| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martin & Company Excavating Low bidder | $648,371 | ||
| 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $693,462 | +7.0% | |
| 3 | Phoenix Corporation of the Quad Cities | $885,649 | +36.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martin & Compan… | #2 Civil Construct… | #3 Phoenix Corpora… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2010400 | STUMP REMOVAL ONLY | 36 | UNIT | $50.00 | $70.00 | $47.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,000.00 | $4,575.00 | $15,040.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $7,000.00 | $5,360.00 | $6,500.00 | |
| 4 | Z0054400 | ROCK FILL | 77 | CU YD | $40.00 | $64.00 | $55.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 3,130 | CU YD | $26.10 | $28.00 | $22.00 | |
| 6 | 20800150 | TRENCH BACKFILL | 186 | CU YD | $46.00 | $26.00 | $40.00 | |
| 7 | 21101615 | TOPSOIL F & P 4 | 9,321 | SQ YD | $1.88 | $6.20 | $15.00 | |
| 8 | 21301052 | EXPLOR TRENCH 52 | 400 | FOOT | $20.00 | $7.50 | $10.00 | |
| 9 | 25000210 | SEEDING CL 2A | 1.3 | ACRE | $1,650.00 | $1,330.00 | $1,500.00 | |
| 10 | 25000310 | SEEDING CL 4 | 1.8 | ACRE | $1,650.00 | $1,330.00 | $1,500.00 | |
| 11 | 25000750 | MOWING | 1.3 | ACRE | $500.00 | $1,000.00 | $600.00 | |
| 12 | 25100125 | MULCH METHOD 3 | 2.6 | ACRE | $2,500.00 | $2,000.00 | $2,200.00 | |
| 13 | 25100630 | EROSION CONTR BLANKET | 1,892 | SQ YD | $2.40 | $2.00 | $2.15 | |
| 14 | 25100900 | TURF REINF MAT | 555 | SQ YD | $8.00 | $6.00 | $7.00 | |
| 15 | 28000200 | EARTH EXC - EROS CONT | 50 | CU YD | $60.00 | $50.00 | $42.00 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 310 | POUND | $1.00 | $2.00 | $3.00 | |
| 17 | 28000305 | TEMP DITCH CHECKS | 800 | FOOT | $28.00 | $15.00 | $8.00 | |
| 18 | 28000400 | PERIMETER EROS BAR | 650 | FOOT | $5.00 | $4.00 | $5.00 | |
| 19 | 28001000 | AGGREGATE - EROS CONT | 30 | TON | $65.00 | $70.00 | $79.00 | |
| 20 | 28100209 | STONE RIPRAP CL A5 | 119 | TON | $49.00 | $51.61 | $100.00 | |
| 21 | 28200200 | FILTER FABRIC | 119 | SQ YD | $3.00 | $4.00 | $3.00 | |
| 22 | 35102000 | AGG BASE CSE B 8 | 220 | SQ YD | $8.44 | $11.00 | $25.00 | |
| 23 | 40600290 | BIT MATLS TACK CT | 632 | POUND | $1.00 | $2.00 | $2.00 | |
| 24 | 40604050 | HMA SC IL-9.5 C N50 | 118 | TON | $166.00 | $155.00 | $155.00 | |
| 25 | 44201383 | CL C PATCH T4 12 | 178 | SQ YD | $135.00 | $110.00 | $190.00 | |
| 26 | 48100700 | AGGREGATE SHLDS A 8 | 840 | SQ YD | $24.00 | $16.50 | $24.00 | |
| 27 | 48102100 | AGG WEDGE SHLD TYPE B | 43 | TON | $30.00 | $34.00 | $107.00 | |
| 28 | 48203023 | HMA SHOULDERS 6 1/2 | 1,227 | SQ YD | $36.00 | $50.00 | $50.00 | |
| 29 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $18,000.00 | $3,600.00 | $14,719.70 | |
| 30 | 50105220 | PIPE CULVERT REMOV | 20 | FOOT | $5.00 | $14.00 | $18.00 | |
| 31 | 50200450 | REM/DISP UNS MATL-STR | 77 | CU YD | $46.00 | $40.00 | $33.00 | |
| 32 | 51500100 | NAME PLATES | 1 | EACH | $700.00 | $750.00 | $800.00 | |
| 33 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $22,000.00 | $21,500.00 | $30,800.00 | |
| 34 | 54011104 | PCBC 11X4 | 89 | FOOT | $1,509.00 | $1,774.00 | $1,890.00 | |
| 35 | 54260315 | TRVRS PIPE GRT CON ES | 129 | FOOT | $125.00 | $93.00 | $145.00 | |
| 36 | 61133100 | FLD TILE JUN VAULT 2D | 2 | EACH | $800.00 | $1,900.00 | $1,700.00 | |
| 37 | 61133200 | FLD TILE JUN VAULT 3D | 2 | EACH | $1,200.00 | $2,200.00 | $2,200.00 | |
| 38 | 61139900 | STORM SEWER SPEC 6 | 210 | FOOT | $40.00 | $26.50 | $30.00 | |
| 39 | 61140200 | STORM SEWER SPEC 12 | 210 | FOOT | $45.00 | $31.25 | $40.00 | |
| 40 | 63200310 | GUARDRAIL REMOV | 250 | FOOT | $6.00 | $9.00 | $6.00 | |
| 41 | 63500105 | DELINEATORS | 2 | EACH | $55.00 | $100.00 | $40.00 | |
| 42 | 64200108 | SHOULDER RUM STRIP 8 | 4,900 | FOOT | $2.00 | $1.85 | $2.25 | |
| 43 | 66600105 | FUR ERECT ROW MARKERS | 27 | EACH | $80.00 | $180.00 | $265.00 | |
| 44 | 66700305 | PERM SURV MKRS T2 | 1 | EACH | $1,800.00 | $1,496.37 | $1,550.00 | |
| 45 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,500.00 | $2,400.00 | $1,600.00 | |
| 46 | 67100100 | MOBILIZATION | 1 | L SUM | $35,000.00 | $41,607.69 | $101,000.00 | |
| 47 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1,100.00 | $1,000.00 | $1,000.00 | |
| 48 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $1,600.00 | $1,500.00 | $1,000.00 | |
| 49 | 70103815 | TR CONT SURVEILLANCE | 15 | CAL DA | $499.00 | $750.00 | $1.00 | |
| 50 | 70107025 | CHANGEABLE MESSAGE SN | 42 | CAL DA | $90.00 | $70.00 | $52.00 | |
| 51 | 70300100 | SHORT TERM PAVT MKING | 16 | FOOT | $1.00 | $1.20 | $6.00 | |
| 52 | 70300150 | SHRT TRM PAVT MK REM | 3 | SQ FT | $55.00 | $6.25 | $10.00 | |
| 53 | 72000100 | SIGN PANEL T1 | 149 | SQ FT | $35.00 | $30.00 | $30.00 | |
| 54 | 72000200 | SIGN PANEL T2 | 21 | SQ FT | $50.00 | $45.00 | $45.00 | |
| 55 | 72400100 | REMOV SIN PAN ASSY TA | 13 | EACH | $20.00 | $100.00 | $150.00 | |
| 56 | 72400200 | REMOV SIN PAN ASSY TB | 2 | EACH | $20.00 | $140.00 | $200.00 | |
| 57 | 73000100 | WOOD SIN SUPPORT | 338 | FOOT | $20.00 | $18.00 | $18.00 | |
| 58 | 78001110 | PAINT PVT MK LINE 4 | 18,490 | FOOT | $0.3000 | $0.4800 | $0.2500 | |
| 59 | 78100100 | RAISED REFL PAVT MKR | 22 | EACH | $120.00 | $315.00 | $115.00 |