2025-2012-RS
- Let date
- Friday, April 24, 2026
- Contract
- 80B31 · job page
- District
- District 1
- County
- Will
- Highway
- Limits
- Design Overlay and new Hot-Mix Asphalt Shoulder project includes hot-mix asphalt removal, earth excavation, pavement patching, resurfacing with hot-mix asphalt, full depth hot-mix asphalt shoulder, placement of pavement markings, ADA Improvements, installation of raised reflective pavement markers. Located on US Route 45 (LaGrange Road) in the Township of Green Garden and Village of Manhattan in Will County.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | P. T. Ferro Construction Co. Low bidder | $2,127,428 | ||
| 2 | Iroquois Paving Corporation | $2,144,605 | +0.8% | |
| 3 | Gallagher Asphalt Corporation | $2,262,111 | +6.3% | |
| 4 | Austin Tyler Construction, Inc. | $2,765,709 | +30.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 P. T. Ferro Con… | #2 Iroquois Paving… | #3 Gallagher Aspha… | #4 Austin Tyler Co… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327611 | REM & REIN BRIC PAVER | 27 | SQ FT | $35.00 | $38.80 | $100.00 | $113.00 | |
| 2 | X2020110 | GRADING & SHAP SHLDRS | 69 | UNIT | $0.0100 | $35.50 | $170.00 | $170.00 | |
| 3 | X4021000 | TEMP ACCESS- PRIV ENT | 3 | EACH | $0.0100 | $545.00 | $535.00 | $880.00 | |
| 4 | X4022000 | TEMP ACCESS- COM ENT | 15 | EACH | $0.0100 | $545.00 | $950.00 | $1,293.00 | |
| 5 | X4060995 | TEMPORARY RAMP SPL | 213 | SQ YD | $0.0100 | $78.00 | $30.00 | $17.50 | |
| 6 | X4400503 | CC&G RMVL REPL > 10FT | 85 | FOOT | $100.00 | $110.00 | $98.00 | $71.50 | |
| 7 | X6420114 | CENTERLN RUM STRIP 16 | 10,265 | FOOT | $0.6000 | $0.6300 | $0.5500 | $1.15 | |
| 8 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $1.00 | $2,950.00 | $500.00 | $3,390.00 | |
| 9 | X7200061 | TEMP INFO SIGNING | 565 | SQ FT | $15.00 | $15.10 | $15.00 | $34.00 | |
| 10 | X7800815 | HS THPL PM LN 4 | 2,598 | FOOT | $2.95 | $1.80 | $1.75 | $2.75 | |
| 11 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $25,000.00 | $12,450.00 | $8,600.00 | $11,812.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 7,392 | CU YD | $0.0100 | $0.0100 | $0.0100 | $48.00 | |
| 13 | 20201200 | REM & DISP UNS MATL | 687 | CU YD | $25.00 | $41.75 | $20.00 | $65.00 | |
| 14 | 21001000 | GEOTECH FAB F/GR STAB | 2,061 | SQ YD | $2.50 | $2.75 | $1.95 | $3.00 | |
| 15 | 21101615 | TOPSOIL F & P 4 | 50 | SQ YD | $50.00 | $65.00 | $50.00 | $56.50 | |
| 16 | 21400100 | GRADING & SHAP DITCH | 200 | FOOT | $25.00 | $57.50 | $10.50 | $23.75 | |
| 17 | 30300001 | AGG SUBGRADE IMPROVE | 687 | CU YD | $40.00 | $68.00 | $20.00 | $100.00 | |
| 18 | 30300112 | AGG SUBGRADE IMPR 12 | 8,245 | SQ YD | $40.00 | $56.00 | $51.30 | $40.00 | |
| 19 | 40600275 | BIT MATLS PR CT | 18,551 | POUND | $0.0100 | $0.0100 | $0.0100 | $1.40 | |
| 20 | 40600290 | BIT MATLS TACK CT | 24,221 | POUND | $0.0100 | $0.0100 | $0.0100 | $1.40 | |
| 21 | 40600370 | LONG JOINT SEALANT | 10,506 | FOOT | $3.25 | $3.20 | $3.15 | $3.50 | |
| 22 | 40600400 | MIX CR JTS FLANGEWYS | 37 | TON | $0.0100 | $0.0100 | $0.0100 | $355.00 | |
| 23 | 40600982 | HMA SURF REM BUTT JT | 312 | SQ YD | $0.0100 | $13.25 | $0.0100 | $23.00 | |
| 24 | 40602985 | HMA BC IL-9.5 N70 | 2,711 | TON | $87.00 | $85.00 | $86.00 | $82.00 | |
| 25 | 40603200 | P HMA BC IL-4.75 N50 | 491 | TON | $115.00 | $121.00 | $130.50 | $115.00 | |
| 26 | 40604062 | HMA SC IL-9.5 D N70 | 3,247 | TON | $87.00 | $80.00 | $97.00 | $82.25 | |
| 27 | 42001300 | PROTECTIVE COAT | 106 | SQ YD | $0.0100 | $0.0100 | $1.10 | $3.25 | |
| 28 | 42400200 | PC CONC SIDEWALK 5 | 784 | SQ FT | $12.50 | $9.75 | $9.10 | $12.00 | |
| 29 | 42400800 | DETECTABLE WARNINGS | 40 | SQ FT | $26.00 | $24.50 | $20.50 | $28.25 | |
| 30 | 44000100 | PAVEMENT REM | 1,700 | SQ YD | $15.00 | $0.0100 | $18.75 | $29.00 | |
| 31 | 44000164 | HMA SURF REM 3 3/4 | 24,200 | SQ YD | $3.00 | $3.40 | $4.00 | $5.25 | |
| 32 | 44000600 | SIDEWALK REM | 784 | SQ FT | $3.00 | $3.80 | $4.85 | $2.75 | |
| 33 | 44004250 | PAVED SHLD REMOVAL | 832 | SQ YD | $15.00 | $0.0100 | $20.40 | $25.50 | |
| 34 | 44201690 | CL D PATCH T1 4 | 8 | SQ YD | $110.00 | $275.00 | $149.00 | $176.00 | |
| 35 | 44201692 | CL D PATCH T2 4 | 10 | SQ YD | $100.00 | $265.00 | $138.00 | $156.00 | |
| 36 | 44201761 | CL D PATCH T1 10 | 10 | SQ YD | $175.00 | $175.00 | $109.00 | $309.00 | |
| 37 | 44201765 | CL D PATCH T2 10 | 150 | SQ YD | $125.00 | $155.00 | $109.00 | $280.00 | |
| 38 | 44201769 | CL D PATCH T3 10 | 250 | SQ YD | $110.00 | $150.00 | $109.00 | $239.00 | |
| 39 | 44201771 | CL D PATCH T4 10 | 250 | SQ YD | $100.00 | $141.00 | $109.00 | $121.00 | |
| 40 | 48102100 | AGG WEDGE SHLD TYPE B | 452 | TON | $35.00 | $44.00 | $50.00 | $52.75 | |
| 41 | 48203037 | HMA SHOULDERS 10 | 8,245 | SQ YD | $65.00 | $46.00 | $65.00 | $52.50 | |
| 42 | 60260100 | INLETS ADJUST | 2 | EACH | $750.00 | $285.00 | $480.00 | $1,550.00 | |
| 43 | 63000001 | SPBGR TY A 6FT POSTS | 120 | FOOT | $41.00 | $41.25 | $41.00 | $57.50 | |
| 44 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $4,200.00 | $4,225.00 | $4,200.00 | $4,750.00 | |
| 45 | 63200310 | GUARDRAIL REMOV | 120 | FOOT | $15.00 | $12.85 | $15.00 | $21.00 | |
| 46 | 64200108 | SHOULDER RUM STRIP 8 | 20,488 | FOOT | $0.4000 | $0.5300 | $0.3300 | $0.7500 | |
| 47 | 66900200 | NON SPL WASTE DISPOSL | 1,380 | CU YD | $75.00 | $83.00 | $67.00 | $76.00 | |
| 48 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,450.00 | $1,460.00 | $1,450.00 | $904.00 | |
| 49 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,100.00 | $3,115.00 | $3,100.00 | $6,215.00 | |
| 50 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,200.00 | $1,210.00 | $1,200.00 | $565.00 | |
| 51 | 66901006 | REG SUB MON | 15 | CAL DA | $680.00 | $685.00 | $680.00 | $836.00 | |
| 52 | 67100100 | MOBILIZATION | 1 | L SUM | $100,000.00 | $68,000.00 | $90,500.00 | $2,193.00 | |
| 53 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $2,072.00 | $2,085.00 | $2,072.00 | $565.00 | |
| 54 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $2,072.00 | $2,085.00 | $2,072.00 | $1,130.00 | |
| 55 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $2,072.00 | $2,085.00 | $2,072.00 | $1,130.00 | |
| 56 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $2,072.00 | $2,085.00 | $2,072.00 | $1,130.00 | |
| 57 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $2,072.00 | $2,085.00 | $2,072.00 | $1,695.00 | |
| 58 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $2,072.00 | $2,085.00 | $2,072.00 | $2,260.00 | |
| 59 | 70103815 | TR CONT SURVEILLANCE | 25 | CAL DA | $200.00 | $200.00 | $8.00 | $1,356.00 | |
| 60 | 70300100 | SHORT TERM PAVT MKING | 11,998 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.35 | |
| 61 | 70300150 | SHRT TRM PAVT MK REM | 19,997 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $2.00 | |
| 62 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 65,030 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.3000 | |
| 63 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 102 | FOOT | $0.0100 | $0.0100 | $0.0100 | $6.00 | |
| 64 | 70307120 | TEMP PVT MK L4 T4 TAPE | 2,999 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.50 | |
| 65 | 72000200 | SIGN PANEL T2 | 185 | SQ FT | $45.00 | $45.50 | $45.00 | $36.00 | |
| 66 | 78000200 | THPL PVT MK LINE 4 | 32,515 | FOOT | $0.8000 | $0.7500 | $0.7500 | $0.8000 | |
| 67 | 78000650 | THPL PVT MK LINE 24 | 51 | FOOT | $16.00 | $6.05 | $6.00 | $11.30 | |
| 68 | 78100100 | RAISED REFL PAVT MKR | 194 | EACH | $75.00 | $45.25 | $45.00 | $56.00 | |
| 69 | 78300200 | RAISED REF PVT MK REM | 194 | EACH | $0.0100 | $0.0100 | $0.0100 | $30.00 |