275BidsApr 24, 2020 to Sep 18, 2026
106Wins (low bidder)
38.5%Win rate
$299,554,407Total won
Competitor scorecard
Last 5 years in Illinois38.9%Win rate75 of 193 bids
—Average bid vs estimate
—Winning bids vs estimate
+18.4%Over the low bid when they loseAverage field: 3.2 bidders
| Head to head | Times met | Beat them | Lost to them | Record |
|---|---|---|---|---|
| Martin & Company Excavating | 118 | 47 | 71 | 40% |
| Sjostrom & Sons, Inc. | 52 | 35 | 17 | 67% |
| Brandt Construction Co. | 39 | 31 | 8 | 79% |
| Alliance Contractors, Inc. | 22 | 17 | 5 | 77% |
| Path Construction Company, Inc. | 19 | 12 | 7 | 63% |
| ERA-Valdivia Contractors, Inc. | 15 | 12 | 3 | 80% |
| D. Construction, Inc. | 14 | 2 | 12 | 14% |
| Rock Road Companies, Inc. | 10 | 3 | 7 | 30% |
| Martam Construction Incorporated | 9 | 7 | 2 | 78% |
| Gensini Excavating, Inc. | 9 | 2 | 7 | 22% |
| Let date | Contract | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Sep 18, 2026 | 64T43 | (37-(3-1,4,5,6))BRRHenry · District 2 | 2 of 4 | $9,250,034 | $8,698,583D. Construction, Inc. | +6.3% |
| Sep 18, 2026 | 64V52 | 6RSWinnebago · District 2 | 1 of 3 | $2,930,601 | $2,930,601 | Won |
| Jul 31, 2026 | 66P22 | (ORCB)BRR-1Bureau · District 3 | 1 of 2 | $1,257,661 | $1,257,661 | Won |
| Jul 31, 2026 | 64T49 | (102BR)BRROgle · District 2 | 2 of 3 | $532,329 | $443,472Martin & Company Excavating | +20.0% |
| Jul 31, 2026 | 64V16 | (K-2)CGJo Daviess · District 2 | 2 of 5 | $56,921 | $45,940Law Excavating, Inc. | +23.9% |
| Jul 31, 2026 | 64T48 | (105BR-1)BRRWhiteside · District 2 | 2 of 3 | $558,681 | $523,502Martin & Company Excavating | +6.7% |
| Jun 12, 2026 | 64N73 | (20-1, 19Z)RS-7Stephenson · District 2 | 1 of 1 | $7,439,990 | $7,439,990 | Won |
| Jun 12, 2026 | 64S70 | (101, 101-1)RSStephenson · District 2 | 2 of 2 | $4,547,696 | $3,817,934Rock Road Companies, Inc. | +19.1% |
| Jun 12, 2026 | 64T07 | (116BR)&(117BR-1)BDROgle · District 2 | 2 of 2 | $749,768 | $747,738Martin & Company Excavating | +0.3% |
| Jun 12, 2026 | 64T46 | (115BR)BRRWhiteside · District 2 | 2 of 3 | $358,892 | $353,100Martin & Company Excavating | +1.6% |
| Jun 12, 2026 | 64T47 | (102BR-1)BRROgle · District 2 | 2 of 2 | $626,999 | $618,490Martin & Company Excavating | +1.4% |
| Jun 12, 2026 | 64T58 | (109BR)BRRStephenson · District 2 | 1 of 2 | $784,183 | $784,183 | Won |
| Jun 12, 2026 | 64V39 | ((19X-1)RS-1)PP&RSStephenson · District 2 | 1 of 1 | $2,734,393 | $2,734,393 | Won |
| Jun 12, 2026 | 64V42 | ((8Z&(32W&32WZ))RS&SWWhiteside · District 2 | 1 of 1 | $2,381,280 | $2,381,280 | Won |
| Jun 12, 2026 | 66N45 | (06-3HB)BRBureau · District 3 | 2 of 3 | $2,910,375 | $2,414,143D. Construction, Inc. | +20.6% |
| Apr 24, 2026 | 64L51 | 101RS-3Jodaviess · District 2 | 1 of 1 | $3,793,443 | $3,793,443 | Won |
| Apr 24, 2026 | 64U85 | (8R)PPLee · District 2 | 1 of 4 | $564,716 | $564,716 | Won |
| Apr 24, 2026 | 64T06 | ((141-3HB)&(141-3VB)BDROgle · District 2 | 2 of 2 | $4,373,796 | $3,168,316Martin & Company Excavating | +38.0% |
| Apr 24, 2026 | 64T42 | 177(-4HB(-1,-2,-3,-4)(2VB)BRRStephenson · District 2 | 2 of 2 | $4,367,658 | $4,082,943Martin & Company Excavating | +7.0% |
| Apr 24, 2026 | 64T73 | 101RSLee · District 2 | 2 of 2 | $2,124,405 | $1,988,394Martin & Company Excavating | +6.8% |
| Apr 24, 2026 | 64U89 | (17R-1BR-1)BDRWinnebago · District 2 | 3 of 3 | $774,829 | $522,276Martin & Company Excavating | +48.4% |
| Apr 24, 2026 | 64U90 | (102BR-4)BJRWinnebago · District 2 | 2 of 3 | $1,968,941 | $1,670,253Martin & Company Excavating | +17.9% |
| Apr 24, 2026 | 66R69 | (22B)BRRBureau · District 3 | 4 of 4 | $612,739 | $421,787Gensini Excavating, Inc. | +45.3% |
| Apr 24, 2026 | 85793 | 25-00358-00-RSLee · District 2 | 3 of 3 | $1,907,713 | $1,489,962Martin & Company Excavating | +28.0% |
| Apr 24, 2026 | 85797 | 25-00365-00-BRLee · District 2 | 3 of 3 | $802,244 | $582,765Martin & Company Excavating | +37.7% |
| Apr 24, 2026 | 85798 | 18-00661-00-BRWinnebago · District 2 | 2 of 2 | $5,751,358 | $4,934,200ICC Group Inc. | +16.6% |
| Feb 27, 2026 | 64T23 | (141-1)PPOgle · District 2 | 4 of 5 | $151,085 | $138,615Martin & Company Excavating | +9.0% |
| Feb 27, 2026 | 64J38 | (32-2)RS-1Whiteside · District 2 | 1 of 2 | $2,673,307 | $2,673,307 | Won |
| Feb 27, 2026 | 64R72 | (15X)RC&5RSWinnebago · District 2 | 1 of 2 | $21,418,706 | $21,418,706 | Won |
| Feb 27, 2026 | 64S71 | 106RSCarroll · District 2 | 1 of 1 | $7,058,363 | $7,058,363 | Won |
| Jan 16, 2026 | 64T05 | (101BR-2)BDROgle · District 2 | 2 of 2 | $768,239 | $460,374Martin & Company Excavating | +66.9% |
| Jan 16, 2026 | 64T96 | (111BR-1)BDRLee · District 2 | 4 of 4 | $502,162 | $369,059Martin & Company Excavating | +36.1% |
| Jan 16, 2026 | 64U20 | (195-3&(110,195-3))PP&RSWhiteside · District 2 | 1 of 2 | $5,204,514 | $5,204,514 | Won |
| Jan 16, 2026 | 64U21 | 75 CIR&RSLee · District 2 | 2 of 2 | $4,841,223 | $4,655,130Martin & Company Excavating | +4.0% |
| Jan 16, 2026 | 85786 | 18-00237-00-BRWhiteside · District 2 | 2 of 3 | $3,327,889 | $2,834,678Martin & Company Excavating | +17.4% |
| Nov 7, 2025 | 64R26 | (102VBR)BDRJodaviess · District 2 | 1 of 2 | $732,334 | $732,334 | Won |
| Nov 7, 2025 | 46944 | HC BRIDGE REPAIRWhiteside · District 2 | 2 of 3 | $1,193,271 | $1,029,566Martin & Company Excavating | +15.9% |
| Nov 7, 2025 | 85779 | 19-00137-00-BRWhiteside · District 2 | 2 of 3 | $1,859,068 | $1,699,166Martin & Company Excavating | +9.4% |
| Nov 7, 2025 | 85785 | 23-00291-00-BTRock Island · District 2 | 5 of 6 | $5,589,787 | $5,092,254Gensini Excavating, Inc. | +9.8% |
| Nov 7, 2025 | 87843 | 21-P4006-03-BTDekalb · District 3 | 3 of 4 | $1,907,743 | $1,580,482Martin & Company Excavating | +20.7% |
| Sep 19, 2025 | 64P02 | D2 SW 2020-1Ogle · District 2 | 4 of 5 | $1,533,258 | $1,269,521Stenstrom Excavation & Blac… | +20.8% |
| Sep 19, 2025 | 85764 | 18-00655-00-BRWinnebago · District 2 | 1 of 4 | $6,340,772 | $6,340,772 | Won |
| Aug 1, 2025 | 64U53 | (17R)PPWhiteside · District 2 | 2 of 2 | $331,993 | $303,113Martin & Company Excavating | +9.5% |
| Aug 1, 2025 | 64U79 | (22,107)AStephenson · District 2 | 3 of 3 | $907,318 | $652,317Fischer Excavating, Inc. | +39.1% |
| Aug 1, 2025 | 68510 | (37-24HVB)BRHenry · District 4 | 2 of 2 | $16,500,000 | $15,796,785IHC Construction Companies,… | +4.5% |
| Jun 13, 2025 | 64T97 | (141-1HB)BDROgle · District 2 | 4 of 4 | $440,284 | $315,487Martin & Company Excavating | +39.6% |
| Jun 13, 2025 | 64T98 | (107BR-1)BDRStephenson · District 2 | 2 of 2 | $918,613 | $758,588Martin & Company Excavating | +21.1% |
| Jun 13, 2025 | 64T99 | (101BR-3)BDRStephenson · District 2 | 2 of 2 | $471,683 | $394,921Martin & Company Excavating | +19.4% |
| Jun 13, 2025 | 64U00 | (1-1HB)BDRWinnebago · District 2 | 2 of 3 | $645,718 | $485,744Martin & Company Excavating | +32.9% |
| Jun 13, 2025 | 64U41 | (12R)CJSLee · District 2 | 2 of 2 | $75,132 | $58,245Martin & Company Excavating | +29.0% |
| Jun 13, 2025 | 64P13 | (2,3,4)RS-7 & 115SWOgle · District 2 | 2 of 2 | $4,594,373 | $4,385,762Martin & Company Excavating | +4.8% |
| Jun 13, 2025 | 64U24 | 101PP&RSStephenson · District 2 | 1 of 1 | $2,355,396 | $2,355,396 | Won |
| Jun 13, 2025 | 66K63 | (125BR)BRDekalb · District 3 | 1 of 3 | $3,866,805 | $3,866,805 | Won |
| Jun 13, 2025 | 64S25 | (201-1HB)BDRWinnebago · District 2 | 3 of 4 | $1,332,919 | $1,028,867Martin & Company Excavating | +29.6% |
| Jun 13, 2025 | 64U19 | 116PP&RSOgle · District 2 | 1 of 2 | $5,307,008 | $5,307,008 | Won |
| Jun 13, 2025 | 64U22 | 4PP&RSOgle · District 2 | 1 of 2 | $5,308,846 | $5,308,846 | Won |
| Apr 25, 2025 | 64U23 | 106 PP&RSStephenson · District 2 | 2 of 2 | $4,451,475 | $4,096,256Rock Road Companies, Inc. | +8.7% |
| Apr 25, 2025 | 64U31 | (3,4)RSCarroll · District 2 | 2 of 2 | $4,548,432 | $4,435,198Martin & Company Excavating | +2.6% |
| Apr 25, 2025 | 66M48 | 122V-BR1Bureau · District 3 | 2 of 3 | $2,725,904 | $1,939,442D. Construction, Inc. | +40.6% |
| Apr 25, 2025 | 85773 | 22-00351-00-BRLee · District 2 | 2 of 3 | $1,260,971 | $950,396Martin & Company Excavating | +32.7% |
| Apr 25, 2025 | 85777 | 22-00260-00-RSWhiteside · District 2 | 1 of 3 | $1,439,241 | $1,439,241 | Won |
| Mar 7, 2025 | 64N01 | (195-3)RS & BDRWhiteside · District 2 | 1 of 1 | $26,883,771 | $26,883,771 | Won |
| Mar 7, 2025 | 64T20 | (40BR-3)BDRHenry · District 2 | 3 of 3 | $388,750 | $263,536Martin & Company Excavating | +47.5% |
| Mar 7, 2025 | 64U30 | (21,21R)RSStephenson · District 2 | 1 of 2 | $1,614,512 | $1,614,512 | Won |
| Mar 7, 2025 | 64S33 | (106 BR)BDRStephenson · District 2 | 1 of 3 | $447,987 | $447,987 | Won |
| Mar 7, 2025 | 64T81 | (17R)PPWhiteside · District 2 | 1 of 3 | $218,027 | $218,027 | Won |
| Jan 17, 2025 | 64M10 | 112CRLee · District 2 | 4 of 4 | $892,570 | $746,263Martin & Company Excavating | +19.6% |
| Jan 17, 2025 | 64S59 | (30,30Y)DR 7 PPJodaviess · District 2 | 3 of 4 | $645,425 | $460,622G. M. Sipes Construction, I… | +40.1% |
| Jan 17, 2025 | 66P33 | (06-2HB-4)BRRBureau · District 3 | 2 of 2 | $596,679 | $439,369D. Construction, Inc. | +35.8% |
| Jan 17, 2025 | 85758 | 19-06126-00-BRCarroll · District 2 | 2 of 4 | $3,298,536 | $3,005,217Sjostrom & Sons, Inc. | +9.8% |
| Nov 8, 2024 | 64P06 | 111BRWinnebago · District 2 | 2 of 3 | $4,298,209 | $3,998,708Sjostrom & Sons, Inc. | +7.5% |
| Nov 8, 2024 | 85766 | 22-00162-00-RSJo Daviess · District 2 | 1 of 1 | $2,153,129 | $2,153,129 | Won |
| Nov 8, 2024 | 68801 | (102)BR-1Mercer · District 4 | 3 of 3 | $4,025,729 | $3,450,000Brandt Construction Co. | +16.7% |
| Nov 8, 2024 | 85743 | 17-00152-00-BTWhiteside · District 2 | 2 of 4 | $6,435,527 | $6,232,140Gensini Excavating, Inc. | +3.3% |
| Sep 20, 2024 | 64S29 | (101(V-BR & R-2)BDRLee · District 2 | 1 of 3 | $1,009,879 | $1,009,879 | Won |
| Sep 20, 2024 | 85762 | 22-00183-00-BRLee · District 2 | 1 of 2 | $14,126,560 | $14,126,560 | Won |
| Aug 2, 2024 | 64T21 | (195-2HB)BDRWhiteside · District 2 | 1 of 3 | $789,178 | $789,178 | Won |
| Aug 2, 2024 | 85761 | 20-00102-00-PVCarroll · District 2 | 3 of 3 | $6,989,994 | $6,126,569Martin & Company Excavating | +14.1% |
| Aug 2, 2024 | 87848 | 20-01009-01-BRDekalb · District 3 | 3 of 6 | $456,847 | $397,900McCarthy Improvement Company | +14.8% |
| Jun 14, 2024 | 64R17 | 104RS-6Ogle · District 2 | 1 of 2 | $2,468,747 | $2,468,747 | Won |
| Jun 14, 2024 | 64T17 | (16,17,18)RS &16RSCarroll, Ogle · District 2 | 1 of 2 | $2,854,652 | $2,854,652 | Won |
| Jun 14, 2024 | 64T19 | ((9,10)R)RSOgle · District 2 | 2 of 3 | $2,511,082 | $2,139,439Rock Road Companies, Inc. | +17.4% |
| Jun 14, 2024 | 64T44 | (110,111)SROgle · District 2 | 1 of 4 | $223,592 | $223,592 | Won |
| Jun 14, 2024 | 66K66 | [(06-2B-1) & (06-2HB-1)]BRBureau · District 3 | 1 of 3 | $24,206,955 | $24,206,955 | Won |
| Jun 14, 2024 | 68E35 | (48-29B)BRKnox · District 4 | 1 of 4 | $14,446,748 | $14,446,748 | Won |
| Jun 14, 2024 | 85760 | 20-00116-00-RSOgle · District 2 | 1 of 4 | $1,545,544 | $1,545,544 | Won |
| Jun 14, 2024 | 87818 | 19-17129-00-BRDekalb · District 3 | 2 of 3 | $1,329,886 | $1,281,196Sjostrom & Sons, Inc. | +3.8% |
| Jun 14, 2024 | 87722 | 14-00009-00-BRDekalb · District 3 | 1 of 4 | $3,263,762 | $3,263,762 | Won |
| Apr 26, 2024 | 64S65 | (110BR-1)BRWhiteside · District 2 | 3 of 5 | $454,722 | $402,242Martin & Company Excavating | +13.0% |
| Apr 26, 2024 | 64T15 | (115RS)RSWhiteside, Ogle · District 2 | 2 of 2 | $3,562,707 | $3,350,526Martin & Company Excavating | +6.3% |
| Apr 26, 2024 | 85757 | 23-00355-00-RSLee · District 2 | 2 of 2 | $1,175,728 | $1,065,955Martin & Company Excavating | +10.3% |
| Apr 26, 2024 | 85759 | 22-0261-00-RSWhiteside · District 2 | 1 of 2 | $979,286 | $979,286 | Won |
| Apr 26, 2024 | 87815 | 07-12125-00-BRBureau · District 3 | 4 of 5 | $620,184 | $499,288Curnyn Construction Co. | +24.2% |
| Apr 26, 2024 | 64S61 | (177-4-2)BDRStephenson · District 2 | 1 of 3 | $449,840 | $449,840 | Won |
| Apr 26, 2024 | 64L95 | (W-15D,115)RS-4Winnebago · District 2 | 4 of 4 | $2,242,840 | $1,979,788Rock Road Companies, Inc. | +13.3% |
| Apr 26, 2024 | 64S27 | (195(1B-1,1VB,1HB-5,2B))BDRWhiteside · District 2 | 2 of 2 | $4,395,765 | $4,099,617Martin & Company Excavating | +7.2% |
| Apr 26, 2024 | 64S30 | (102 BR-4)BDRLee · District 2 | 2 of 3 | $750,345 | $585,814Martin & Company Excavating | +28.1% |
| Apr 26, 2024 | 64S38 | 109 RS-1Ogle · District 2 | 4 of 4 | $259,741 | $201,632Curran Contracting Company | +28.8% |
| Apr 26, 2024 | 64S55 | D2 PP 2024-01Jodaviess · District 2 | 1 of 2 | $442,965 | $442,965 | Won |
| Mar 8, 2024 | 64S62 | (195-2HVB)BRWhiteside · District 2 | 3 of 4 | $378,744 | $341,096Martin & Company Excavating | +11.0% |
| Mar 8, 2024 | 64S66 | (37BR-2)&(102B-1R-1)Ogle, Winnebago · District 2 | 2 of 5 | $485,611 | $392,380Martin & Company Excavating | +23.8% |
| Mar 8, 2024 | 64B39 | 114BR-1 & 114BR-2Lee · District 2 | 3 of 3 | $5,212,881 | $3,724,770Martin & Company Excavating | +40.0% |
| Mar 8, 2024 | 64S63 | (195-3HB-3&195-3HB2)BRWhiteside · District 2 | 2 of 5 | $514,848 | $385,049ERA-Valdivia Contractors, I… | +33.7% |
| Mar 8, 2024 | 64P41 | (101,102,135)RSBureau, Whiteside · District 2 | 2 of 2 | $7,411,208 | $6,978,085Martin & Company Excavating | +6.2% |
| Mar 8, 2024 | 85753 | 22-00168-00-BRHenry · District 2 | 3 of 4 | $870,034 | $718,769Curnyn Construction Co. | +21.0% |
| Mar 8, 2024 | 85756 | 20-00331-00-RSOgle · District 2 | 1 of 2 | $1,059,060 | $1,059,060 | Won |
| Jan 19, 2024 | 64P11 | (103,104)RS-1Jodaviess · District 2 | 1 of 3 | $3,414,665 | $3,414,665 | Won |
| Jan 19, 2024 | 64S31 | (195-3B,195-3HB)BDRWhiteside · District 2 | 2 of 3 | $2,494,481 | $1,822,997Martin & Company Excavating | +36.8% |
| Jan 19, 2024 | 68D83 | 48[(26VB)BY,BY-1]BRRKnox · District 4 | 1 of 2 | $2,637,099 | $2,637,099 | Won |
| Jan 19, 2024 | 85748 | 21-01132-00-BRStephenson · District 2 | 3 of 3 | $495,810 | $474,974Sjostrom & Sons, Inc. | +4.4% |
| Jan 19, 2024 | 89756 | 18-00113-00-BRMercer · District 4 | 1 of 2 | $812,313 | $812,313 | Won |
| Nov 17, 2023 | 64918 | 108 RS-3Carroll · District 2 | 2 of 3 | $1,610,110 | $1,429,025Martin & Company Excavating | +12.7% |
| Nov 17, 2023 | 64K73 | 77-1BRWinnebago · District 2 | 1 of 4 | $25,360,046 | $25,360,046 | Won |
| Nov 17, 2023 | 64S39 | (195-3HB-4)BDRWhiteside · District 2 | 2 of 5 | $1,624,617 | $1,375,082Martin & Company Excavating | +18.1% |
| Nov 17, 2023 | 64S40 | (195-3HB-6)BDRWhiteside · District 2 | 2 of 3 | $1,553,827 | $1,248,487Martin & Company Excavating | +24.5% |
| Sep 22, 2023 | 64S50 | (81-1B)BDRRock Island · District 2 | 1 of 6 | $953,837 | $953,837 | Won |
| Sep 22, 2023 | 68804 | (103)BR-1Mercer · District 4 | 2 of 2 | $2,902,169 | $2,820,000Brandt Construction Co. | +2.9% |
| Aug 4, 2023 | 64K08 | 15R-1Whiteside · District 2 | 5 of 6 | $5,712,598 | $5,087,535Fischer Excavating, Inc. | +12.3% |
| Jun 16, 2023 | 64R55 | (106 BR)BDR & (105VB-2)BDRCarroll · District 2 | 1 of 3 | $1,495,293 | $1,495,293 | Won |
| Jun 16, 2023 | 64S03 | (161-1HB-3)BJRRock Island · District 2 | 2 of 6 | $49,184 | $42,950Path Construction Company, … | +14.5% |
| Jun 16, 2023 | 64S04 | (195-2HB)BJRWhiteside · District 2 | 2 of 3 | $1,020,534 | $925,041Martin & Company Excavating | +10.3% |
| Jun 16, 2023 | 64S08 | (161-1HB-5)BJRRock Island · District 2 | 1 of 5 | $125,695 | $125,695 | Won |
| Jun 16, 2023 | 85745 | 20-15134-00-BRStephenson · District 2 | 1 of 4 | $309,936 | $309,936 | Won |
| Jun 16, 2023 | 64P63 | (107B-1)BDR&(107VB-2)BDRWhiteside · District 2 | 1 of 2 | $1,610,549 | $1,610,549 | Won |
| Jun 16, 2023 | 64S09 | (161-1HB-9)BJRRock Island · District 2 | 1 of 5 | $187,707 | $187,707 | Won |
| Apr 28, 2023 | 64P85 | (161-1B-1,2&161-1HB-9)BDRRock Island · District 2 | 1 of 1 | $3,922,476 | $3,922,476 | Won |
| Apr 28, 2023 | 85734 | 17-00228-00-BRWhiteside · District 2 | 2 of 2 | $2,263,991 | $2,072,031Martin & Company Excavating | +9.3% |
| Apr 28, 2023 | 85742 | 21-00191-00-BRStephenson · District 2 | 1 of 3 | $554,922 | $554,922 | Won |
| Mar 10, 2023 | 64S15 | (161-1HB-7)BDRRock Island · District 2 | 1 of 3 | $421,357 | $421,357 | Won |
| Mar 10, 2023 | 64S22 | D2 MAINT YD 2023-02Lee · District 2 | 1 of 3 | $219,492 | $219,492 | Won |
| Mar 10, 2023 | 64S24 | (161-1HB-4)BJRRock Island · District 2 | 3 of 4 | $625,526 | $533,147General Constructors Inc. o… | +17.3% |
| Mar 10, 2023 | 85733 | 20-00330-00-RSOgle · District 2 | 1 of 2 | $940,932 | $940,932 | Won |
| Mar 10, 2023 | 85737 | 21-00258-00-RSWhiteside · District 2 | 1 of 1 | $1,297,131 | $1,297,131 | Won |
| Jan 20, 2023 | 64R48 | (11BR-4)BDRCarroll · District 2 | 2 of 5 | $619,209 | $606,592Sjostrom & Sons, Inc. | +2.1% |
| Jan 20, 2023 | 64R49 | (101BR)BDRBoone · District 2 | 3 of 3 | $667,987 | $586,034Sjostrom & Sons, Inc. | +14.0% |
| Jan 20, 2023 | 64R54 | (111 VBR)BDRLee · District 2 | 1 of 4 | $699,832 | $699,832 | Won |
| Jan 20, 2023 | 68G91 | 112B[BR;BR(1,2,3)]BJR,BDRKnox · District 4 | 3 of 3 | $2,147,202 | $1,898,891Path Construction Company, … | +13.1% |
| Jan 20, 2023 | 85700 | 17-00178-00-BTLee · District 2 | 2 of 2 | $5,248,502 | $4,313,104Martin & Company Excavating | +21.7% |
| Jan 20, 2023 | 85730 | 19-00181-00-SWLee · District 2 | 2 of 2 | $2,410,061 | $2,010,320Martin & Company Excavating | +19.9% |
| Jan 20, 2023 | 85731 | 20-00326-00-BROgle · District 2 | 2 of 3 | $3,109,433 | $2,993,599Sjostrom & Sons, Inc. | +3.9% |
| Jan 20, 2023 | 85732 | 19-00113-00-BRBoone · District 2 | 1 of 4 | $1,640,467 | $1,640,467 | Won |
| Nov 18, 2022 | 64G68 | 4HBR-3Winnebago · District 2 | 3 of 4 | $8,916,975 | $7,982,288Sjostrom & Sons, Inc. | +11.7% |
| Nov 18, 2022 | 64H57 | 16BR-1Ogle · District 2 | 1 of 3 | $3,263,935 | $3,263,935 | Won |
| Nov 18, 2022 | 64R12 | (39BR)BDROgle · District 2 | 1 of 6 | $410,622 | $410,622 | Won |
| Nov 18, 2022 | 64R51 | (104 BY-R)BDRCarroll · District 2 | 1 of 3 | $694,355 | $694,355 | Won |
| Nov 18, 2022 | 66M74 | (140BR)BRRBureau · District 3 | 2 of 2 | $633,359 | $546,258D. Construction, Inc. | +15.9% |
| Nov 18, 2022 | 85728 | 20-00381-00-DRRock Island · District 2 | 2 of 3 | $1,046,173 | $988,253General Constructors Inc. o… | +5.9% |
| Nov 18, 2022 | 64G66 | (110)C&RS-3Whiteside · District 2 | 1 of 2 | $7,298,721 | $7,298,721 | Won |
| Nov 18, 2022 | 64R98 | D2 PP 2023-01Stephenson · District 2 | 7 of 7 | $911,721 | $558,348Triggi Construction, Inc. | +63.3% |
| Aug 5, 2022 | 64R13 | (106BR-2)BDRStephenson · District 2 | 1 of 3 | $392,203 | $392,203 | Won |
| Aug 5, 2022 | 64R50 | (14 BD-1)BDRBoone · District 2 | 1 of 6 | $386,559 | $386,559 | Won |
| Aug 5, 2022 | DI033 | DIXON MUNICIPALLee · District 2 | 2 of 2 | $1,036,514 | $902,009Martin & Company Excavating | +14.9% |
| Jul 15, 2022 | 64P42 | 25RS-7Jo Daviess · District 2 | 1 of 1 | $4,639,685 | $4,639,685 | Won |
| Jul 15, 2022 | 68G71 | (94-16HB-1)BDR,BJR,BRRWarren · District 4 | 2 of 2 | $1,131,504 | $1,033,550Brandt Construction Co. | +9.5% |
| Jun 17, 2022 | 64P95 | 110NWhiteside · District 2 | 1 of 2 | $145,965 | $145,965 | Won |
| Jun 17, 2022 | 66M02 | (125BR)BRRDekalb · District 3 | 4 of 5 | $491,505 | $370,683Sjostrom & Sons, Inc. | +32.6% |
| Jun 17, 2022 | 85709 | 18-00136-00-FPWhiteside · District 2 | 2 of 3 | $2,753,264 | $2,521,018Martin & Company Excavating | +9.2% |
| Jun 17, 2022 | 85722 | 20-06122-00-BRStephenson · District 2 | 3 of 4 | $359,122 | $342,370Curnyn Construction Co. | +4.9% |
| Jun 17, 2022 | 87778 | 18-00267-00-BRBureau · District 3 | 3 of 3 | $1,316,921 | $961,378Gensini Excavating, Inc. | +37.0% |
| Jun 17, 2022 | 87779 | 18-00193-00-BRDekalb · District 3 | 3 of 4 | $5,935,704 | $5,253,737Herlihy Mid-Continent Compa… | +13.0% |
| Jun 17, 2022 | 89760 | 17-00137-00-BRWarren · District 4 | 2 of 3 | $2,395,085 | $2,275,756County Contractors, Inc. | +5.2% |
| Jun 17, 2022 | 64K62 | (103,104)CRJo Daviess · District 2 | 1 of 1 | $2,281,460 | $2,281,460 | Won |
| Jun 17, 2022 | 64N77 | D2 SW 2019-3Whiteside · District 2 | 1 of 2 | $976,105 | $976,105 | Won |
| Jun 17, 2022 | 64P15 | 111RS-6Whiteside · District 2 | 1 of 1 | $3,018,594 | $3,018,594 | Won |
| Apr 29, 2022 | 64J47 | (7B)BRRWhiteside · District 2 | 1 of 1 | $987,610 | $987,610 | Won |
| Apr 29, 2022 | 64M17 | 15CR&SRCarroll · District 2 | 2 of 3 | $693,462 | $648,371Martin & Company Excavating | +7.0% |
| Apr 29, 2022 | 64N71 | (3BR)BRR-1Rock Island · District 2 | 2 of 2 | $2,568,493 | $1,458,043White Construction LLC | +76.2% |
| Apr 29, 2022 | 64R14 | (201-2HB)BDRWinnebago · District 2 | 3 of 7 | $789,522 | $750,819Martin & Company Excavating | +5.2% |
| Apr 29, 2022 | 66K73 | (06-1HB-2 & 06-2HB)BRBureau · District 3 | 2 of 2 | $7,599,567 | $7,246,218D. Construction, Inc. | +4.9% |
| Apr 29, 2022 | 85724 | 20-00253-00-RSWhiteside · District 2 | 1 of 3 | $1,611,487 | $1,611,487 | Won |
| Apr 29, 2022 | 85725 | 17-00654-00-BRWinnebago · District 2 | 1 of 5 | $987,871 | $987,871 | Won |
| Mar 11, 2022 | 64D78 | 9R & 9RS-3Whiteside · District 2 | 3 of 5 | $6,740,338 | $6,345,198Martin & Company Excavating | +6.2% |
| Mar 11, 2022 | 64R10 | (17R-1, 17R-3)RSWinnebago · District 2 | 1 of 4 | $1,629,019 | $1,629,019 | Won |
| Mar 11, 2022 | 64R33 | (102BR)RSOgle · District 2 | 2 of 5 | $263,165 | $238,027Martin & Company Excavating | +10.6% |
| Mar 11, 2022 | 64R34 | D2 BDR 2022-1Ogle · District 2 | 2 of 8 | $411,046 | $352,324Martin & Company Excavating | +16.7% |
| Mar 11, 2022 | 64R43 | (B)BDRWhiteside · District 2 | 3 of 6 | $299,501 | $239,261Path Construction Company, … | +25.2% |
| Mar 11, 2022 | 66L74 | 50(5A&5B)BJR,BRRLasalle · District 3 | 2 of 4 | $1,194,155 | $1,066,495D. Construction, Inc. | +12.0% |
| Mar 11, 2022 | 68F73 | [(48-27HB)BY,BY-1]BDR,BJR,BRRKnox · District 4 | 2 of 2 | $1,346,259 | $1,167,000Brandt Construction Co. | +15.4% |
| Mar 11, 2022 | 85714 | 17-00318-00-RSOgle · District 2 | 4 of 4 | $743,119 | $662,789Martin & Company Excavating | +12.1% |
| Mar 11, 2022 | 85720 | 18-00320-00-RSOgle · District 2 | 5 of 5 | $391,503 | $353,666Martin & Company Excavating | +10.7% |
| Mar 11, 2022 | WH016 | WHITESIDE COUNTYWhiteside · District 2 | 1 of 2 | $598,055 | $598,055 | Won |
| Jan 21, 2022 | 66J00 | (18B)BRLasalle · District 3 | 2 of 3 | $2,271,782 | $1,835,069D. Construction, Inc. | +23.8% |
| Jan 21, 2022 | 85715 | 19-00671-00-BRWinnebago · District 2 | 6 of 7 | $462,168 | $393,893Sjostrom & Sons, Inc. | +17.3% |
| Jan 21, 2022 | 85717 | 19-00187-00-BRStephenson · District 2 | 5 of 7 | $718,757 | $534,166M & M Concrete, Inc. | +34.6% |
| Jan 21, 2022 | 85718 | 20-00345-00-RSLee · District 2 | 2 of 2 | $1,055,851 | $988,644Martin & Company Excavating | +6.8% |
| Jan 21, 2022 | 64J63 | 110TStephenson · District 2 | 3 of 5 | $1,218,791 | $1,044,240Martin & Company Excavating | +16.7% |
| Jan 21, 2022 | 64N03 | (101-3B)DStephenson · District 2 | 1 of 3 | $1,696,103 | $1,696,103 | Won |
| Jan 21, 2022 | 64N48 | 130CRBoone · District 2 | 2 of 6 | $1,150,806 | $1,035,672Sjostrom & Sons, Inc. | +11.1% |
| Jan 21, 2022 | 64P16 | (23,24)RS-6Jo Daviess · District 2 | 1 of 1 | $1,451,862 | $1,451,862 | Won |
| Jan 21, 2022 | 64P88 | (141-2HB-1)BDROgle · District 2 | 2 of 6 | $929,474 | $782,871Martin & Company Excavating | +18.7% |
| Jan 21, 2022 | 64R31 | (81-3B-1)BJRRock Island · District 2 | 2 of 6 | $581,044 | $550,210General Constructors Inc. o… | +5.6% |
| Jan 21, 2022 | 64R32 | (18BR)RSStephenson · District 2 | 2 of 3 | $137,737 | $127,408Martin & Company Excavating | +8.1% |
| Jan 21, 2022 | 64R36 | RA RS-01Carroll · District 2 | 1 of 3 | $48,229 | $48,229 | Won |
| Nov 5, 2021 | 64H58 | 10BR-5Jo Daviess · District 2 | 2 of 3 | $2,902,599 | $2,878,168Sjostrom & Sons, Inc. | +0.8% |
| Nov 5, 2021 | 64M41 | (110, 111)CRLee · District 2 | 2 of 4 | $1,740,547 | $1,566,058Fischer Excavating, Inc. | +11.1% |
| Nov 5, 2021 | 64R27 | D2 PP 2022-2Whiteside · District 2 | 1 of 4 | $595,141 | $595,141 | Won |
| Nov 5, 2021 | 66H26 | (135B-1)BRBureau · District 3 | 1 of 5 | $2,548,314 | $2,548,314 | Won |
| Nov 5, 2021 | 66J01 | (06-3B)BRBureau · District 3 | 3 of 4 | $2,936,019 | $2,541,583D. Construction, Inc. | +15.5% |
| Nov 5, 2021 | 87742 | 18-09808-00-BRLasalle · District 3 | 4 of 4 | $905,984 | $815,302Riber Construction, Inc. | +11.1% |
| Nov 5, 2021 | 87767 | 17-06123-00-BRDekalb · District 3 | 2 of 6 | $490,168 | $456,936Sjostrom & Sons, Inc. | +7.3% |
| Sep 17, 2021 | 64L75 | 106VBR-DOgle · District 2 | 1 of 7 | $2,189,925 | $2,189,925 | Won |
| Sep 17, 2021 | 64N63 | 43 RSJodaviess · District 2 | 1 of 1 | $1,226,553 | $1,226,553 | Won |
| Sep 17, 2021 | 64R22 | 8SFYWhiteside · District 2 | 1 of 1 | $139,824 | $139,824 | Won |
| Sep 17, 2021 | 89795 | 20-00130-14-BRFulton · District 4 | 4 of 5 | $1,609,167 | $1,359,595Stark Excavating, Inc. | +18.4% |
| Jul 30, 2021 | 64M90 | 109RS-2Whiteside · District 2 | 2 of 3 | $2,805,134 | $2,757,015Valley Construction Co. | +1.7% |
| Jul 30, 2021 | 64P53 | (110V-BR)BDRWhiteside · District 2 | 1 of 4 | $663,345 | $663,345 | Won |
| Jul 30, 2021 | 64P92 | (17R-1VBR)BDRWhiteside · District 2 | 1 of 4 | $646,160 | $646,160 | Won |
| Jul 30, 2021 | 68F71 | [(104B)BR]BJRWarren · District 4 | 1 of 3 | $434,766 | $434,766 | Won |
| Jul 30, 2021 | 68F78 | (23-BR)BJR,BP,BRRMercer · District 4 | 1 of 3 | $429,504 | $429,504 | Won |
| Jul 30, 2021 | 85713 | 20-03121-00-BRBoone · District 2 | 2 of 5 | $476,786 | $409,085Sjostrom & Sons, Inc. | +16.5% |
| Jun 11, 2021 | 64M18 | (1-1,1,2)RS-2Winnebago · District 2 | 3 of 3 | $13,650,569 | $12,388,900William Charles Constructio… | +10.2% |
| Jun 11, 2021 | 64N38 | (32-2-1)RWhiteside · District 2 | 3 of 3 | $1,831,049 | $1,787,878Fischer Excavating, Inc. | +2.4% |
| Jun 11, 2021 | 64N49 | (1-2)RWRWinnebago · District 2 | 5 of 5 | $1,296,968 | $862,466Martam Construction Incorpo… | +50.4% |
| Jun 11, 2021 | 64N50 | (1,2)SLPCarroll · District 2 | 1 of 6 | $341,342 | $341,342 | Won |
| Jun 11, 2021 | 64P49 | 104QJodaviess · District 2 | 2 of 2 | $64,555 | $61,502Brandt Construction Co. | +5.0% |
| Jun 11, 2021 | 64P86 | D2 MAINT YARD 2021-1Whiteside · District 2 | 1 of 5 | $234,765 | $234,765 | Won |
| Jun 11, 2021 | 64P94 | (195-3B-4)BDRWhiteside · District 2 | 1 of 4 | $1,444,158 | $1,444,158 | Won |
| Jun 11, 2021 | 66L02 | (50-8HB)I-1Lasalle · District 3 | 3 of 3 | $1,394,615 | $1,081,507D. Construction, Inc. | +29.0% |
| Apr 23, 2021 | 64P29 | (102,103)RS-4Winnebago · District 2 | 4 of 4 | $5,133,405 | $4,379,698Rock Road Companies, Inc. | +17.2% |
| Apr 23, 2021 | 64P30 | (73,74)RS-6Lee · District 2 | 4 of 4 | $4,393,083 | $4,129,760Advanced Asphalt Company | +6.4% |
| Apr 23, 2021 | 64P65 | (110BR-2)BJRWhiteside · District 2 | 2 of 6 | $181,278 | $147,606Martin & Company Excavating | +22.8% |
| Apr 23, 2021 | 64P66 | (105VB-3)BJRCarroll · District 2 | 2 of 6 | $191,154 | $187,212Martin & Company Excavating | +2.1% |
| Apr 23, 2021 | 64P74 | D2 RS 2021-2Whiteside · District 2 | 2 of 2 | $445,290 | $438,325Martin & Company Excavating | +1.6% |
| Apr 23, 2021 | 66L54 | (116R-2BR-1)BRRDekalb · District 3 | 6 of 8 | $299,803 | $250,265Martin & Company Excavating | +19.8% |
| Apr 23, 2021 | 85686 | 17-23125-00-BRJo Daviess · District 2 | 1 of 3 | $1,542,120 | $1,542,120 | Won |
| Apr 23, 2021 | 85705 | 19-00245-00-RSWhiteside · District 2 | 1 of 3 | $1,147,959 | $1,147,959 | Won |
| Apr 23, 2021 | 85711 | 19-16124-00-BRStephenson · District 2 | 1 of 3 | $414,633 | $414,633 | Won |
| Apr 23, 2021 | 87662 | 05-00210-00-BRDekalb · District 3 | 3 of 4 | $1,192,912 | $1,041,745Martin & Company Excavating | +14.5% |
| Apr 23, 2021 | 87739 | 15-12119-01-BRDekalb · District 3 | 2 of 8 | $707,042 | $693,852Riber Construction, Inc. | +1.9% |
| Apr 23, 2021 | 87764 | 12-00241-00-BRBureau · District 3 | 5 of 5 | $452,837 | $338,614D. Construction, Inc. | +33.7% |
| Apr 23, 2021 | 61G94 | 18-00490-00-BRMchenry · District 1 | 4 of 7 | $1,617,059 | $1,545,703Lorig Construction Company | +4.6% |
| Apr 23, 2021 | 64G99 | 101RS-2Ogle · District 2 | 1 of 2 | $1,497,763 | $1,497,763 | Won |
| Apr 23, 2021 | 64M91 | (31,30,8)RSLee · District 2 | 2 of 2 | $2,060,949 | $2,016,252Martin & Company Excavating | +2.2% |
| Mar 5, 2021 | 64M35 | D2 SW 2017-1Lee · District 2 | 3 of 6 | $419,352 | $358,849Stenstrom Excavation & Blac… | +16.9% |
| Mar 5, 2021 | 64P64 | (6B)BJRWinnebago · District 2 | 3 of 7 | $300,115 | $284,386Path Construction Company, … | +5.5% |
| Mar 5, 2021 | 64P81 | D2 PP 2021-4Whiteside · District 2 | 2 of 4 | $380,743 | $362,456G. M. Sipes Construction, I… | +5.0% |
| Mar 5, 2021 | 85704 | 16-00620-00-BRWinnebago · District 2 | 1 of 3 | $4,678,451 | $4,678,451 | Won |
| Mar 5, 2021 | 85707 | 17-00317-00-RSOgle · District 2 | 5 of 5 | $1,124,499 | $892,032William Charles Constructio… | +26.1% |
| Mar 5, 2021 | 85710 | 20-00344-00-RSLee · District 2 | 4 of 4 | $705,319 | $626,028Rock Road Companies, Inc. | +12.7% |
| Mar 5, 2021 | RC010 | ROCHELLE MUNICIPALOgle · District 2 | 7 of 7 | $1,362,895 | $899,968Sjostrom & Sons, Inc. | +51.4% |
| Mar 5, 2021 | FR044 | ALBERTUSStephenson · District 2 | 3 of 3 | $253,226 | $235,202Martin & Company Excavating | +7.7% |
| Jan 15, 2021 | 64N02 | 29SLPJodaviess · District 2 | 5 of 7 | $496,500 | $398,118Law Excavating, Inc. | +24.7% |
| Jan 15, 2021 | 64P51 | (138BR-1)BDRHenry · District 2 | 4 of 4 | $647,830 | $601,848General Constructors Inc. o… | +7.6% |
| Jan 15, 2021 | 64P52 | (40VBR)BDRHenry · District 2 | 1 of 4 | $853,036 | $853,036 | Won |
| Jan 15, 2021 | 66L00 | (50-6HB-1)I-3Lasalle · District 3 | 2 of 3 | $1,277,301 | $1,200,540D. Construction, Inc. | +6.4% |
| Jan 15, 2021 | 85675 | 12-00008-00-SWOgle · District 2 | 5 of 9 | $233,191 | $191,488Alliance Contractors, Inc. | +21.8% |
| Jan 15, 2021 | 85703 | 19-00630-00-BRWinnebago · District 2 | 1 of 5 | $1,393,880 | $1,393,880 | Won |
| Nov 6, 2020 | 64F78 | (81-1B)D & (81-1-1, 81-1-2)RS-1Rock Island · District 2 | 2 of 2 | $49,816,058 | $49,728,568Kraemer North America, LLC | +0.2% |
| Nov 6, 2020 | 64P04 | (141-2B-VB)BDROgle · District 2 | 3 of 7 | $1,968,137 | $1,754,249Martam Construction Incorpo… | +12.2% |
| Nov 6, 2020 | 64P50 | (37-3HB)BDRHenry · District 2 | 2 of 4 | $676,828 | $627,394General Constructors Inc. o… | +7.9% |
| Nov 6, 2020 | 85689 | 14-12124-00-BRCarroll · District 2 | 1 of 5 | $861,269 | $861,269 | Won |
| Nov 6, 2020 | 85701 | 07-12130-00-BRStephenson · District 2 | 2 of 3 | $587,939 | $526,257Martin & Company Excavating | +11.7% |
| Nov 6, 2020 | 85702 | 19-00018-00-SWOgle · District 2 | 1 of 4 | $92,146 | $92,146 | Won |
| Sep 18, 2020 | 64A08 | 4HBRWinnebago · District 2 | 2 of 6 | $4,256,249 | $4,252,385Sjostrom & Sons, Inc. | +0.1% |
| Jul 31, 2020 | DI030 | DIXON MUNICIPALLee · District 2 | 2 of 2 | $752,775 | $732,013Martin & Company Excavating | +2.8% |
| Jul 31, 2020 | WH015 | WHITESIDE COUNTYWhiteside · District 2 | 1 of 3 | $971,112 | $971,112 | Won |
| Jun 12, 2020 | 64L74 | (111BR-1)BDRWhiteside · District 2 | 1 of 4 | $1,192,662 | $1,192,662 | Won |
| Jun 12, 2020 | 64P31 | D2 RS 2020-5Whiteside · District 2 | 2 of 4 | $1,536,775 | $1,367,500Valley Construction Co. | +12.4% |
| Jun 12, 2020 | 64P35 | D2 BJR 2020-2Ogle · District 2 | 5 of 5 | $456,314 | $266,643ERA-Valdivia Contractors, I… | +71.1% |
| Jun 12, 2020 | 64P36 | D2 BJR 2020-3Rock Island · District 2 | 3 of 4 | $278,568 | $233,263ERA-Valdivia Contractors, I… | +19.4% |
| Jun 12, 2020 | 64P37 | D2 BJR 2020-4Whiteside · District 2 | 1 of 4 | $267,213 | $267,213 | Won |
| Jun 12, 2020 | 64P38 | D2 BDR 2020-1Boone · District 2 | 3 of 4 | $667,584 | $564,889Sjostrom & Sons, Inc. | +18.2% |
| Jun 12, 2020 | 64P39 | D2 BRR 2020-2Whiteside · District 2 | 3 of 4 | $135,513 | $105,517Brandt Construction Co. | +28.4% |
| Jun 12, 2020 | 68F53 | (21-HB)BRRKnox · District 4 | 3 of 3 | $91,813 | $49,336Halverson Construction Co.,… | +86.1% |
| Jun 12, 2020 | 87723 | 14-09110-01-BRDekalb · District 3 | 1 of 5 | $1,463,053 | $1,463,053 | Won |
| Apr 24, 2020 | 64M42 | (15,16)RS-3Whiteside · District 2 | 1 of 2 | $2,995,862 | $2,995,862 | Won |
| Apr 24, 2020 | 64M45 | 101RS-6Lee · District 2 | 1 of 2 | $2,479,194 | $2,479,194 | Won |
| Apr 24, 2020 | 64N58 | (177-3,4)RSStephenson · District 2 | 1 of 1 | $1,178,254 | $1,178,254 | Won |
| Apr 24, 2020 | 64N59 | 177-(3,4,4-1)-1RSStephenson · District 2 | 1 of 1 | $1,375,356 | $1,375,356 | Won |
| Apr 24, 2020 | 64P10 | (17R-1BR)BDRWinnebago · District 2 | 1 of 4 | $251,143 | $251,143 | Won |
| Apr 24, 2020 | 85645 | 03-00083-00-BRCarroll · District 2 | 2 of 4 | $6,336,951 | $6,066,569Martin & Company Excavating | +4.5% |
| Apr 24, 2020 | 85685 | 18-00179-00-RSLee · District 2 | 2 of 2 | $1,021,724 | $996,062Martin & Company Excavating | +2.6% |
| Apr 24, 2020 | 85693 | 19-00180-00-RSLee · District 2 | 2 of 2 | $576,515 | $571,769Martin & Company Excavating | +0.8% |
| Apr 24, 2020 | 85694 | 08-03119-00-BROgle · District 2 | 3 of 4 | $327,062 | $246,611Curnyn Construction Co. | +32.6% |
| Apr 24, 2020 | 87730 | 18-P4006-01-BTDekalb · District 3 | 1 of 4 | $2,107,561 | $2,107,561 | Won |
Subcontracts on active jobs 0
No subcontracts on TxDOT's active contract list.