$0.9913Avg low bid / FOOT
$1.04Avg of all bids
—Avg engineer's estimate
298Jobs · 7,160,084 FOOT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 149 | 3,588,706 | $0.9329 | $1.04 |
| 2025 | 144 | 3,465,474 | $1.03 | $1.02 |
| 2024 | 5 | 105,904 | $1.60 | $1.40 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 18, 2026 | 62X33 | KaneDistrict 1 | 12,690 FOOT | $0.0100 | Builders Paving, LLC |
| Sep 18, 2026 | 62X84 | CookDistrict 1 | 66,058 FOOT | $0.0100 | K-Five Construction Corporation |
| Sep 18, 2026 | 64T43 | HenryDistrict 2 | 140,843 FOOT | $1.75 | D. Construction, Inc. |
| Sep 18, 2026 | 62L58 | CookDistrict 1 | 10,140 FOOT | $0.0100 | Builders Paving, LLC |
| Sep 18, 2026 | 80B49 | DupageDistrict 1 | 6,478 FOOT | $1.50 | Martam Construction Incorporated |
| Sep 18, 2026 | 74650 | ColesDistrict 7 | 38,400 FOOT | $1.95 | Sangamo Construction Company |
| Sep 18, 2026 | 66926 | LasalleDistrict 3 | 2,708 FOOT | $2.21 | D. Construction, Inc. |
| Sep 18, 2026 | 80C95 | WillDistrict 1 | 657 FOOT | $2.50 | Gallagher Asphalt Corporation |
| Sep 18, 2026 | 62V55 | CookDistrict 1 | 2,730 FOOT | $1.00 | Gallagher Asphalt Corporation |
| Sep 18, 2026 | 80D33 | CookDistrict 1 | 7,217 FOOT | $1.20 | K-Five Construction Corporation |
| Sep 18, 2026 | 61L85 | MchenryDistrict 1 | 5,100 FOOT | $1.20 | ICC Group Inc. |
| Sep 18, 2026 | 62V85 | CookDistrict 1 | 75,499 FOOT | $0.0100 | Builders Paving, LLC |
| Sep 18, 2026 | 61M10 | Kane, DupageDistrict 1 | 3,933 FOOT | $1.35 | K-Five Construction Corporation |
| Jul 31, 2026 | 62Y20 | CookDistrict 1 | 21,890 FOOT | $1.30 | Martam Construction Incorporated |
| Jul 31, 2026 | 64T49 | OgleDistrict 2 | 2,502 FOOT | $1.45 | Martin & Company Excavating |
| Jul 31, 2026 | 64T48 | WhitesideDistrict 2 | 2,482 FOOT | $1.45 | Martin & Company Excavating |
| Jul 31, 2026 | 61M13 | KaneDistrict 1 | 37,430 FOOT | $0.3000 | Dunnet Bay Construction Company |
| Jul 31, 2026 | 80B44 | CookDistrict 1 | 14,940 FOOT | $1.20 | D. Construction, Inc. |
| Jul 31, 2026 | 62J64 | CookDistrict 1 | 5,723 FOOT | $0.0100 | Peter Baker & Son Co. |
| Jul 31, 2026 | 80C87 | CookDistrict 1 | 1,580 FOOT | $0.0100 | Gallagher Asphalt Corporation |
| Jul 31, 2026 | 62V45 | CookDistrict 1 | 17,351 FOOT | $0.0100 | D. Construction, Inc. |
| Jul 31, 2026 | 62W20 | CookDistrict 1 | 14,186 FOOT | $2.00 | D. Construction, Inc. |
| Jul 31, 2026 | 61K19 | CookDistrict 1 | 8,217 FOOT | $1.30 | R. W. Dunteman Company |
| Jun 12, 2026 | 80C48 | LakeDistrict 1 | 16,165 FOOT | $0.0100 | Peter Baker & Son Co. |
| Jun 12, 2026 | 64T58 | StephensonDistrict 2 | 4,676 FOOT | $1.25 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Jun 12, 2026 | 80B33 | CookDistrict 1 | 385 FOOT | $0.0100 | D. Construction, Inc. |
| Jun 12, 2026 | 62X52 | DupageDistrict 1 | 4,635 FOOT | $0.0100 | D. Construction, Inc. |
| Jun 12, 2026 | 62L30 | CookDistrict 1 | 123,768 FOOT | $1.10 | D. Construction, Inc. |
| Jun 12, 2026 | 76R32 | MadisonDistrict 8 | 18,598 FOOT | $2.42 | Stutz Excavating, Inc. |
| Jun 12, 2026 | 80D00 | CookDistrict 1 | 7,693 FOOT | $0.0100 | Plote Construction, Inc. |
| Jun 12, 2026 | 66A91 | LasalleDistrict 3 | 212,621 FOOT | $0.7000 | Advanced Asphalt Company |
| Jun 12, 2026 | 80B35 | CookDistrict 1 | 30,564 FOOT | $1.25 | K-Five Construction Corporation |
| Jun 12, 2026 | 64N73 | StephensonDistrict 2 | 10,852 FOOT | $1.25 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Jun 12, 2026 | 62M71 | Kane, KendallDistrict 1 | 243,475 FOOT | $1.50 | D. Construction, Inc. |
| Jun 12, 2026 | 80B17 | WillDistrict 1 | 531 FOOT | $0.0100 | Iroquois Paving Corporation |
| Jun 12, 2026 | 80D46 | LakeDistrict 1 | 14,079 FOOT | $1.30 | Curran Contracting Company |
| Jun 12, 2026 | 66K39 | FordDistrict 3 | 121,536 FOOT | $1.90 | Stark Excavating, Inc. |
| Jun 12, 2026 | 80B51 | CookDistrict 1 | 5,826 FOOT | $1.30 | Capital Industrial Services, LLC |
| Jun 12, 2026 | 64T07 | OgleDistrict 2 | 3,729 FOOT | $1.50 | Martin & Company Excavating |
| Jun 12, 2026 | 62R61 | CookDistrict 1 | 33,083 FOOT | $1.23 | OHLA Central, Inc. |
| Jun 12, 2026 | 80B22 | CookDistrict 1 | 10,127 FOOT | $1.40 | K-Five Construction Corporation |
| Jun 12, 2026 | 78977 | FranklinDistrict 9 | 1,425 FOOT | $0.0100 | Samron Midwest Contracting, Inc. |
| Jun 12, 2026 | 66M84 | LasalleDistrict 3 | 18 FOOT | $5.00 | D. Construction, Inc. |
| Jun 12, 2026 | 80B87 | CookDistrict 1 | 4,000 FOOT | $0.0100 | Builders Paving, LLC |
| Jun 12, 2026 | 64T46 | WhitesideDistrict 2 | 1,932 FOOT | $1.50 | Martin & Company Excavating |
| Jun 12, 2026 | 62U72 | MchenryDistrict 1 | 212,485 FOOT | $0.4000 | Martam Construction Incorporated |
| Jun 12, 2026 | 80B23 | KaneDistrict 1 | 6,041 FOOT | $0.1000 | Plote Construction, Inc. |
| Jun 12, 2026 | 97899 | St. ClairDistrict 8 | 4,207 FOOT | $1.95 | Hank's Excavating & Landscaping, Inc. |
| Jun 12, 2026 | 66M92 | LivingstonDistrict 3 | 4,850 FOOT | $0.0100 | Iroquois Paving Corporation |
| Jun 12, 2026 | 61M42 | KaneDistrict 1 | 11,895 FOOT | $0.0100 | D. Construction, Inc. |
| Jun 12, 2026 | 80C45 | MchenryDistrict 1 | 1,122 FOOT | $1.11 | Peter Baker & Son Co. |
| Jun 12, 2026 | 64T47 | OgleDistrict 2 | 2,594 FOOT | $4.00 | Martin & Company Excavating |
| Jun 12, 2026 | 62W99 | CookDistrict 1 | 178,327 FOOT | $0.0100 | K-Five Construction Corporation |
| Jun 12, 2026 | 80B28 | CookDistrict 1 | 24,935 FOOT | $0.0100 | K-Five Construction Corporation |
| Jun 12, 2026 | 68J15 | TazewellDistrict 4 | 1,681 FOOT | $1.76 | R. A. Cullinan and Son, a div of UCM, Inc. |
| Jun 12, 2026 | 61M43 | KaneDistrict 1 | 4,763 FOOT | $0.0100 | D. Construction, Inc. |
| Apr 24, 2026 | 80B39 | CookDistrict 1 | 39,320 FOOT | $0.0100 | K-Five Construction Corporation |
| Apr 24, 2026 | 80B10 | MchenryDistrict 1 | 1,595 FOOT | $0.0100 | Peter Baker & Son Co. |
| Apr 24, 2026 | 64U89 | WinnebagoDistrict 2 | 6,336 FOOT | $1.50 | Martin & Company Excavating |
| Apr 24, 2026 | 80B05 | WillDistrict 1 | 19,742 FOOT | $1.25 | D. Construction, Inc. |
| Apr 24, 2026 | 61L86 | MchenryDistrict 1 | 3,760 FOOT | $1.35 | Dunnet Bay Construction Company |
| Apr 24, 2026 | 62L85 | CookDistrict 1 | 1,149 FOOT | $1.35 | K-Five Construction Corporation |
| Apr 24, 2026 | 80B48 | CookDistrict 1 | 11,281 FOOT | $1.40 | Martam Construction Incorporated |
| Apr 24, 2026 | 61M41 | LakeDistrict 1 | 868 FOOT | $1.40 | Alliance Contractors, Inc. |
| Apr 24, 2026 | 64U90 | WinnebagoDistrict 2 | 4,560 FOOT | $1.50 | Martin & Company Excavating |
| Apr 24, 2026 | 80B21 | CookDistrict 1 | 3,282 FOOT | $1.50 | K-Five Construction Corporation |
| Apr 24, 2026 | 61M36 | DupageDistrict 1 | 2,904 FOOT | $0.0100 | Builders Paving, LLC |
| Apr 24, 2026 | 62P51 | CookDistrict 1 | 37,356 FOOT | $1.40 | Martam Construction Incorporated |
| Apr 24, 2026 | 80B62 | CookDistrict 1 | 6,838 FOOT | $1.50 | Martam Construction Incorporated |
| Apr 24, 2026 | 80B20 | MchenryDistrict 1 | 9,350 FOOT | $1.25 | Triggi Construction, Inc. |
| Apr 24, 2026 | 68K22 | WoodfordDistrict 4 | 11,385 FOOT | $1.60 | Stark Excavating, Inc. |
| Apr 24, 2026 | 80B27 | CookDistrict 1 | 24,948 FOOT | $0.0100 | Plote Construction, Inc. |
| Apr 24, 2026 | 62X57 | CookDistrict 1 | 3,649 FOOT | $1.35 | Schroeder Asphalt Services, Inc. |
| Apr 24, 2026 | 62V71 | WillDistrict 1 | 7,550 FOOT | $0.0100 | D. Construction, Inc. |
| Apr 24, 2026 | 80B68 | DupageDistrict 1 | 2,703 FOOT | $0.0100 | D. Construction, Inc. |
| Apr 24, 2026 | 80B54 | DupageDistrict 1 | 10,800 FOOT | $0.1000 | ERA-Valdivia Contractors, Inc. |
| Apr 24, 2026 | 70H82 | McleanDistrict 5 | 640 FOOT | $3.00 | Stark Excavating, Inc. |
| Apr 24, 2026 | 80B30 | CookDistrict 1 | 72,489 FOOT | $0.0100 | K-Five Construction Corporation |
| Apr 24, 2026 | 64T06 | OgleDistrict 2 | 24,273 FOOT | $1.45 | Martin & Company Excavating |
| Apr 24, 2026 | 62Y30 | CookDistrict 1 | 3,315 FOOT | $1.50 | Martam Construction Incorporated |
| Apr 24, 2026 | 80C49 | CookDistrict 1 | 65,420 FOOT | $0.0100 | K-Five Construction Corporation |
| Apr 24, 2026 | 80B09 | CookDistrict 1 | 19,640 FOOT | $0.0100 | Builders Paving, LLC |
| Apr 24, 2026 | 80B31 | WillDistrict 1 | 2,999 FOOT | $0.0100 | P. T. Ferro Construction Co. |
| Apr 24, 2026 | 64T42 | StephensonDistrict 2 | 25,627 FOOT | $1.50 | Martin & Company Excavating |
| Apr 24, 2026 | 66N58 | GrundyDistrict 3 | 5,686 FOOT | $1.80 | D. Construction, Inc. |
| Apr 24, 2026 | 80C85 | MchenryDistrict 1 | 302,672 FOOT | $1.14 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Apr 24, 2026 | 62K33 | CookDistrict 1 | 147,343 FOOT | $1.15 | Plote Construction, Inc. |
| Feb 27, 2026 | 61M32 | CookDistrict 1 | 3,250 FOOT | $0.0100 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 68J57 | PeoriaDistrict 4 | 2,494 FOOT | $1.60 | Advanced Asphalt Company |
| Feb 27, 2026 | 62V43 | KaneDistrict 1 | 10,557 FOOT | $0.0100 | Builders Paving, LLC |
| Feb 27, 2026 | 62Y17 | CookDistrict 1 | 6,843 FOOT | $1.50 | MYS, Incorporated |
| Feb 27, 2026 | 61M26 | CookDistrict 1 | 296 FOOT | $0.0100 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 80B25 | DupageDistrict 1 | 6,345 FOOT | $1.30 | R. W. Dunteman Company |
| Feb 27, 2026 | 70F37 | McleanDistrict 5 | 24,276 FOOT | $1.85 | Stark Excavating, Inc. |
| Feb 27, 2026 | 68J46 | PeoriaDistrict 4 | 2,099 FOOT | $1.67 | Otto Baum Company, Inc. |
| Feb 27, 2026 | 62Y26 | WillDistrict 1 | 41,148 FOOT | $0.0100 | Iroquois Paving Corporation |
| Feb 27, 2026 | 61M27 | CookDistrict 1 | 285 FOOT | $1.00 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 80B56 | CookDistrict 1 | 4,425 FOOT | $1.28 | Eagle Painting & Maintenance Company, Inc. |
| Feb 27, 2026 | 70F77 | McleanDistrict 5 | 13,475 FOOT | $1.80 | Stark Excavating, Inc. |
| Feb 27, 2026 | 80B08 | DupageDistrict 1 | 6,791 FOOT | $0.0100 | Builders Paving, LLC |
| Feb 27, 2026 | 64R72 | WinnebagoDistrict 2 | 79,961 FOOT | $1.15 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Feb 27, 2026 | 62P01 | WillDistrict 1 | 42,978 FOOT | $1.55 | Austin Tyler Construction, Inc. |
| Feb 27, 2026 | 80B75 | LakeDistrict 1 | 6,692 FOOT | $1.16 | Peter Baker & Son Co. |
| Feb 27, 2026 | 74C49 | ClarkDistrict 7 | 5,656 FOOT | $1.42 | Sangamo Construction Company |
| Feb 27, 2026 | 61M19 | MchenryDistrict 1 | 3,368 FOOT | $0.0100 | Geske and Sons, Inc. |
| Feb 27, 2026 | 68E33 | MarshallDistrict 4 | 3,482 FOOT | $1.93 | Gillan Construction LLC |
| Feb 27, 2026 | 62R23 | WillDistrict 1 | 11,067 FOOT | $1.50 | D. Construction, Inc. & Kraemer North America, LLC JV |
| Feb 27, 2026 | 85769 | WinnebagoDistrict 2 | 4,200 FOOT | $1.21 | N-Trak Group LLC |
| Feb 27, 2026 | 80B13 | WillDistrict 1 | 14,722 FOOT | $0.0100 | P. T. Ferro Construction Co. |
| Feb 27, 2026 | 61L39 | KaneDistrict 1 | 29,436 FOOT | $0.5000 | Geneva Construction Company LLC. |
| Feb 27, 2026 | 62T82 | LakeDistrict 1 | 7,077 FOOT | $1.40 | Martam Construction Incorporated |
| Feb 27, 2026 | 68J51 | PeoriaDistrict 4 | 3,192 FOOT | $1.75 | Stark Excavating, Inc. |
| Feb 27, 2026 | 62V09 | CookDistrict 1 | 604 FOOT | $1.40 | Plote Construction, Inc. |
| Feb 27, 2026 | 62X88 | CookDistrict 1 | 14,202 FOOT | $0.0100 | Peter Baker & Son Co. |
| Feb 27, 2026 | 61M16 | CookDistrict 1 | 1,534 FOOT | $0.0100 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 80B15 | DupageDistrict 1 | 9,291 FOOT | $1.00 | R. W. Dunteman Company |
| Jan 16, 2026 | 62R76 | WillDistrict 1 | 9,790 FOOT | $0.0100 | D. Construction, Inc. |
| Jan 16, 2026 | 61K16 | CookDistrict 1 | 15,213 FOOT | $1.00 | Alliance Contractors, Inc. |
| Jan 16, 2026 | 80B34 | WillDistrict 1 | 4,335 FOOT | $0.0100 | Gallagher Asphalt Corporation |
| Jan 16, 2026 | 62D34 | CookDistrict 1 | 6,291 FOOT | $1.20 | Lorig Construction Company |
| Jan 16, 2026 | 70F93 | McleanDistrict 5 | 26,834 FOOT | $1.75 | Stark Excavating, Inc. |
| Jan 16, 2026 | 64L27 | StephensonDistrict 2 | 9,232 FOOT | $1.40 | Martin & Company Excavating |
| Jan 16, 2026 | 62U12 | CookDistrict 1 | 12,834 FOOT | $1.25 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 61J01 | DupageDistrict 1 | 40,260 FOOT | $1.22 | R. W. Dunteman Company |
| Jan 16, 2026 | 80B50 | LakeDistrict 1 | 3,077 FOOT | $0.0100 | Builders Paving, LLC |
| Jan 16, 2026 | 80B36 | WillDistrict 1 | 20,864 FOOT | $0.0100 | D. Construction, Inc. |
| Jan 16, 2026 | 62F94 | WillDistrict 1 | 67,642 FOOT | $2.50 | D. Construction, Inc. |
| Jan 16, 2026 | 74893 | EffinghamDistrict 7 | 83,001 FOOT | $1.50 | William Charles Construction Company, LLC |
| Jan 16, 2026 | 64T05 | OgleDistrict 2 | 2,355 FOOT | $1.50 | Martin & Company Excavating |
| Jan 16, 2026 | 62W47 | CookDistrict 1 | 12,227 FOOT | $0.0100 | D. Construction, Inc. |
| Jan 16, 2026 | 61L19 | LakeDistrict 1 | 440 FOOT | $2.25 | Dunnet Bay Construction Company |
| Jan 16, 2026 | 93826 | LoganDistrict 6 | 1,500 FOOT | $1.25 | Kinney Contractors, Inc. |
| Jan 16, 2026 | 62K62 | CookDistrict 1 | 17,395 FOOT | $1.20 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 78A09 | FranklinDistrict 9 | 1,245 FOOT | $3.00 | Samron Midwest Contracting, Inc. |
| Jan 16, 2026 | 64T96 | LeeDistrict 2 | 2,950 FOOT | $1.60 | Martin & Company Excavating |
| Jan 16, 2026 | 64L71 | HenryDistrict 2 | 2,352 FOOT | $1.50 | Phoenix Corporation of the Quad Cities |
| Jan 16, 2026 | 61L42 | LakeDistrict 1 | 10,272 FOOT | $1.34 | D'Land Construction, LLC |
| Jan 16, 2026 | 80B18 | CookDistrict 1 | 1,211 FOOT | $1.40 | Everlast Blacktop Inc. |
| Jan 16, 2026 | 62K64 | CookDistrict 1 | 69,932 FOOT | $0.2500 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 80B19 | CookDistrict 1 | 12,728 FOOT | $0.0100 | Gallagher Asphalt Corporation |
| Jan 16, 2026 | 80B11 | WillDistrict 1 | 27,065 FOOT | $0.0100 | Iroquois Paving Corporation |
| Jan 16, 2026 | 66R21 | LasalleDistrict 3 | 4,696 FOOT | $3.50 | D. Construction, Inc. |
| Jan 16, 2026 | 62W33 | CookDistrict 1 | 5,050 FOOT | $0.0100 | Iroquois Paving Corporation |
| Jan 16, 2026 | 62K65 | CookDistrict 1 | 28,281 FOOT | $0.2000 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 97851 | MadisonDistrict 8 | 14,664 FOOT | $1.35 | The Kilian Corporation |
| Jan 16, 2026 | 80B29 | LakeDistrict 1 | 676 FOOT | $0.0100 | Peter Baker & Son Co. |
| Jan 16, 2026 | 62321 | CookDistrict 1 | 5,356 FOOT | $1.20 | MAT Construction Leasing, Inc. |
| Jan 16, 2026 | 68F50 | FultonDistrict 4 | 6,135 FOOT | $1.62 | Civil Coatings and Construction Inc. |
| Jan 16, 2026 | 62Y05 | MchenryDistrict 1 | 2,205 FOOT | $1.30 | Martam Construction Incorporated |
| Nov 7, 2025 | 85785 | Rock IslandDistrict 2 | 9,662 FOOT | $1.50 | Gensini Excavating, Inc. |