(102BR-1)BRR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martin & Company Excavating Low bidder | $618,490 | ||
| 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $626,999 | +1.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martin & Compan… | #2 Civil Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X5030250 | BR DECK GROOVING LONG | 298 | SQ YD | $26.00 | $16.50 | |
| 2 | X7820008 | BARRIER WALL REFL SPL | 10 | EACH | $40.00 | $30.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,500.00 | $3,450.00 | |
| 4 | Z0029090 | DIAMOND GRIND BR SEC | 570 | SQ YD | $31.00 | $18.00 | |
| 5 | Z0032400 | JOINT REPAIR | 14 | EACH | $250.00 | $220.00 | |
| 6 | Z0041895 | POLYMER CONCRETE | 3 | CU FT | $1,635.00 | $1,760.00 | |
| 7 | Z0043800 | P P CONC I-BM REPAIR | 6 | SQ FT | $1,500.00 | $300.00 | |
| 8 | 40600290 | BIT MATLS TACK CT | 372 | POUND | $0.1000 | $0.6500 | |
| 9 | 40600982 | HMA SURF REM BUTT JT | 326 | SQ YD | $20.00 | $28.00 | |
| 10 | 40603080 | HMA BC IL-19.0 N50 | 16 | TON | $300.00 | $251.00 | |
| 11 | 40604050 | HMA SC IL-9.5 C N50 | 64 | TON | $300.00 | $255.00 | |
| 12 | 44000157 | HMA SURF REM 2 | 339 | SQ YD | $20.00 | $28.00 | |
| 13 | 50102400 | CONC REM | 33.2 | CU YD | $2,400.00 | $3,100.00 | |
| 14 | 50300255 | CONC SUP-STR | 35.2 | CU YD | $2,400.00 | $1,800.00 | |
| 15 | 50300300 | PROTECTIVE COAT | 62 | SQ YD | $1.00 | $10.00 | |
| 16 | 50800205 | REINF BARS, EPOXY CTD | 4,410 | POUND | $4.00 | $3.70 | |
| 17 | 50800515 | BAR SPLICERS | 36 | EACH | $65.00 | $88.00 | |
| 18 | 52000110 | PREF JT STRIP SEAL | 94 | FOOT | $396.00 | $330.00 | |
| 19 | 53016001 | DECK SLAB REP (FD-T1) | 2 | SQ YD | $1,850.00 | $2,700.00 | |
| 20 | 53101002 | BR DECK SCAR 3/4 | 581 | SQ YD | $105.00 | $166.00 | |
| 21 | 53101408 | BR DK LTX C OLY 2 1/4 | 581 | SQ YD | $210.00 | $196.00 | |
| 22 | 53212754 | STR REP CON DP = < 5 | 3 | SQ FT | $500.00 | $545.00 | |
| 23 | 60260100 | INLETS ADJUST | 2 | EACH | $2,500.00 | $520.00 | |
| 24 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $3,500.00 | $3,925.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $35,000.00 | $37,618.00 | |
| 26 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $14,000.00 | $11,450.00 | |
| 27 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $100.00 | $100.00 | |
| 28 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $100.00 | $100.00 | |
| 29 | 70103815 | TR CONT SURVEILLANCE | 5 | CAL DA | $1.00 | $500.00 | |
| 30 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $11,000.00 | $9,000.00 | |
| 31 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $60.00 | $50.00 | |
| 32 | 70300150 | SHRT TRM PAVT MK REM | 8,889 | SQ FT | $0.0100 | $0.7500 | |
| 33 | 70307120 | TEMP PVT MK L4 T4 TAPE | 2,594 | FOOT | $4.00 | $1.25 | |
| 34 | 70307210 | TEMP PVT MK L24 T4 TAPE | 24 | FOOT | $10.00 | $7.50 | |
| 35 | 70400100 | TEMP CONC BARRIER | 418 | FOOT | $40.00 | $54.00 | |
| 36 | 70400200 | REL TEMP CONC BARRIER | 418 | FOOT | $10.00 | $9.00 | |
| 37 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $2,900.00 | $2,500.00 | |
| 38 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $600.00 | $500.00 | |
| 39 | 78009004 | MOD URETH PM LINE 4 | 1,229 | FOOT | $5.00 | $5.00 | |
| 40 | 78011025 | GRV RCSD PVT MRKG 5 | 800 | FOOT | $6.00 | $3.00 | |
| 41 | 78300202 | PVT MKG REM WTR BLAST | 428 | SQ FT | $5.50 | $4.50 |