18-00086-00-BR
- Let date
- Friday, June 13, 2025
- Contract
- 61L49 · job page
- District
- District 1
- County
- Mchenry
- Highway
- Limits
- Construction of a triple-cell 12'X 5' box culvert to carry Oakwood Drive over Boone Creek in McHenry. Includes, HMA roadway, sidewalks, curb and gutter, storm sewer and utility adjustments.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Alliance Contractors, Inc. Low bidder | $1,194,482 | ||
| 2 | Martam Construction Incorporated | $1,455,259 | +21.8% | |
| 3 | Lorig Construction Company | $1,831,742 | +53.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Alliance Contra… | #2 Martam Construc… | #3 Lorig Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326806 | WASHOUT BASIN | 1 | L SUM | $500.00 | $3,500.00 | $100.00 | |
| 2 | X2511630 | EROS CONT BLANKET SPL | 1,272 | SQ YD | $2.50 | $3.00 | $1.50 | |
| 3 | X5030290 | STAIN CONC STRUCTURES | 1,104 | SQ FT | $13.33 | $15.00 | $13.50 | |
| 4 | X5610004 | D I WTR MN FITTINGS | 3,000 | POUND | $0.0100 | $9.00 | $0.0100 | |
| 5 | X5610700 | WATER MAIN REMOVAL | 125 | FOOT | $50.00 | $40.00 | $50.00 | |
| 6 | X5610778 | PRESS CONNECT 12X12 | 1 | EACH | $17,000.00 | $12,200.00 | $17,000.00 | |
| 7 | X5630012 | CUT & CAP EX 12 WM | 2 | EACH | $3,500.00 | $2,600.00 | $3,500.00 | |
| 8 | X5630712 | CONN TO EX W MAIN 12 | 1 | EACH | $8,000.00 | $6,500.00 | $8,000.00 | |
| 9 | X5810103 | MEMB WTRPRF SYS B STR | 223 | SQ YD | $57.87 | $45.00 | $50.00 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $14,000.00 | $106,000.00 | $200,000.00 | |
| 11 | X7200061 | TEMP INFO SIGNING | 52 | SQ FT | $16.00 | $18.00 | $17.00 | |
| 12 | Z0013796 | SED CON STAB CONST EN | 77 | SQ YD | $1.00 | $68.00 | $48.00 | |
| 13 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,725.00 | $8,000.00 | $85,000.00 | |
| 14 | Z0054400 | ROCK FILL | 131 | CU YD | $60.00 | $72.00 | $230.00 | |
| 15 | Z0073510 | TEMP TR SIGNAL TIMING | 3 | EACH | $700.00 | $500.00 | $400.00 | |
| 16 | 20200100 | EARTH EXCAVATION | 1 | CU YD | $100.00 | $560.00 | $300.00 | |
| 17 | 20201200 | REM & DISP UNS MATL | 184 | CU YD | $100.00 | $95.00 | $118.00 | |
| 18 | 20300100 | CHANNEL EXCAVATION | 20 | CU YD | $100.00 | $360.00 | $120.00 | |
| 19 | 20400800 | FURNISHED EXCAVATION | 87 | CU YD | $1.00 | $55.00 | $100.00 | |
| 20 | 20700220 | POROUS GRAN EMBANK | 140 | CU YD | $60.00 | $92.00 | $180.00 | |
| 21 | 20800150 | TRENCH BACKFILL | 53 | CU YD | $60.00 | $115.00 | $0.2500 | |
| 22 | 21001000 | GEOTECH FAB F/GR STAB | 645 | SQ YD | $1.00 | $3.00 | $2.75 | |
| 23 | 21101625 | TOPSOIL F & P 6 | 45 | SQ YD | $65.00 | $30.00 | $14.00 | |
| 24 | 21301048 | EXPLOR TRENCH 48 | 75 | FOOT | $1.00 | $40.00 | $100.00 | |
| 25 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $4,280.00 | $5,000.00 | $8,000.00 | |
| 26 | 25000314 | SEEDING CL 4B | 0.25 | ACRE | $5,380.00 | $5,800.00 | $8,500.00 | |
| 27 | 25000400 | NITROGEN FERT NUTR | 26 | POUND | $3.00 | $4.00 | $4.00 | |
| 28 | 25000600 | POTASSIUM FERT NUTR | 26 | POUND | $3.00 | $4.00 | $4.00 | |
| 29 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $6.00 | $7.00 | $15.00 | |
| 30 | 28000400 | PERIMETER EROS BAR | 590 | FOOT | $3.50 | $4.00 | $5.00 | |
| 31 | 28000510 | INLET FILTERS | 2 | EACH | $250.00 | $300.00 | $375.00 | |
| 32 | 28001100 | TEMP EROS CONTR BLANK | 1,272 | SQ YD | $1.30 | $1.30 | $1.10 | |
| 33 | 28100107 | STONE RIPRAP CL A4 | 240 | SQ YD | $200.00 | $95.00 | $195.00 | |
| 34 | 28200200 | FILTER FABRIC | 240 | SQ YD | $1.00 | $4.00 | $4.25 | |
| 35 | 30300001 | AGG SUBGRADE IMPROVE | 184 | CU YD | $67.00 | $65.00 | $110.00 | |
| 36 | 30300112 | AGG SUBGRADE IMPR 12 | 645 | SQ YD | $26.00 | $23.00 | $36.00 | |
| 37 | 35101600 | AGG BASE CSE B 4 | 278 | SQ YD | $9.00 | $12.00 | $21.00 | |
| 38 | 40600275 | BIT MATLS PR CT | 1,452 | POUND | $0.0100 | $0.1000 | $0.0100 | |
| 39 | 40600290 | BIT MATLS TACK CT | 146 | POUND | $0.0100 | $0.1000 | $0.0100 | |
| 40 | 40603080 | HMA BC IL-19.0 N50 | 142 | TON | $100.00 | $150.00 | $110.00 | |
| 41 | 40604060 | HMA SC IL-9.5 D N50 | 71 | TON | $115.00 | $230.00 | $125.00 | |
| 42 | 42400200 | PC CONC SIDEWALK 5 | 2,502 | SQ FT | $8.00 | $14.00 | $12.00 | |
| 43 | 44000100 | PAVEMENT REM | 645 | SQ YD | $30.00 | $23.00 | $17.00 | |
| 44 | 44000500 | COMB CURB GUTTER REM | 376 | FOOT | $20.00 | $9.00 | $9.00 | |
| 45 | 44000600 | SIDEWALK REM | 2,132 | SQ FT | $2.00 | $2.00 | $3.00 | |
| 46 | 50100100 | REM EXIST STRUCT | 1 | EACH | $90,000.00 | $162,000.00 | $325,000.00 | |
| 47 | 50200300 | COFFERDAM EXCAVATION | 343 | CU YD | $100.00 | $89.00 | $110.00 | |
| 48 | 50200450 | REM/DISP UNS MATL-STR | 131 | CU YD | $100.00 | $95.00 | $135.00 | |
| 49 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $1,500.00 | $126,000.00 | $10,000.00 | |
| 50 | 50300285 | FORM LINER TEX SURF | 1,104 | SQ FT | $6.00 | $24.00 | $14.00 | |
| 51 | 50300300 | PROTECTIVE COAT | 123 | SQ YD | $0.0100 | $3.00 | $4.50 | |
| 52 | 50800205 | REINF BARS, EPOXY CTD | 42,490 | POUND | $2.05 | $1.80 | $1.80 | |
| 53 | 50900805 | PEDESTRIAN RAIL | 55 | FOOT | $172.10 | $232.00 | $175.00 | |
| 54 | 50901750 | PARAPET RAILING | 78 | FOOT | $154.25 | $204.00 | $157.00 | |
| 55 | 51500100 | NAME PLATES | 1 | EACH | $1,500.00 | $1,200.00 | $800.00 | |
| 56 | 54003000 | CONC BOX CUL | 252 | CU YD | $1,693.00 | $1,250.00 | $1,650.00 | |
| 57 | 54213657 | PRC FLAR END SEC 12 | 1 | EACH | $750.00 | $1,500.00 | $2,500.00 | |
| 58 | 550A0050 | STORM SEW CL A 1 12 | 12 | FOOT | $133.00 | $165.00 | $165.00 | |
| 59 | 550A0340 | STORM SEW CL A 2 12 | 48 | FOOT | $133.00 | $188.00 | $165.00 | |
| 60 | 56104100 | D I WATER MAIN MJ 12 | 153 | FOOT | $410.00 | $365.00 | $410.00 | |
| 61 | 56105200 | WATER VALVES 12 | 2 | EACH | $4,000.00 | $4,800.00 | $4,000.00 | |
| 62 | 56400820 | FIRE HYD W/AUX V & VB | 1 | EACH | $12,000.00 | $12,600.00 | $12,000.00 | |
| 63 | 59100100 | GEOCOMPOSITE WALL DR | 223 | SQ YD | $49.30 | $32.00 | $41.00 | |
| 64 | 60221100 | MAN TA 5 DIA T1F CL | 1 | EACH | $6,000.00 | $7,600.00 | $5,200.00 | |
| 65 | 60240310 | INLETS TB T11F&G | 2 | EACH | $4,000.00 | $2,800.00 | $2,900.00 | |
| 66 | 60248900 | VV TA 5 DIA T1F CL | 2 | EACH | $4,500.00 | $5,400.00 | $4,500.00 | |
| 67 | 60603800 | COMB CC&G TB6.12 | 376 | FOOT | $41.00 | $52.00 | $75.00 | |
| 68 | 66900200 | NON SPL WASTE DISPOSL | 46 | CU YD | $125.00 | $117.00 | $120.00 | |
| 69 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,600.00 | $1,800.00 | $1,800.00 | |
| 70 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,900.00 | $3,500.00 | $3,000.00 | |
| 71 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $1,300.00 | $2,000.00 | |
| 72 | 66901006 | REG SUB MON | 5 | CAL DA | $1,750.00 | $1,000.00 | $1,400.00 | |
| 73 | 67100100 | MOBILIZATION | 1 | L SUM | $54,891.00 | $84,000.00 | $100,000.00 | |
| 74 | 72400500 | RELOC SIN PAN ASSY TA | 1 | EACH | $250.00 | $300.00 | $250.00 | |
| 75 | 72800100 | TELES STL SIN SUPPORT | 13 | FOOT | $20.00 | $22.00 | $20.00 |