D2 PP 2022-2
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Civil Constructors, Inc. d/b/a/ Helm Civil Low bidder | $595,141 | ||
| 2 | G. M. Sipes Construction, Inc. | $647,845 | +8.9% | |
| 3 | Kinney Contractors, Inc. | $699,855 | +17.6% | |
| 4 | Stenstrom Excavation & Blacktop, Inc. | $752,619 | +26.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Civil Construct… | #2 G. M. Sipes Con… | #3 Kinney Contract… | #4 Stenstrom Excav… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 40601005 | HMA REPL OVER PATCH | 328 | TON | $125.00 | $169.30 | $160.00 | $233.00 | |
| 2 | 44002210 | HMA RM OV PATCH 2 1/2 | 2,335 | SQ YD | $0.0100 | $16.88 | $7.00 | $5.75 | |
| 3 | 44200529 | CL A PATCH T2 8 | 1,040 | SQ YD | $183.00 | $160.00 | $190.00 | $205.00 | |
| 4 | 44200533 | CL A PATCH T3 8 | 500 | SQ YD | $155.00 | $150.00 | $188.00 | $204.00 | |
| 5 | 44200535 | CL A PATCH T4 8 | 600 | SQ YD | $143.00 | $145.00 | $186.00 | $203.00 | |
| 6 | 44213000 | PATCH REINFORCEMENT | 2,140 | SQ YD | $45.00 | $85.00 | $65.00 | $39.00 | |
| 7 | 44213200 | SAW CUTS | 12,410 | FOOT | $2.95 | $0.0100 | $1.00 | $5.56 | |
| 8 | 44213204 | TIE BARS 3/4 | 495 | EACH | $14.00 | $5.00 | $16.00 | $6.76 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $35,708.47 | $32,000.00 | $32,000.00 | $9,330.00 | |
| 10 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $7,750.00 | $4,000.00 | $34,000.00 | $51,144.95 | |
| 11 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $100.00 | $0.0100 | $100.00 | $115.00 | |
| 12 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $100.00 | $4,000.00 | $100.00 | $115.00 | |
| 13 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1,000.00 | $0.0100 | $2,000.00 | $1,158.00 | |
| 14 | 70103815 | TR CONT SURVEILLANCE | 20 | CAL DA | $800.00 | $0.0100 | $10.00 | $405.00 |