19-00113-00-BR
- Let date
- Friday, January 20, 2023
- Contract
- 85732 · job page
- District
- District 2
- County
- Boone
- Highway
- Limits
- Removal of a three-span concrete slab bridge and construction of a two-span PPC I-Beam bridge with integral abutments and approach roadway construction on Poplar Grove Road over Beaver Creek in Boone County.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Civil Constructors, Inc. d/b/a/ Helm Civil Low bidder | $1,640,467 | ||
| 2 | Dunnet Bay Construction Company | $1,672,103 | +1.9% | |
| 3 | Sjostrom & Sons, Inc. | $1,677,540 | +2.3% | |
| 4 | Alliance Contractors, Inc. | $2,329,056 | +42.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Civil Construct… | #2 Dunnet Bay Cons… | #3 Sjostrom & Sons… | #4 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | XX004565 | GROUTED RIPRAP | 839 | SQ YD | $109.40 | $115.00 | $91.00 | $225.00 | |
| 2 | XX009562 | ERE PP CON BEAM IL27N | 1 | L SUM | $50,900.00 | $66,700.00 | $34,259.20 | $197,645.00 | |
| 3 | XX009563 | REINF BARS EPOXY SPL | 130,180 | POUND | $1.88 | $1.80 | $1.64 | $1.78 | |
| 4 | X2020410 | EARTH EXCAVATION SPL | 885 | CU YD | $47.00 | $60.00 | $64.07 | $10.00 | |
| 5 | X2501000 | SEEDING CL 2 SPL | 0.7 | ACRE | $2,150.00 | $2,660.00 | $2,660.00 | $4,900.00 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $12,000.00 | $12,000.00 | $12,000.00 | $12,000.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $9,960.00 | $5,000.00 | $5,500.00 | $12,070.00 | |
| 8 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 10 | 20201200 | REM & DISP UNS MATL | 60 | CU YD | $35.00 | $75.00 | $162.76 | $15.00 | |
| 11 | 20300100 | CHANNEL EXCAVATION | 1,611 | CU YD | $25.00 | $40.50 | $25.33 | $0.0100 | |
| 12 | 20400800 | FURNISHED EXCAVATION | 547 | CU YD | $37.00 | $28.00 | $51.85 | $5.00 | |
| 13 | 25100630 | EROSION CONTR BLANKET | 3,339 | SQ YD | $1.59 | $1.10 | $1.10 | $1.10 | |
| 14 | 28000250 | TEMP EROS CONTR SEED | 70 | POUND | $3.00 | $5.00 | $5.00 | $1.00 | |
| 15 | 28000305 | TEMP DITCH CHECKS | 90 | FOOT | $6.75 | $12.00 | $12.00 | $20.00 | |
| 16 | 28000400 | PERIMETER EROS BAR | 990 | FOOT | $3.05 | $3.00 | $3.00 | $3.25 | |
| 17 | 28200200 | FILTER FABRIC | 839 | SQ YD | $3.00 | $4.60 | $5.16 | $1.00 | |
| 18 | 30300001 | AGG SUBGRADE IMPROVE | 80 | CU YD | $58.00 | $50.00 | $98.53 | $50.00 | |
| 19 | 35102400 | AGG BASE CSE B 12 | 2,423 | SQ YD | $19.50 | $15.00 | $18.63 | $25.00 | |
| 20 | 40600275 | BIT MATLS PR CT | 5,755 | POUND | $0.5000 | $0.5000 | $0.5600 | $0.5000 | |
| 21 | 40600290 | BIT MATLS TACK CT | 2,303 | POUND | $0.5000 | $0.5000 | $0.5600 | $0.5000 | |
| 22 | 40603080 | HMA BC IL-19.0 N50 | 1,029 | TON | $84.00 | $84.00 | $89.50 | $84.00 | |
| 23 | 40604050 | HMA SC IL-9.5 C N50 | 294.2 | TON | $97.00 | $97.00 | $97.00 | $97.00 | |
| 24 | 42000070 | PVT CON HMA BR APP SL | 192 | SQ YD | $75.00 | $75.00 | $75.00 | $75.00 | |
| 25 | 48101500 | AGGREGATE SHLDS B 6 | 128 | SQ YD | $35.26 | $35.50 | $10.40 | $45.00 | |
| 26 | 50100100 | REM EXIST STRUCT | 1 | EACH | $65,574.00 | $80,000.00 | $59,500.00 | $195,120.00 | |
| 27 | 50200100 | STRUCTURE EXCAVATION | 250 | CU YD | $29.20 | $0.0100 | $35.60 | $45.00 | |
| 28 | 50200300 | COFFERDAM EXCAVATION | 72 | CU YD | $65.10 | $150.00 | $73.20 | $0.0100 | |
| 29 | 50201101 | COFFERDAM TYP 1 LOC 1 | 1 | EACH | $53,400.00 | $80,000.00 | $23,012.38 | $0.0100 | |
| 30 | 50300100 | FLOOR DRAINS | 16 | EACH | $712.00 | $630.00 | $740.78 | $1,675.00 | |
| 31 | 50300225 | CONC STRUCT | 149.7 | CU YD | $856.00 | $950.00 | $978.63 | $1,550.00 | |
| 32 | 50300255 | CONC SUP-STR | 218.9 | CU YD | $1,140.00 | $900.00 | $1,608.82 | $1,800.00 | |
| 33 | 50300260 | BR DECK GROOVING | 638 | SQ YD | $9.89 | $9.50 | $13.72 | $11.25 | |
| 34 | 50300300 | PROTECTIVE COAT | 873 | SQ YD | $2.24 | $2.45 | $2.39 | $1.95 | |
| 35 | 50301350 | CONC SUPSTR APP SLAB | 108.9 | CU YD | $480.00 | $470.00 | $548.18 | $625.00 | |
| 36 | 50901750 | PARAPET RAILING | 308 | FOOT | $122.92 | $122.92 | $122.92 | $133.40 | |
| 37 | 51200959 | FUR M S PILE 14X0.312 | 970 | FOOT | $102.00 | $86.00 | $84.08 | $265.00 | |
| 38 | 51202305 | DRIVING PILES | 970 | FOOT | $0.1000 | $0.0100 | $0.0100 | $1.00 | |
| 39 | 51203200 | TEST PILE MET SHELLS | 3 | EACH | $8,320.00 | $13,000.00 | $4,988.06 | $2,500.00 | |
| 40 | 51500100 | NAME PLATES | 1 | EACH | $773.00 | $550.00 | $671.75 | $750.00 | |
| 41 | 58600101 | GRANULAR BACKFILL STR | 146 | CU YD | $78.90 | $110.00 | $50.39 | $45.00 | |
| 42 | 59100100 | GEOCOMPOSITE WALL DR | 66 | SQ YD | $31.20 | $23.00 | $59.94 | $35.00 | |
| 43 | 60146304 | P UNDR FOR STRUCT 4 | 189 | FOOT | $38.20 | $38.00 | $29.84 | $25.00 | |
| 44 | 63000001 | SPBGR TY A 6FT POSTS | 450 | FOOT | $31.70 | $31.70 | $31.70 | $31.70 | |
| 45 | 63100070 | TRAF BAR TERM T5 | 2 | EACH | $1,088.00 | $1,088.00 | $1,088.00 | $1,088.00 | |
| 46 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $4,111.00 | $4,352.79 | $4,111.00 | $4,111.00 | |
| 47 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,233.00 | $3,233.00 | $3,233.00 | $3,233.00 | |
| 48 | 63200310 | GUARDRAIL REMOV | 308.4 | FOOT | $7.20 | $7.20 | $7.20 | $7.20 | |
| 49 | 67100100 | MOBILIZATION | 1 | L SUM | $98,428.00 | $100,326.15 | $100,652.35 | $139,000.00 | |
| 50 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $35.00 | $35.00 | $100.00 | $35.00 | |
| 51 | 78008210 | POLYUREA PM T1 LN 4 | 1,690 | FOOT | $2.25 | $2.25 | $2.25 | $2.25 | |
| 52 | 78011025 | GRV RCSD PVT MRKG 5 | 1,690 | FOOT | $0.9700 | $0.9700 | $0.9700 | $0.9700 | |
| 53 | 78200006 | GRDRAIL REF TYPE B | 10 | EACH | $10.00 | $10.00 | $10.00 | $10.00 | |
| 54 | 78200011 | BARR WALL REF TYPE C | 6 | EACH | $28.00 | $25.00 | $28.00 | $25.00 |