| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Apr 25, 2025 | 85774 | Rock IslandDistrict 2 | Pavement reconstruction, sidewalks, storm sewer, curb and gutter, traffic signals, lighting, and landscaping on 15 Avenue from 6th Street to 13th Street in East Moline. | — | Executed | Valley Construction Co. $12,185,222 · | ||
| Apr 25, 2025 | 85776 | StephensonDistrict 2 | Removal and replacement of guardrail and terminals on various routes in Stephenson County. | — | Executed | Northern Contracting, Inc. $947,223 · | ||
| Apr 25, 2025 | 85777 | WhitesideDistrict 2 | Resurfacing on Fenton Road 0.8 mile south of Garden Plain Road to Black Road. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $1,439,241 · | ||
| Apr 25, 2025 | 85778 | OgleDistrict 2 | Extension of two industrial rail spurs from east of Steward Street to south of Ritchie Road in Rochelle. Includes; concrete paving, precast concrete box culverts, storm sewers, and landscaping. | — | Executed | McCarthy Improvement Company $4,668,879 · | ||
| Apr 25, 2025 | 87862 | LivingstonDistrict 3 | HMA resurfacing with aggregate shoulders on various county highways in Livingston County. | — | Executed | H. J. Eppel & Co. $1,638,174 · | ||
| Apr 25, 2025 | 87880 | BureauDistrict 3 | Replace sidewalks and ADA ramp improvements along Cleveland street from Peru Avenue to Summit Avenue in Ladd. | — | Executed | Gillan Construction LLC $255,362 · | ||
| Apr 25, 2025 | 87881 | LaSalleDistrict 3 | Sidewalk removal and replacement at various locations in Mendota. | — | Executed | D. Construction, Inc. $247,455 · | ||
| Apr 25, 2025 | 89780 | WarrenDistrict 4 | Pavement reconstruction on West Harlem Avenue from US 34 to North Main Street in Monmouth. | — | Executed | Brandt Construction Co. $2,855,658 · | ||
| Apr 25, 2025 | 89802 | TazewellDistrict 4 | HMA resurfacing and construction of a Multi-use path along Detroit Avenue in Morton. Includes; sidewalks, pedestrian signals, ADA ramps, and curb and gutter. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $2,452,499 · | ||
| Apr 25, 2025 | 89852 | TazewellDistrict 4 | Sidewalk construction at various locations in the City of Washington. | — | Executed | Stark Excavating, Inc. $791,727 · | ||
| Apr 25, 2025 | 89868 | MercerDistrict 4 | Construct a shared-use path along 9th Avenue from 6th Street to 4th Street in Aledo. Includes; Curb and gutter, storm sewer, HMA Patching, and PCC entrances. | — | Executed | Phoenix Corporation of the Quad Cities $918,761 · | ||
| Apr 25, 2025 | 91650 | VermilionDistrict 5 | HMA shoulders with rumble strips on Perrysville Road from Brewer Road to the Indiana State Line. | — | Executed | Cross Construction, Inc. $1,720,330 · | ||
| Apr 25, 2025 | 91654 | VermilionDistrict 5 | Sidewalk replacement along Jefferson Street and Walnut Street in Westville. | — | Executed | SNC Construction, Inc. $273,470 · | ||
| Apr 25, 2025 | 93829 | PikeDistrict 6 | Construct a single-span PPC deck beam bridge to carry TR 424B over Blue Creek in Pike County. Includes; Aggregate roadway reconstruction and channel excavation. | — | Executed | County Contractors, Inc. $391,972 · | ||
| Apr 25, 2025 | 93830 | AdamsDistrict 6 | HMA resurfacing on South 18th Street from Harrison Street to Ohio Street in Quincy. Includes; sidewalks and ADA improvements. | — | Executed | Diamond Construction Company $1,576,416 · | ||
| Apr 25, 2025 | 95940 | ShelbyDistrict 7 | Construct a PCC Bike path with a single-span prefabricated pedestrian structure along IL 16 in Shelbyville. Includes; ADA ramps, drainage improvements, signage, and traffic signal improvements. | — | Executed | Kinney Contractors, Inc. $2,495,777 · | ||
| Apr 25, 2025 | 95969 | ClarkDistrict 7 | Sidewalk replacement on 7th Street from Oak Street to Mulberry Street, and on Mulberry Street from 6th St. to Michigan Avenue in Marshall. | — | Executed | Feutz Contractors, Inc. $394,399 · | ||
| Apr 25, 2025 | 95972 | EffinghamDistrict 7 | HMA resurfacing on N 300 Street from 475 N to the Effingham/Fayetteville county line. Includes; aggregate shoulders, and pavement markings. | — | Executed | Howell Paving, Inc. $2,411,360 · | ||
| Apr 25, 2025 | 95975 | ColesDistrict 7 | Resurfacing on Madison Avenue from 7th Street to 18th Street in Charleston. | — | Executed | Ne-Co Asphalt Co., Inc. $356,482 · | ||
| Apr 25, 2025 | 95976 | ShelbyDistrict 7 | Cold-in-place recycling with HMA surface and binder on CH 3 from Findlay to the Moultrie County line. Includes aggregate shoulders and pavement markings. | — | Executed | Howell Paving, Inc. $2,057,823 · | ||
| Apr 25, 2025 | 95977 | MaconDistrict 7 | Construct a shared-use path along Harryland Road from Sundance Drive to North Baltimore Avenue in Mt. Zion. | — | Executed | Kinney Contractors, Inc. $247,095 · | ||
| Apr 25, 2025 | 95978 | MaconDistrict 7 | Construct multi-use paths at various locations in Forsyth. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $536,307 · | ||
| Apr 25, 2025 | 97839 | MadisonDistrict 8 | HMA resurfacing on Esic Drive from University Drive to IL 157 in Edwardsville. Includes; ADA improvements, storm sewer, and signage. | — | Executed | Charles E. Mahoney Co. $615,086 · | ||
| Apr 25, 2025 | 97852 | JerseyDistrict 8 | Pavement reconstruction and widening on Hollow Avenue from 0.1 mile west of Waggoner Avenue to 0.1 mile west of North Hickory Street in Jerseyville. | — | Executed | Baxmeyer Construction, Inc. $2,063,878 · | ||
| Apr 25, 2025 | 97857 | WashingtonDistrict 8 | Resurface CH 12 from CH 10 to New Marigold Road. | — | Executed | E. T. Simonds Construction Company $773,798 · | ||
| Apr 25, 2025 | 97858 | BondDistrict 8 | Construct PCC sidewalk with ADA improvements in the East Wood Subdivision in Greenville. Includes; Utility relocations, driveways, and curb and gutter. | — | Executed | Keller Construction, Inc. $449,364 · | ||
| Apr 25, 2025 | 97861 | ClintonDistrict 8 | Resurfacing on Aviston Road from Old US Highway 50 to IL 161. | — | Executed | Christ Bros. Asphalt, Inc. $2,147,938 · | ||
| Apr 25, 2025 | 97862 | MadisonDistrict 8 | Pavement reconstruction, sidewalk, curb and gutter on Pierce Lane from north of Stamper Lane to Stamper lane in Godfrey. | — | Executed | Keller Construction, Inc. $1,917,545 · | ||
| Apr 25, 2025 | 99727 | JacksonDistrict 9 | HMA resurfacing on South Wall Street from East park Street to East Main Street in Carbondale. Includes; ADA improvements and Storm Sewers. | — | Executed | Samron Midwest Contracting, Inc. $1,596,208 · | ||
| Jun 13, 2025 | 46658 | VariousDistrict 7 | Replacing guardrail reflectors and linear delineation panels on various routes throughout District 7. | — | Executed | Done Rite Construction Co., Inc. $227,213 · | ||
| Jun 13, 2025 | 46661 | VariousDistrict 2 | Removing existing guardrail delineators and barrier wall delineators and installing new guardrail delineators and barrier wall delineators within the limits of each individual work order. | — | Executed | O'Brien Civil Works, Inc. $167,625 · | ||
| Jun 13, 2025 | 46664 | VariousDistrict 4 | Repairing various widths of preformed plastic, epoxy, modified urethane pavement marking lines, letters and symbols and removal of existing pavement markings within the limits specified on each individual Work Order, and related collateral work necessary to complete the project on various routes throughout District 4. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $1,978,061 · | ||
| Jun 13, 2025 | 46937 | LaSalleDistrict 3 | Roadway improvements (HMA resurfacing, A3 oil and chip, drainage improvements and other work) within Illini State Park (IDNR) in LaSalle County, IL. 1.6 miles gross length. | — | Executed | D. Construction, Inc. $1,632,707 · | ||
| Jun 13, 2025 | 46941 | LaSalleDistrict 3 | PCC concrete patching of the parking lot at the lodge at Starved Rock State Park (IDNR) in LaSalle County, IL. | — | Executed | Advanced Asphalt Company $513,534 · | ||
| Jun 13, 2025 | 60R76 | WillDistrict 1 | Construction of a retaining wall, guardrail replacement, shoulder widening, headwall replacement and culvert e (1225-Ft) Bridge Deck Replacement consists of construction of a retaining wall, guardrail replacement, shoulder widening, headwall replacement and culvert extension located on I-57 at Pauling Road (Overhead) in Will County. | — | Executed | D. Construction, Inc. $4,142,053 · | ||
| Jun 13, 2025 | 61J86 | LakeDistrict 1 | Construction of new pavement to extend Hook Drive from Nicole Lane to Orchard Lane, and the construction of Nicole Lane from Hook Drive to Rollins Road in Round Lake Beach. Includes; Excavation, Aggregate base and sub-base, HMA Pavement, Sidewalk, curb and gutter, storm and sanitary sewer, water main, landscaping, lighting foundations and conduit. | — | Executed | Lake County Grading Company, LLC $4,391,124 · | ||
| Jun 13, 2025 | 61K96 | LakeDistrict 1 | HMA resurfacing and shoulder widening on Saunders Road from Duffy Lane to Riverwoods Road in Riverwoods. | — | Executed | |||
| Jun 13, 2025 | 61L34 | CookDistrict 1 | Add bike lanes on Church Street from Linder Avenue to McCormick Boulevard in Skokie. Includes PCC base course widening, curb and gutter, sidewalks, and traffic signal modifications. | — | Executed | Alliance Contractors, Inc. $2,111,750 · | ||
| Jun 13, 2025 | 61L40 | KaneDistrict 1 | Resurfacing and the construction of a multi-use path on Sleepy Hollow Road from Huntley Road to IL-72 in West Dendee. | — | Executed | Schroeder Asphalt Services, Inc. $1,348,856 · | ||
| Jun 13, 2025 | 61L49 | McHenryDistrict 1 | Construction of a triple-cell 12'X 5' box culvert to carry Oakwood Drive over Boone Creek in McHenry. Includes, HMA roadway, sidewalks, curb and gutter, storm sewer and utility adjustments. | — | Executed | Alliance Contractors, Inc. $1,194,482 · | ||
| Jun 13, 2025 | 61L50 | McHenryDistrict 1 | HMA resurfacing on Johnsburg Road from Fairview Avenue to the north city limits of Johnsburg. Includes aggregate shoulders. | — | Executed | Geske and Sons, Inc. $1,758,088 · | ||
| Jun 13, 2025 | 61L51 | McHenryDistrict 1 | Resurfacing Nish Road from Barreville Road to IL 176 in Prairie Grove. | — | Executed | Geske and Sons, Inc. $588,609 · | ||
| Jun 13, 2025 | 61L52 | LakeDistrict 1 | Construction of an HMA Bike Path in Round Lake. Includes sidewalk removal, storm sewer, pavement markings, and parkway restoration. | — | Executed | Alliance Contractors, Inc. $521,885 · | ||
| Jun 13, 2025 | 61L53 | CookDistrict 1 | Resurfacing Glenview Road from Milwaukee Avenue to Shermer Road in Glenview. | — | Executed | Peter Baker & Son Co. $2,007,772 · | ||
| Jun 13, 2025 | 61L59 | KaneDistrict 1 | HMA resurfacing on State Street from Hampshire Creek to Allen Road in Hampshire. Includes pavement patching, curb and gutter, and drainage structure adjustments. | — | Executed | Curran Contracting Company $308,598 · | ||
| Jun 13, 2025 | 61L60 | KaneDistrict 1 | HMA resurfacing on South Elgin Boulevard from East Main Street to the north village limits of South Elgin. Includes curb and gutter, drainage structures, and parkway restoration. | — | Executed | Plote Construction, Inc. $1,197,423 · | ||
| Jun 13, 2025 | 61L62 | CookDistrict 1 | Resurfacing Beckwith Road from Shermer Road to Austin Avenue in Morton Grove. | — | Executed | Peter Baker & Son Co. $1,660,324 · | ||
| Jun 13, 2025 | 61L63 | CookDistrict 1 | Resurfacing Gross Point Road from Main Street to Oakton Street in Morton Grove. | — | Executed | Peter Baker & Son Co. $929,683 · | ||
| Jun 13, 2025 | 61L64 | CookDistrict 1 | Resurfacing Central Avenue from Golf Road to Dempster Street in Morton Grove. | — | Executed | Peter Baker & Son Co. $1,669,904 · | ||
| Jun 13, 2025 | 61L65 | CookDistrict 1 | Resurfacing Shermer Road from Gold Road to Harlem Avenue in Morton Grove. | — | Executed | A Lamp Concrete Contractors, Inc. $939,244 · | ||
| Jun 13, 2025 | 62G52 | WillDistrict 1 | (1.716-Mile) Designed Overlay improvements include: Curb and gutter spot repair , asphalt surface removal and replacement with new binder and surface (cold milling and inlay), full-depth patches (Class D), drainage structures adjustment and cleaning, pavement markings, raised reflective pavement markers, detector loops replacement. Location: IL 53 (Independence Boulevard), from Joliet Road to Belmont Drive within the Village of Romeoville. | — | Executed | K-Five Construction Corporation $3,382,064 · | ||
| Jun 13, 2025 | 62L61 | McHenryDistrict 1 | (10,700-Ft) Designed Overlay and Shoulder Reconstruction, project includes asphalt removal, earth excavation, pavement patching, resurfacing with (HMA), full depth (HMA) shoulder, pavement markings, raised reflective pavement markers. Located along IL 47 (Eastwood Drive) from North of IL 176 (North Junction) to South of US 14 in the City of Woodstock. | — | Executed | Curran Contracting Company $2,693,463 · | ||
| Jun 13, 2025 | 62N39 | CookDuPageDistrict 1 | (9.38-Mile) Changeable Message Signs, Signal Timing/Progression, Signing (New), Surveillance, Traffic Signal Modernization, and ADA Improvements. Located along 22nd St / Cermak Rd from York Rd to IL 50 (Cicero Ave.) in the Village of Oak Brook in DuPage County, and in the Villages of Hillside, Westchester, Broadview North Riverside, Forest Park, the City of Berwyn, and the Town of Cicero,in Cook County. | — | Executed | Meade Inc. $20,875,047 · | ||
| Jun 13, 2025 | 62P73 | LakeDistrict 1 | US RTE 12 (10 The projects consist of US RTE 12 (10.39 miles) - SMART Overlay, shoulders, shoulder rumble strips, channelization, and pavement markings and IL RTE 176 (0.71 miles) - shoulder and centerline rumble strips and pavement markings. Project located in Villages of Fox Lake, Volo, Lakemoor, Wauconda and Mundelein | — | Executed | Curran Contracting Company $16,944,587 · | ||
| Jun 13, 2025 | 62T22 | CookDistrict 1 | Bridge and approach slab scarification, replacement of joints at abutments and piers with strip seals, cleanin (405-Ft) Bridge Deck Overlay on SN 016-1005 and SN 016-1006 and associated bridge rehabilitation consists of bridge and approach slab scarification, replacement of joints at abutments and piers with strip seals, cleaning/ adjusting shoulder drains, concrete sealer of deck and parapets, HMA overlay on bridge approaches, slope wall repair and replacement, maintenance of traffic control, pavement marking. Located along IL-171 at Joliet Road and BNSF Railroad Spur in the Village of McCook, Cook Coun | — | Executed | Martam Construction Incorporated $1,747,368 · | ||
| Jun 13, 2025 | 62T95 | CookDistrict 1 | (1,082.40-Ft) The improvement includes earth excavation, non-special waste disposal, erosion control and protection, temporary drainage, traffic control and protection. The project is located along the east side of the NB Mannheim Ramp between Mannheim Road and the CN Railroad tracks and I-190 and Willow Creek. | — | Executed | Lindahl Brothers, Inc. $8,580,778 · | ||
| Jun 13, 2025 | 62U39 | WillDistrict 1 | Removal and replacement of the Bridge (SN 099-0205) carrying Francis Road over I-80 and the subsequent pavemen Project consists of removal and replacement of the Bridge (SN 099-0205) carrying Francis Road over I-80 and the subsequent pavement improvements necessary for this replacement. Located on FAI 80 (I-80) at Francis Road, Will County, IL. | — | Executed | D. Construction, Inc. $5,328,033 · | ||
| Jun 13, 2025 | 62V14 | CookDistrict 1 | Resurfacing the existing HMA pavement with HMA surface and binder course, thermoplastic pavement markings, ADA (1.472-Mile) This project consists of resurfacing the existing HMA pavement with HMA surface and binder course, thermoplastic pavement markings, ADA Improvements for curb ramps. Located along Sacramento Blvd in the City of Chicago in Cook County. | — | Executed | MAT Construction Leasing, Inc. $2,054,601 · | ||
| Jun 13, 2025 | 62V39 | LakeDistrict 1 | Resurfacing of the existing HMA pavement with HMA surface course, adding 4-foot wide HMA shoulders, thermoplas (1.91-Mile) Project consists of resurfacing of the existing HMA pavement with HMA surface course, adding 4-foot wide HMA shoulders, thermoplastic pavement markings. This project is located along US 45 in the Village of Antioch and the Township of Antioch in Lake County. | — | Executed | Payne & Dolan, Inc. $1,630,685 · | ||
| Jun 13, 2025 | 62V52 | McHenryDistrict 1 | (9,601-Ft) SMART Overlay and Standard Overlay, ADA sidewalk ramp improvement, pavement patching, milling of existing HMA surface, placing HMA surface course and HMA binder course, drainage structures adjustment and cleaning, pavement markings, sidewalk ramp improvements. Project located on IL 176 (State Road) in the Village of Island Lake. | — | Executed | Curran Contracting Company $2,389,468 · | ||
| Jun 13, 2025 | 62V57 | McHenryDistrict 1 | (2.62-Mile) Designed overlay and new (HMA) shoulder reconstruction project includes asphalt removal, earth excavation, pavement patching, resurfacing with (HMA), full-depth (HMA) shoulder, pavement markings, raised reflective pavement markers, shoulder and centerline rumble strips. Located along IL Route 176 from East of Haligus Road to West of US 14 (Virginia Street) in the City of Crystal Lake. | — | Executed | Curran Contracting Company $2,685,966 · | ||
| Jun 13, 2025 | 62V58 | LakeDistrict 1 | (2.02-Mile) SMART Overlay, Shoulder Repair and ADA Improvements consists (HMA) removal, earth excavation, pavement patching, resurfacing with (HMA) asphalt, full depth hot-mix asphalt shoulder, placement of pavement markings, installation of raised reflective pavement markers, ADA ramps, traffic signals, detector loops. Project located on IL 131 (Green Bay Road) from IL 173 (Rosecrans Road) to Russell Road in the City of Zion. | — | Executed | Peter Baker & Son Co. $3,524,201 · | ||
| Jun 13, 2025 | 62V88 | DuPageDistrict 1 | Curb and gutter spot repairs, sidewalk removal and replacement for curb ramps for sidewalks (ADA), cold asphal (3,848-Ft) Designed Overlay, ADA Improvements, New Shoulders consists of curb and gutter spot repairs, sidewalk removal and replacement for curb ramps for sidewalks (ADA), cold asphalt pavement milling, patches (Class D), replace existing aggregate shoulders with HMA, drainage structures adjustments and cleaning, longitudinal joint sealing, resurfacing (inlay) with HMA binder and surface course, new thermoplastic pavement markings and raised reflective pavement markers, accessible pedestrian sig | — | Executed | R. W. Dunteman Company $1,208,153 · | ||
| Jun 13, 2025 | 62W15 | WillDistrict 1 | (1.59-Mile) Replace light towers with poles, LED luminaries, foundations, conduits/cables, restorations. Project located in the Villages of Mokena, Orland Park, and Tinley Park in Will County, at I-80 and US-45 interchange. | — | Executed | John Burns Construction Company $1,709,237 · | ||
| Jun 13, 2025 | 62W90 | VariousDistrict 1 | Replacement of old controllers, replace fiber optic cable, network switches, PTZ cameras, and controllers among other equipment to allow for remote access and monitoring capabilities, complete the ATMS system in Lake County allowing for fully remote access to all intersection. There are one hundred fifteen locations proposed on this project located in mainly in Lake County with fewer location in Cook and McHenry Counties. | — | Executed | H & H Electric Co. $3,357,143 · | ||
| Jun 13, 2025 | 62X02 | CookDistrict 1 | (420.25-Ft) HMA Pavement Patching and resurfacing, storm sewer installation, drainage structure installation, bridge deck overlay, superstructure repairs, substructure repairs. This project is in the City of Chicago and Village of Riverdale, Cook County, on IL 1 (Halsted Street, FAU 3730) over Little Calumet River. | — | Executed | D. Construction, Inc. $4,238,796 · | ||
| Jun 13, 2025 | 62X29 | CookDistrict 1 | Joint sealing, concrete removal, concrete superstructure, wing wall modifications, approach slab repair, struc (900-Ft) Bridge joint repair and replacement, and bridge approach pavement improvement consists of joint sealing, concrete removal, concrete superstructure, wing wall modifications, approach slab repair, structural repair of concrete, HMA surface removal, butt joints, PCC surface removal, HMA surface course, full depth HMA Class D patches, guardrail removal, guardrail, pavement markings, Class SI concrete, tree removal, This project is located in the Village of Thornton, in Cook County. | — | Executed | MYS, Incorporated $882,083 · | ||
| Jun 13, 2025 | 62X33 | KaneDistrict 1 | Hot-mix asphalt surface removal, pavement patching, resurfacing with asphalt binder course and asphalt surface (6.70-Mile) Design overlay consists of hot-mix asphalt surface removal, pavement patching, resurfacing with asphalt binder course and asphalt surface course, placement of thermoplastic pavement markings. Located on Illinois Rte. FAP 567, IL 38, from Dekalb County Line to IL 47 (Main Street) within the Village of Elburn in Kane County. | — | Rejected | Builders Paving, LLC $4,414,888 · | ||
| Jun 13, 2025 | 62X34 | WillDistrict 1 | Asphalt surface removal, pavement patching, combination concrete curb and gutter removal and replacement, conc (2.88-Mile) Designed overlay and pedestrian ramp (ADA) project consists of asphalt surface removal, pavement patching, combination concrete curb and gutter removal and replacement, concrete sidewalk removal replacement, resurfacing with asphalt binder course and asphalt surface course, pavement markings. The improvement is in the Cities of Braidwood and Wilmington in Will County. | — | Executed | Iroquois Paving Corporation $1,353,712 · | ||
| Jun 13, 2025 | 62X35 | McHenryDistrict 1 | Pavement patching, hot-mix asphalt surface removal, resurfacing with polymerized hot-mix asphalt surface cours (2.68-Mile) This project consists of pavement patching, hot-mix asphalt surface removal, resurfacing with polymerized hot-mix asphalt surface course, binder course, ADA improvement and curb and gutter replacement, thermoplastic pavement marking. This improvement is in Dorr Township and in the City of Woodstock in McHenry County. | — | Executed | Plote Construction, Inc. $2,341,185 · | ||
| Jun 13, 2025 | 62X42 | CookDistrict 1 | This work includes trombone mast arm and pole replacement, installation of LED signal heads, traffic signal posts, installation of accessible pedestrian signals located in various locations in District 1. | — | Executed | Hecker and Company, Inc. $1,733,690 · | ||
| Jun 13, 2025 | 62X59 | KaneDistrict 1 | (1.12-Mile) Designed Overlay, Traffic Signal Modernization, ADA Improvement consists asphalt surface removal, pavement patching, (HMA) binder and surface course, concrete curb and gutter removal and replacement, pedestrian curb ramps (ADA) improvements, traffic signal modernization, accessible pedestrian signal improvements, detector loop replacement, raised reflective pavement markers, pavement marking. Located within the City of Elgin in Kane County. | — | Executed | Plote Construction, Inc. $2,838,180 · | ||
| Jun 13, 2025 | 62X60 | DuPageDistrict 1 | Designed overlay, ADA improvements, and collateral work necessary to complete the project (2,909-Ft) Improvement consists of Designed overlay, ADA improvements, and collateral work necessary to complete the project. Located on Gary-s Mill Road from IL. 38 to IL. 59 in the City of West Chicago. | — | Executed | R. W. Dunteman Company $842,712 · | ||
| Jun 13, 2025 | 62X61 | KaneDistrict 1 | Hot-mix asphalt pavement removal and replacement, combination curb and gutter removal and replacement, thermop (2,955-Ft) Design Overlay and ADA improvements consist of hot-mix asphalt pavement removal and replacement, combination curb and gutter removal and replacement, thermoplastic pavement marking, sidewalk removal and replacement. Project is located in the Cities of Highwood and Highland Park, Lake County. | — | Executed | Peter Baker & Son Co. $922,469 · | ||
| Jun 13, 2025 | 62X62 | CookDistrict 1 | (1466-Ft) Pavement patching, hot-mix asphalt surface removal, resurfacing with hot-mix asphalt surface course, binder course, ADA improvement and curb and gutter replacement, thermoplastic pavement marking. This improvement is in Evanston Township and in the City of Evanston. | — | Executed | Peter Baker & Son Co. $1,005,325 · | ||
| Jun 13, 2025 | 62X64 | CookDistrict 1 | (4,602-Ft) Smart Overlay improvements include curb and gutter spot repairs (remove and replace), hot-mix asphalt (HMA) surface removal and replacement with (cold milling and inlay), full-depth patches (Class D), thermoplastic pavement markings, raised reflective pavement markers, detector loops. Located on I-55 North Frontage Road from County Line Road to Commonwealth Drive within the Village of Burr Ridge. | — | Executed | K-Five Construction Corporation $511,057 · | ||
| Jun 13, 2025 | 62X66 | McHenryDistrict 1 | Pavement patching, milling of existing asphalt surface, polymerized HMA binder course and HMA surface course, (2.93-Mile) Standard Overlay consists of pavement patching, milling of existing asphalt surface, polymerized HMA binder course and HMA surface course, thermoplastic and hot spray pavement markings, grading and shaping ditches. This project located in Coral Township, in McHenry County. | — | Executed | Plote Construction, Inc. $1,405,173 · | ||
| Jun 13, 2025 | 62X67 | KaneDistrict 1 | Asphalt surface removal, placement of (HMA) surface course, pavement patching, pavement markings SMART Overlay and Standard Overlay improvement project consists of asphalt surface removal, placement of (HMA) surface course, pavement patching, pavement markings. The project is located in the villages of Hampshire and Pingree Grove within Kane County. | — | Executed | Curran Contracting Company $2,654,662 · | ||
| Jun 13, 2025 | 62X68 | McHenryDistrict 1 | (HMA) surface removal, pavement patching, concrete sidewalk removal and replacement, polymerized (HMA) surface (1.06-Mile) Standard Overlay and Pedestrian Ramp (ADA) project consists of (HMA) surface removal, pavement patching, concrete sidewalk removal and replacement, polymerized (HMA) surface course and binder course, thermoplastic and hot spray pavement marking, combination concrete curb and gutter removal and replacement. Project is in the City of Marengo in Marengo, Seneca, and Coral Townships in McHenry County. | — | Executed | Schroeder Asphalt Services, Inc. $881,875 · | ||
| Jun 13, 2025 | 62X69 | KaneDistrict 1 | (1.79-Mile) SMART and Designed Overlay, ADA Improvements, New Shoulders Improvements include curb and gutter spot repairs (remove and replace), sidewalk removal and replacement for curb ramps for sidewalks (ADA), (HMA) surface removal and replacement, (cold milling and inlay), full-depth patches (Class D), drainage structures adjustment and cleaning, pavement marking, pedestrian signals (APS) improvements and detector loops. Location: IL 56 (Butterfield Road), from East of IL 25 River Road to We | — | Executed | Geneva Construction Company LLC. $2,713,457 · | ||
| Jun 13, 2025 | 62X70 | CookDistrict 1 | 0.48-mile) Standard Overlay, ADA Improvements includes curb and gutter spot repairs (remove and replace), sidewalk removal and replacement for curb ramps (ADA), hot-mix asphalt surface removal and replacements (cold milling and inlay), full-depth patches (Class D), drainage structures adjustment and cleaning, new thermoplastic pavement markings and raised reflective pavement markers, accessible pedestrian signals (APS) improvements and detector loops. Location: Niles Center Road, from south of M | — | Executed | A Lamp Concrete Contractors, Inc. $755,632 · | ||
| Jun 13, 2025 | 62X71 | CookDistrict 1 | Asphalt surface removal, mix asphalt resurfacing, sidewalk removal, placement of thermoplastic pavement markin (1.08-Mile) Standard Overlay project consists of asphalt surface removal, mix asphalt resurfacing, sidewalk removal, placement of thermoplastic pavement markings, combination curb and gutter removal and replacement, installation of concrete sidewalk and detectable warnings, drainage structure adjustments and pedestrian ramp improvements. Located on Pershing Road from 56th Court to ILL 50 (Cicero Avenue) within the Village of Stickney and the Town of Cicero in Cook County. | — | Executed | K-Five Construction Corporation $1,538,560 · | ||
| Jun 13, 2025 | 62X74 | CookDistrict 1 | Repairing bridge drainage system as shown on the plans and any incidental collateral work necessary to complet This improvement consists of repairing bridge drainage system as shown on the plans and any incidental collateral work necessary to complete the improvements Located in the Cities of Chicago and Blue Island and Village of Hillside in Cook County. | — | Executed | D. Construction, Inc. $913,615 · | ||
| Jun 13, 2025 | 62X99 | WillDistrict 1 | Building demolition for ten (10) residential and/or commercial parcels and outbuildings, include removing any The work consists of building demolition for ten (10) residential and/or commercial parcels and outbuildings, include removing any structure above and below the ground, main building frames, attached and detached buildings, facilities, and filling of basements, removal of fences, sidewalks and driveways, utilities, and trees, grading and seeding. Located in the City of Joliet, in the vicinity of FAI Route 80 (Interstate 80) and Des Plaines River in Will County. | — | Executed | C & D Recycling Services, Inc. $469,833 · | ||
| Jun 13, 2025 | 62Y02 | CookKaneDistrict 1 | Cleaning and painting steel surfaces as designated on the plans and any incidental and collateral work (0.01-Mile) This is a bridge painting project consists of cleaning and painting steel surfaces as designated on the plans and any incidental and collateral work. This project has two locations: (SN 045-0037 and SN 047-0029) 1) Galena Blvd over IL-56 in the Village of Sugar Grove. 2) US 30 over Blackberry Creek in the Village of Montgomery. | — | Executed | Capital Industrial Services, LLC $499,333 · | ||
| Jun 13, 2025 | 62Y04 | CookDistrict 1 | Bridge substructure repairs to the SN 016-0511 (EB) and SN 016-0512 (WB) Structures of I-190 over Des Plaines (349- FT) Scope of work consist of bridge substructure repairs to the SN 016-0511 (EB) and SN 016-0512 (WB) Structures of I-190 over Des Plaines River Road. Improvement is located in the Village of Rosemont in Cook County. | — | Executed | Areatha Construction Co., Inc. $694,687 · | ||
| Jun 13, 2025 | 62Y07 | CookDistrict 1 | Cleaning and painting steel surfaces as designated on the plans and any incidental and collateral work (0.01-Mile) Bridge Painting project consists of cleaning and painting steel surfaces as designated on the plans and any incidental and collateral work. This project has two locations: (SN 016-2665 and SN 016-0537) 1) US 12/ 20/ 45 (LaGrange Rd) over I-55, in the City of Countryside and Village of Hodgkins;2) Willow Springs Rd over I-55 in the City of Countryside. | — | Executed | ERA-Valdivia Contractors, Inc. $642,843 · | ||
| Jun 13, 2025 | 62Y08 | VariousDistrict 1 | Repair and replacement work order contract for Impact Attenuators, Sand Barrels and Miscellaneous Traffic Control in coordination with MCHD to enhance roadway safety and manage traffic flow effectively. Location on various State maintained expressway and arterial routes within the counties of Cook, DuPage, Will, Lake, McHenry and Kane. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $2,141,300 · | ||
| Jun 13, 2025 | 62Y10 | VariousDistrict 1 | Pruning and/or removing dead, dying, diseased and hazardous trees and limbs, while providing proper traffic co This project consists of pruning and/or removing dead, dying, diseased and hazardous trees and limbs, while providing proper traffic control on a work basis. Located in District One (counties of Cook, DuPage, Kane, Lake, McHenry, and Will). | — | Executed | Homer Tree Service, Inc. $536,830 · | ||
| Jun 13, 2025 | 64B40 | Jo DaviessDistrict 2 | 4.07 miles of reconstruction of US 20 from 0.2 mile west of Logemann Rd to Rush St in Stockton. | — | Executed | Civil Constructors, Inc. d/b/a Helm Civil and Fischer Excavating, Inc. J.V. $31,655,626 · | ||
| Jun 13, 2025 | 64J66 | WinnebagoDistrict 2 | 1.21 miles ADA sidewalk ramps, HMA patching, RTL widening, video detection systems, and sign replacement from Fairview Ave to Rockford College Dr. | — | Executed | Stenstrom Excavation & Blacktop, Inc. $1,848,165 · | ||
| Jun 13, 2025 | 64M38 | WinnebagoDistrict 2 | 2.184 mi Designed Overlay, patching, milling, retaining wall repair, and ADA Improvements from Snow Ave in Loves Park to Whitman St in Rockford and Forest Hills Rd from Landstrom Rd to IL 251. | — | Executed | Rock Road Companies, Inc. $7,698,386 · | ||
| Jun 13, 2025 | 64M76 | LeeDistrict 2 | Remove and replace culvert over a drainage way 0.3 mile south of US 30, north of Amboy on US 52. | — | Executed | Martin & Company Excavating $493,527 · | ||
| Jun 13, 2025 | 64P13 | OgleDistrict 2 | Hot-Mix Asphalt resurfacing south of IL-72 (W) to south of Willow St and ADA improvements on IL-72. 4.51 gross miles. | — | Executed | Martin & Company Excavating $4,385,762 · | ||
| Jun 13, 2025 | 64R15 | BooneWinnebagoDistrict 2 | 1.05 miles of HMA resurfacing (SMART overlay) from 0.3 miles east of Kishwaukee River to 0.4 miles west of Wheeler Rd on US 20. | — | Executed | Rock Road Companies, Inc. $2,406,956 · | ||
| Jun 13, 2025 | 64R16 | Rock IslandDistrict 2 | 5.39 miles of milling and resurfacing on I-74: I-280/US 6 Interchange to Henry County Line and I-280: Milan Beltway to the I-74/US 6 Interchange. | — | Executed | Advanced Asphalt Company $11,584,709 · | ||
| Jun 13, 2025 | 64S25 | WinnebagoDistrict 2 | Deck repair, joint replacement, deck overlay, and other miscellaneous repairs carrying SN 101-0145 over Baxter Road, 1 mile north of Ogle County Line. | — | Executed | Martin & Company Excavating $1,028,867 · | ||
| Jun 13, 2025 | 64S28 | WhitesideDistrict 2 | Bridge deck overlay, joint replacement and miscellaneous repairs on SN 098-0055 carrying Cordova Rd over I-88, 2.5 miles west of Erie. | — | Executed | Brandt Construction Co. $705,219 · | ||
| Jun 13, 2025 | 64S51 | WinnebagoDistrict 2 | 2.98 miles of pavement patching, cold milling, HMA resurfacing, ADA improvement, and traffic signal modifications on IL 251 from Windsor Rd in Loves Park to 0.3 miles south of Il 173 in Machesney Park. | — | Executed | Rock Road Companies, Inc. $8,243,328 · | ||
| Jun 13, 2025 | 64T30 | OgleWinnebagoDistrict 2 | Crack joint sealing on US 20 from 0.2 mi W of Falconer Rd to Simpson Rd and US BUS 20 from US 20 to Weldon Rd SW of Rockford. US 64 from 0.1 mi E of US 52 to ILL 26. IL 70 from Pecatonica River to 0.1 mi W of Safford Rd in Rockford. 4.91 miles gross length. | — | Executed |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.