaDivision 8 | 1,433 LF | $97.75 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 104 LF | $65.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 862 LF | $115.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Apr 16, 2020 | 200028 | Cirb-264d(069)rb | 44 LF | $78.40 | THE CUMMINS CONSTRUCTION CO., INC. |
| Apr 16, 2020 | 200175 | WagonerDivision 1 | 148 LF | $98.65 | APAC-CENTRAL, INC. |
| Mar 19, 2020 | 200132 | CusterDivision 5 | 94 LF | $120.00 | SEWELL BROS., INC. |
| Mar 19, 2020 | 200133 | HaskellDivision 1 | 117 LF | $105.31 | C3 Construction, Inc. |
| Mar 19, 2020 | 200085 | TulsaDivision 8 | 162 LF | $130.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Mar 19, 2020 | 200032 | SeminoleDivision 3 | 32 LF | $120.00 | RRY SERVICES LLC |
| Mar 19, 2020 | 200110 | McintoshDivision 1 | 108 LF | $96.40 | Robinson Construction, LLC |
| Feb 20, 2020 | 200069 | LincolnDivision 3 | 30 LF | $107.77 | Cowboy Contracting, Inc. |
| Feb 20, 2020 | 200057 | ClevelandDivision 3 | 262 LF | $105.40 | Silver Star Construction Company, Inc. |
| Feb 20, 2020 | 200183 | Stp-170c(127)pm | 228 LF | $85.00 | J & R SAND COMPANY, INC. |
| Jan 16, 2020 | 200020 | NobleDivision 4 | 82 LF | $102.30 | Evans & Associates Construction Co., Inc. |
| Jan 16, 2020 | 190317 | KayDivision 4 | 72 LF | $92.50 | BRIDGECO CONTRACTORS, INC. |
| Jan 16, 2020 | 200001 | AlfalfaDivision 6 | 1,412 LF | $115.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200092 | TulsaDivision 8 | 1,058 LF | $95.00 | APAC-CENTRAL, INC. |
| Jan 16, 2020 | 200009 | CusterDivision 5 | 625 LF | $110.00 | SEWELL BROS., INC. |
| Jan 16, 2020 | 190356 | KayDivision 4 | 74 LF | $100.00 | Evans & Associates Construction Co., Inc. |
| Nov 14, 2019 | 190389 | TulsaDivision 8 | 479 LF | $109.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Nov 14, 2019 | 190109 | CanadianDivision 4 | 58 LF | $67.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Nov 14, 2019 | 190341 | CaddoDivision 7 | 256 LF | $88.00 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Sep 19, 2019 | 190242 | ChoctawDivision 2 | 458 LF | $98.00 | HUB Construction, Inc. |
| Aug 22, 2019 | 190271 | TulsaDivision 8 | 110 LF | $165.00 | Paragon Contractors, LLC |
| Aug 22, 2019 | 190262 | TulsaDivision 8 | 950 LF | $96.00 | BECCO CONTRACTORS, INC. |
| Jul 25, 2019 | 190265 | BeckhamDivision 5 | 109 LF | $106.30 | CASWELL CONSTRUCTION, INC. |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 1,182 LF | $108.50 | DUIT CONSTRUCTION COMPANY, INC. |
| Jul 25, 2019 | 190215 | MarshallDivision 2 | 97 LF | $82.15 | OVERLAND CORPORATION |
| Jun 20, 2019 | 190195 | Stp-214b(069)ag | 444 LF | $127.20 | Silver Star Construction Company, Inc. |
| Jun 20, 2019 | 190142 | Jefferson | 46 LF | $62.75 | OVERLAND CORPORATION |
| Jun 20, 2019 | 190195 | Stp-214b(069)ag | 248 LF | $115.50 | Silver Star Construction Company, Inc. |
| Jun 20, 2019 | 190149 | CusterDivision 5 | 78 LF | $107.00 | Treas Construction Inc |
| Jun 20, 2019 | 190156 | OklahomaDivision 4 | 213 LF | $90.00 | SCHWARZ PAVING CO., INC. |
| May 16, 2019 | 190027 | WashingtonDivision 8 | 252 LF | $115.00 | BECCO CONTRACTORS, INC. |
| May 16, 2019 | 180351 | Cotton | 112 LF | $79.00 | SEWELL BROS., INC. |
| May 16, 2019 | 190117 | KiowaDivision 5 | 126 LF | $78.00 | SEWELL BROS., INC. |
| May 16, 2019 | 190132 | Pontotoc | 156 LF | $91.29 | OVERLAND CORPORATION |
| Apr 18, 2019 | 190165 | StephensDivision 7 | 244 LF | $77.80 | OVERLAND CORPORATION |
| Apr 18, 2019 | 180355 | GradyDivision 7 | 346 LF | $81.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 14, 2019 | 190133 | RogersDivision 8 | 472.5 LF | $154.59 | SHERWOOD CONSTRUCTION CO., INC. |
| Feb 14, 2019 | 190101 | Pontotoc | 491 LF | $65.35 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 17, 2019 | 180191 | Cotton | 22 LF | $84.00 | SEWELL BROS., INC. |
| Jan 17, 2019 | 180358 | Stp-242c(058)ss | 96 LF | $85.00 | RRY SERVICES LLC |
| Nov 15, 2018 | 180238 | GradyDivision 7 | 64 LF | $80.00 | SEWELL BROS., INC. |
| Nov 15, 2018 | 180347 | CarterDivision 7 | 308 LF | $70.05 | OVERLAND CORPORATION |
| Nov 15, 2018 | 180293 | Stp-255c(431)ag | 552 LF | $162.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Nov 15, 2018 | 180359 | OklahomaDivision 4 | 1,230 LF | $120.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Oct 18, 2018 | 180283 | DelawareDivision 8 | 138 LF | $73.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Oct 18, 2018 | 180188 | CarterDivision 7 | 134 LF | $72.50 | OVERLAND CORPORATION |
| Sep 20, 2018 | 180298 | PawneeDivision 8 | 132 LF | $110.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Sep 20, 2018 | 180280 | CraigDivision 8 | 359 LF | $105.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Jul 19, 2018 | 180251 | Nhppi-4000-(064)pm | 445 LF | $140.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Jun 14, 2018 | 180229 | Nhppi-4440-(007)pm | 1,100 LF | $119.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Jun 14, 2018 | 180231 | WashitaDivision 5 | 118 LF | $121.80 | CASWELL CONSTRUCTION, INC. |
| May 17, 2018 | 180193 | CreekDivision 8 | 12 LF | $135.00 | Cimarron Construction Company, LLC |
| May 17, 2018 | 180211 | StephensDivision 7 | 122 LF | $63.32 | OVERLAND CORPORATION |
| May 17, 2018 | 180190 | ClevelandDivision 3 | 49 LF | $105.50 | Silver Star Construction Company, Inc. |
| Mar 15, 2018 | 180122 | Acstp-277d(044)ur | 270 LF | $84.05 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 15, 2018 | 180122 | Acstp-277d(044)ur | 121 LF | $54.85 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 15, 2018 | 180129 | ComancheDivision 7 | 48 LF | $85.00 | Redlands Contracting, LLC |
| Feb 15, 2018 | 180113 | Roger MillsDivision 5 | 72 LF | $78.00 | CASWELL CONSTRUCTION, INC. |
| Feb 15, 2018 | 180099 | OklahomaDivision 4 | 9 LF | $150.00 | RUDY CONSTRUCTION CO. |
| Feb 15, 2018 | 180108 | OsageDivision 8 | 51 LF | $97.50 | BRIDGECO CONTRACTORS, INC. |
| Jan 18, 2018 | 180030 | RogersDivision 8 | 48 LF | $85.00 | BECCO CONTRACTORS, INC. |
| Jan 18, 2018 | 180032 | SeminoleDivision 3 | 80 LF | $90.00 | T. McDonald Construction, Inc. |
| Aug 17, 2017 | 170009 | Acstp-110c(192)ss | 121 LF | $85.80 | Treas Construction Inc |
| Feb 16, 2017 | 170004 | BeckhamDivision 5 | 144 LF | $83.20 | CASWELL CONSTRUCTION, INC. |
| Feb 16, 2017 | 170035 | OklahomaDivision 4 | 264 LF | $113.50 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 16, 2017 | 170064 | CaddoDivision 7 | 42 LF | $101.15 | FRONTIER BRIDGE, INC. / BRIDGECO CONTRACTORS, INC. |
| Feb 16, 2017 | 170076 | GarvinDivision 3 | 69 LF | $115.00 | K & R BUILDERS, INC. |