$37.26Avg low bid / CU YD
$44.26Avg of all bids
—Avg engineer's estimate
201Jobs · 437,727 CU YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 83 | 261,913 | $32.46 | $43.02 |
| 2025 | 117 | 175,759 | $44.41 | $46.07 |
| 2024 | 1 | 55 | $30.00 | $48.33 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 18, 2026 | 61L85 | MchenryDistrict 1 | 1,083 CU YD | $66.00 | ICC Group Inc. |
| Jul 31, 2026 | 80B44 | CookDistrict 1 | 62 CU YD | $60.00 | D. Construction, Inc. |
| Jul 31, 2026 | 61K19 | CookDistrict 1 | 327 CU YD | $79.57 | R. W. Dunteman Company |
| Jul 31, 2026 | 61K85 | CookDistrict 1 | 647 CU YD | $50.00 | Plote Construction, Inc. |
| Jul 31, 2026 | 61M13 | KaneDistrict 1 | 19,814 CU YD | $0.0100 | Dunnet Bay Construction Company |
| Jul 31, 2026 | 62J64 | CookDistrict 1 | 24 CU YD | $90.00 | Peter Baker & Son Co. |
| Jul 31, 2026 | 62W20 | CookDistrict 1 | 78 CU YD | $60.00 | D. Construction, Inc. |
| Jun 12, 2026 | 80B22 | CookDistrict 1 | 95 CU YD | $100.00 | K-Five Construction Corporation |
| Jun 12, 2026 | 62R61 | CookDistrict 1 | 401 CU YD | $83.78 | OHLA Central, Inc. |
| Jun 12, 2026 | 80B23 | KaneDistrict 1 | 649 CU YD | $60.00 | Plote Construction, Inc. |
| Jun 12, 2026 | 62U72 | MchenryDistrict 1 | 28,970 CU YD | $48.00 | Martam Construction Incorporated |
| Jun 12, 2026 | 61M44 | KaneDistrict 1 | 88 CU YD | $25.00 | Geske and Sons, Inc. |
| Jun 12, 2026 | 80B28 | CookDistrict 1 | 294 CU YD | $72.00 | K-Five Construction Corporation |
| Jun 12, 2026 | 62V08 | Cook, Dupage, KaneDistrict 1 | 20 CU YD | $80.00 | D. Construction, Inc. |
| Jun 12, 2026 | 61M51 | CookDistrict 1 | 1,793 CU YD | $79.37 | Martam Construction Incorporated |
| Jun 12, 2026 | 80B33 | CookDistrict 1 | 83 CU YD | $60.00 | D. Construction, Inc. |
| Jun 12, 2026 | 62X52 | DupageDistrict 1 | 2 CU YD | $250.00 | D. Construction, Inc. |
| Jun 12, 2026 | 62L30 | CookDistrict 1 | 1,310 CU YD | $55.00 | D. Construction, Inc. |
| Jun 12, 2026 | 80D00 | CookDistrict 1 | 35 CU YD | $80.00 | Plote Construction, Inc. |
| Jun 12, 2026 | 68J59 | TazewellDistrict 4 | 512 CU YD | $146.00 | R. A. Cullinan and Son, a div of UCM, Inc. |
| Jun 12, 2026 | 62M71 | Kane, KendallDistrict 1 | 63,496 CU YD | $42.00 | D. Construction, Inc. |
| Jun 12, 2026 | 80D46 | LakeDistrict 1 | 28 CU YD | $103.60 | Curran Contracting Company |
| Apr 24, 2026 | 80C85 | MchenryDistrict 1 | 49,155 CU YD | $0.0100 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Apr 24, 2026 | 61M41 | LakeDistrict 1 | 132 CU YD | $65.00 | Alliance Contractors, Inc. |
| Apr 24, 2026 | 80B21 | CookDistrict 1 | 2,098 CU YD | $0.0100 | K-Five Construction Corporation |
| Apr 24, 2026 | 70F20 | McleanDistrict 5 | 100 CU YD | $120.00 | Stark Excavating, Inc. |
| Apr 24, 2026 | 61L84 | DupageDistrict 1 | 20 CU YD | $45.00 | K-Five Construction Corporation |
| Apr 24, 2026 | 87899 | KendallDistrict 3 | 38,297 CU YD | $34.00 | Austin Tyler Construction, Inc. |
| Apr 24, 2026 | 80B27 | CookDistrict 1 | 38 CU YD | $225.00 | Plote Construction, Inc. |
| Apr 24, 2026 | 61L54 | CookDistrict 1 | 365 CU YD | $73.44 | Martam Construction Incorporated |
| Apr 24, 2026 | 61M11 | AuroraDistrict 1 | 40 CU YD | $60.00 | Alliance Contractors, Inc. |
| Apr 24, 2026 | 61L48 | Kane, MchenryDistrict 1 | 17,146 CU YD | $55.58 | William Charles Construction Company, LLC |
| Apr 24, 2026 | 80B30 | CookDistrict 1 | 760 CU YD | $50.00 | K-Five Construction Corporation |
| Apr 24, 2026 | 61M15 | CookDistrict 1 | 61 CU YD | $72.00 | Dunnet Bay Construction Company |
| Apr 24, 2026 | 62P51 | CookDistrict 1 | 387 CU YD | $42.78 | Martam Construction Incorporated |
| Apr 24, 2026 | 61L86 | MchenryDistrict 1 | 229 CU YD | $69.00 | Dunnet Bay Construction Company |
| Apr 24, 2026 | 80B31 | WillDistrict 1 | 687 CU YD | $40.00 | P. T. Ferro Construction Co. |
| Apr 24, 2026 | 61M17 | KaneDistrict 1 | 1,240 CU YD | $58.00 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Apr 24, 2026 | 72N43 | SangamonDistrict 6 | 41 CU YD | $117.25 | Baxmeyer Construction, Inc. |
| Apr 24, 2026 | 61M36 | DupageDistrict 1 | 36 CU YD | $50.00 | Builders Paving, LLC |
| Apr 24, 2026 | 80C49 | CookDistrict 1 | 255 CU YD | $69.65 | K-Five Construction Corporation |
| Apr 24, 2026 | 61M37 | DupageDistrict 1 | 176 CU YD | $10.00 | R. W. Dunteman Company |
| Apr 24, 2026 | 80B12 | MchenryDistrict 1 | 36 CU YD | $63.00 | Alliance Contractors, Inc. |
| Apr 24, 2026 | 64T73 | LeeDistrict 2 | 22 CU YD | $25.00 | Martin & Company Excavating |
| Feb 27, 2026 | 62P01 | WillDistrict 1 | 100 CU YD | $32.00 | Austin Tyler Construction, Inc. |
| Feb 27, 2026 | 61M18 | CookDistrict 1 | 20 CU YD | $100.00 | Gallagher Asphalt Corporation |
| Feb 27, 2026 | 62R23 | WillDistrict 1 | 5,330 CU YD | $40.00 | D. Construction, Inc. & Kraemer North America, LLC JV |
| Feb 27, 2026 | 61L39 | KaneDistrict 1 | 334 CU YD | $42.75 | Geneva Construction Company LLC. |
| Feb 27, 2026 | 61M19 | MchenryDistrict 1 | 86 CU YD | $39.60 | Geske and Sons, Inc. |
| Feb 27, 2026 | 64R72 | WinnebagoDistrict 2 | 1,506 CU YD | $47.00 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Feb 27, 2026 | 61M05 | CookDistrict 1 | 50 CU YD | $65.00 | K-Five Construction Corporation |
| Feb 27, 2026 | 61M23 | MchenryDistrict 1 | 228 CU YD | $15.00 | Geske and Sons, Inc. |
| Feb 27, 2026 | 64U03 | Lasalle, LeeDistrict 2 | 91 CU YD | $25.00 | Rock Road Companies, Inc. |
| Feb 27, 2026 | 61M25 | WillDistrict 1 | 10 CU YD | $100.00 | D. Construction, Inc. |
| Feb 27, 2026 | 62T82 | LakeDistrict 1 | 25 CU YD | $70.57 | Martam Construction Incorporated |
| Feb 27, 2026 | 80B15 | DupageDistrict 1 | 159 CU YD | $65.00 | R. W. Dunteman Company |
| Feb 27, 2026 | 61M26 | CookDistrict 1 | 2,586 CU YD | $20.00 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 62V09 | CookDistrict 1 | 372 CU YD | $45.00 | Plote Construction, Inc. |
| Jan 16, 2026 | 61L36 | DupageDistrict 1 | 311 CU YD | $48.00 | Acura Inc. |
| Jan 16, 2026 | 80B11 | WillDistrict 1 | 83 CU YD | $89.75 | Iroquois Paving Corporation |
| Jan 16, 2026 | 62W47 | CookDistrict 1 | 200 CU YD | $55.00 | D. Construction, Inc. |
| Jan 16, 2026 | 61L19 | LakeDistrict 1 | 1,252 CU YD | $50.00 | Dunnet Bay Construction Company |
| Jan 16, 2026 | 62F94 | WillDistrict 1 | 7,056 CU YD | $40.00 | D. Construction, Inc. |
| Jan 16, 2026 | 61K16 | CookDistrict 1 | 408 CU YD | $50.00 | Alliance Contractors, Inc. |
| Jan 16, 2026 | 60R94 | CookDistrict 1 | 2,663 CU YD | $60.00 | OHLA Central, Inc. |
| Jan 16, 2026 | 80B34 | WillDistrict 1 | 19 CU YD | $130.00 | Gallagher Asphalt Corporation |
| Jan 16, 2026 | 61L42 | LakeDistrict 1 | 1,212 CU YD | $70.00 | D'Land Construction, LLC |
| Jan 16, 2026 | 62K62 | CookDistrict 1 | 667 CU YD | $71.00 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 61L44 | DupageDistrict 1 | 148 CU YD | $50.00 | Builders Paving, LLC |
| Jan 16, 2026 | 61M01 | WillDistrict 1 | 983 CU YD | $38.00 | Austin Tyler Construction, Inc. |
| Jan 16, 2026 | 93839 | SangamonDistrict 6 | 180 CU YD | $79.00 | Kinney Contractors, Inc. |
| Jan 16, 2026 | 61L94 | MchenryDistrict 1 | 793 CU YD | $32.46 | Geske and Sons, Inc. |
| Jan 16, 2026 | 62K64 | CookDistrict 1 | 100 CU YD | $75.00 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 61M08 | LakeDistrict 1 | 668 CU YD | $76.09 | Campanella and Sons, Inc. |
| Jan 16, 2026 | 85763 | Rock IslandDistrict 2 | 230 CU YD | $88.00 | Valley Construction Co. |
| Jan 16, 2026 | 62W33 | CookDistrict 1 | 150 CU YD | $70.00 | Iroquois Paving Corporation |
| Jan 16, 2026 | 62K65 | CookDistrict 1 | 857 CU YD | $75.00 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 61M09 | CookDistrict 1 | 150 CU YD | $65.00 | Martam Construction Incorporated |
| Jan 16, 2026 | 89873 | PeoriaDistrict 4 | 80 CU YD | $107.59 | Otto Baum Company, Inc. |
| Jan 16, 2026 | 64L27 | StephensonDistrict 2 | 479 CU YD | $38.00 | Martin & Company Excavating |
| Jan 16, 2026 | 62U12 | CookDistrict 1 | 10 CU YD | $100.00 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 61J01 | DupageDistrict 1 | 1,085 CU YD | $1.00 | R. W. Dunteman Company |
| Jan 16, 2026 | 62D34 | CookDistrict 1 | 100 CU YD | $120.00 | Lorig Construction Company |
| Nov 7, 2025 | 61L97 | KaneDistrict 1 | 122 CU YD | $52.00 | Everlast Blacktop Inc. |
| Nov 7, 2025 | 61L98 | CookDistrict 1 | 853 CU YD | $127.00 | PirTano Construction Co., LLC |
| Nov 7, 2025 | 61L88 | MchenryDistrict 1 | 1,021 CU YD | $57.00 | Dunnet Bay Construction Company |
| Nov 7, 2025 | 62R51 | WillDistrict 1 | 520 CU YD | $0.0100 | Iroquois Paving Corporation |
| Nov 7, 2025 | 62R63 | CookDistrict 1 | 1,762 CU YD | $63.45 | Dunnet Bay Construction Company |
| Nov 7, 2025 | 87889 | DekalbDistrict 3 | 100 CU YD | $55.00 | D. Construction, Inc. |
| Nov 7, 2025 | 62U41 | CookDistrict 1 | 808 CU YD | $110.00 | Lorig Construction Company |
| Nov 7, 2025 | 61J94 | CookDistrict 1 | 171 CU YD | $59.00 | A Lamp Concrete Contractors, Inc. |
| Nov 7, 2025 | 61J54 | DupageDistrict 1 | 315 CU YD | $120.00 | Lorig Construction Company |
| Nov 7, 2025 | 87843 | DekalbDistrict 3 | 390 CU YD | $60.00 | Martin & Company Excavating |
| Nov 7, 2025 | 61L73 | WillDistrict 1 | 253 CU YD | $60.00 | D. Construction, Inc. |
| Nov 7, 2025 | 61L92 | CookDistrict 1 | 299 CU YD | $50.00 | Capitol Cement Co., Inc. |
| Nov 7, 2025 | 61L82 | CookDistrict 1 | 81 CU YD | $108.00 | Dunnet Bay Construction Company |
| Nov 7, 2025 | 61L78 | DupageDistrict 1 | 500 CU YD | $25.00 | A Lamp Concrete Contractors, Inc. |
| Sep 19, 2025 | 62U11 | Cook, WillDistrict 1 | 30 CU YD | $190.00 | Everlast Blacktop Inc. |
| Sep 19, 2025 | 64P76 | HenryDistrict 2 | 203 CU YD | $0.0100 | Advanced Asphalt Company |
| Sep 19, 2025 | 61L28 | KaneDistrict 1 | 1,077 CU YD | $61.13 | Martam Construction Incorporated |
| Sep 19, 2025 | 61L69 | DupageDistrict 1 | 848 CU YD | $60.00 | D. Construction, Inc. |
| Sep 19, 2025 | 70F21 | McleanDistrict 5 | 150 CU YD | $112.76 | Rowe Construction, a div of UCM, Inc. |
| Sep 19, 2025 | 62B64 | CookDistrict 1 | 53 CU YD | $76.10 | R. W. Dunteman Company |
| Sep 19, 2025 | 61K93 | CookDistrict 1 | 3,431 CU YD | $54.60 | Lima Contractors |
| Sep 19, 2025 | 87846 | KendallDistrict 3 | 203 CU YD | $50.00 | D. Construction, Inc. |
| Sep 19, 2025 | 62K78 | KaneDistrict 1 | 275 CU YD | $55.00 | Plote Construction, Inc. |
| Sep 19, 2025 | 61L71 | CookDistrict 1 | 14 CU YD | $110.00 | Builders Paving, LLC |
| Sep 19, 2025 | 61K52 | LakeDistrict 1 | 40 CU YD | $260.00 | Dunnet Bay Construction Company |
| Sep 19, 2025 | 62R22 | WillDistrict 1 | 7,332 CU YD | $40.00 | D. Construction, Inc. |
| Sep 19, 2025 | 76T17 | St.clairDistrict 8 | 136 CU YD | $57.60 | Keeley & Sons, Inc. |
| Sep 19, 2025 | 62X01 | WillDistrict 1 | 8,972 CU YD | $0.0100 | Iroquois Paving Corporation |
| Aug 1, 2025 | 62V91 | CookDistrict 1 | 145 CU YD | $55.00 | D. Construction, Inc. |
| Aug 1, 2025 | 61L58 | KaneDistrict 1 | 389 CU YD | $80.00 | Plote Construction, Inc. |
| Aug 1, 2025 | 61L45 | DupageDistrict 1 | 149 CU YD | $51.50 | R. W. Dunteman Company |
| Aug 1, 2025 | 61K77 | DupageDistrict 1 | 95 CU YD | $77.40 | R. W. Dunteman Company |
| Aug 1, 2025 | 64P28 | WinnebagoDistrict 2 | 134 CU YD | $35.00 | Martin & Company Excavating |
| Aug 1, 2025 | 61L47 | DupageDistrict 1 | 1,066 CU YD | $58.00 | Everlast Blacktop Inc. |
| Aug 1, 2025 | 61L37 | CookDistrict 1 | 1,497 CU YD | $40.00 | Plote Construction, Inc. |
| Aug 1, 2025 | 64C24 | WinnebagoDistrict 2 | 21,160 CU YD | $28.27 | OHLA Central, Inc. |
| Aug 1, 2025 | 61L38 | CookDistrict 1 | 1,340 CU YD | $40.00 | Plote Construction, Inc. |
| Aug 1, 2025 | 61L67 | KaneDistrict 1 | 650 CU YD | $50.00 | D. Construction, Inc. |
| Aug 1, 2025 | 61L46 | DupageDistrict 1 | 58 CU YD | $20.00 | A Lamp Concrete Contractors, Inc. |
| Aug 1, 2025 | 62N97 | CookDistrict 1 | 885 CU YD | $58.00 | Everlast Blacktop Inc. |
| Jun 13, 2025 | 61L64 | CookDistrict 1 | 184 CU YD | $68.00 | Peter Baker & Son Co. |
| Jun 13, 2025 | 62U39 | WillDistrict 1 | 123 CU YD | $55.00 | D. Construction, Inc. |
| Jun 13, 2025 | 61L49 | MchenryDistrict 1 | 184 CU YD | $67.00 | Alliance Contractors, Inc. |
| Jun 13, 2025 | 64M38 | WinnebagoDistrict 2 | 110 CU YD | $120.00 | Rock Road Companies, Inc. |
| Jun 13, 2025 | 62X69 | KaneDistrict 1 | 295 CU YD | $40.00 | Geneva Construction Company LLC. |
| Jun 13, 2025 | 61L65 | CookDistrict 1 | 40 CU YD | $20.00 | A Lamp Concrete Contractors, Inc. |
| Jun 13, 2025 | 62V52 | MchenryDistrict 1 | 325 CU YD | $65.00 | Curran Contracting Company |
| Jun 13, 2025 | 61L51 | MchenryDistrict 1 | 202 CU YD | $15.00 | Geske and Sons, Inc. |
| Jun 13, 2025 | 64R15 | Boone, WinnebagoDistrict 2 | 344 CU YD | $10.00 | Rock Road Companies, Inc. |
| Jun 13, 2025 | 64P13 | OgleDistrict 2 | 38 CU YD | $62.00 | Martin & Company Excavating |
| Jun 13, 2025 | 64S51 | WinnebagoDistrict 2 | 619 CU YD | $40.00 | Rock Road Companies, Inc. |
| Jun 13, 2025 | 62V57 | MchenryDistrict 1 | 632 CU YD | $50.00 | Curran Contracting Company |
| Jun 13, 2025 | 61L52 | LakeDistrict 1 | 109 CU YD | $65.00 | Alliance Contractors, Inc. |
| Jun 13, 2025 | 61L53 | CookDistrict 1 | 36 CU YD | $50.00 | Peter Baker & Son Co. |
| Jun 13, 2025 | 60R76 | WillDistrict 1 | 49 CU YD | $50.00 | D. Construction, Inc. |
| Jun 13, 2025 | 62V58 | LakeDistrict 1 | 541 CU YD | $78.65 | Peter Baker & Son Co. |
| Jun 13, 2025 | 61L62 | CookDistrict 1 | 213 CU YD | $68.00 | Peter Baker & Son Co. |
| Jun 13, 2025 | 61L60 | KaneDistrict 1 | 269 CU YD | $15.00 | Plote Construction, Inc. |
| Jun 13, 2025 | 61J86 | LakeDistrict 1 | 601 CU YD | $64.00 | Lake County Grading Company, LLC |
| Jun 13, 2025 | 62V88 | DupageDistrict 1 | 75 CU YD | $69.36 | R. W. Dunteman Company |
| Jun 13, 2025 | 61L63 | CookDistrict 1 | 123 CU YD | $67.00 | Peter Baker & Son Co. |
| Jun 13, 2025 | 62P73 | LakeDistrict 1 | 7,780 CU YD | $45.00 | Curran Contracting Company |
| Jun 13, 2025 | 61L40 | KaneDistrict 1 | 245 CU YD | $45.00 | Schroeder Asphalt Services, Inc. |
| Jun 13, 2025 | 62X59 | KaneDistrict 1 | 11 CU YD | $60.00 | Plote Construction, Inc. |
| Apr 25, 2025 | 64U31 | CarrollDistrict 2 | 577 CU YD | $46.00 | Martin & Company Excavating |
| Apr 25, 2025 | 62R62 | CookDistrict 1 | 219 CU YD | $83.55 | Areatha Construction Co., Inc. |
| Apr 25, 2025 | 61L18 | MchenryDistrict 1 | 957 CU YD | $73.00 | PirTano Construction Co., LLC |