07-12125-00-BR
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Curnyn Construction Co. Low bidder | $499,288 | ||
| 2 | D. Construction, Inc. | $569,786 | +14.1% | |
| 3 | Sjostrom & Sons, Inc. | $585,279 | +17.2% | |
| 4 | Civil Constructors, Inc. d/b/a/ Helm Civil | $620,184 | +24.2% | |
| 5 | Gensini Excavating, Inc. | $819,159 | +64.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Curnyn Construc… | #2 D. Construction… | #3 Sjostrom & Sons… | #4 Civil Construct… | #5 Gensini Excavat… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X2020410 | EARTH EXCAVATION SPL | 232 | CU YD | $22.00 | $50.00 | $60.00 | $95.00 | $46.32 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.5 | ACRE | $4,800.00 | $8,800.00 | $8,000.00 | $6,978.00 | $10,000.00 | |
| 3 | X2810212 | STONE RIPRAP CL A6 SP | 1,061 | TON | $80.00 | $65.00 | $68.00 | $75.00 | $112.02 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $2,500.00 | $20,000.00 | $8,000.00 | $4,500.00 | $5,000.00 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,200.00 | $11,000.00 | $6,000.00 | $17,500.00 | $5,000.00 | |
| 6 | 20300100 | CHANNEL EXCAVATION | 423 | CU YD | $12.00 | $35.00 | $35.00 | $30.00 | $35.00 | |
| 7 | 25100630 | EROSION CONTR BLANKET | 1,453 | SQ YD | $3.00 | $3.30 | $3.00 | $2.00 | $3.00 | |
| 8 | 28000400 | PERIMETER EROS BAR | 770 | FOOT | $3.00 | $5.50 | $5.00 | $4.74 | $5.00 | |
| 9 | 35101400 | AGG BASE CSE B | 365 | TON | $29.00 | $27.00 | $27.00 | $35.00 | $30.00 | |
| 10 | 40200100 | AGG SURF CSE A | 164 | TON | $29.00 | $30.00 | $30.00 | $35.00 | $30.00 | |
| 11 | 40200800 | AGG SURF COURSE TY B | 30 | TON | $29.00 | $30.00 | $30.00 | $35.00 | $30.00 | |
| 12 | 50100100 | REM EXIST STRUCT | 1 | EACH | $18,000.00 | $30,000.00 | $25,000.00 | $40,000.00 | $52,800.00 | |
| 13 | 50105220 | PIPE CULVERT REMOV | 40 | FOOT | $5.00 | $20.00 | $15.00 | $20.00 | $45.00 | |
| 14 | 50200100 | STRUCTURE EXCAVATION | 136 | CU YD | $22.00 | $38.00 | $35.00 | $35.00 | $55.00 | |
| 15 | 50300225 | CONC STRUCT | 34.2 | CU YD | $900.00 | $1,200.00 | $1,200.00 | $1,300.00 | $3,983.00 | |
| 16 | 50300280 | CONCRETE ENCASEMENT | 5.5 | CU YD | $1,400.00 | $600.00 | $2,400.00 | $700.00 | $1,000.00 | |
| 17 | 50400605 | P P CONC DK BM 33 DP | 1,708 | SQ FT | $114.00 | $114.00 | $125.00 | $135.00 | $148.03 | |
| 18 | 50800205 | REINF BARS, EPOXY CTD | 3,340 | POUND | $3.00 | $3.00 | $3.50 | $3.00 | $4.00 | |
| 19 | 50901050 | STEEL RAILING TY SM | 145 | FOOT | $235.00 | $234.95 | $220.00 | $225.00 | $240.00 | |
| 20 | 51200958 | FUR M S PILE 14X0.250 | 384 | FOOT | $92.00 | $94.00 | $82.00 | $70.00 | $205.75 | |
| 21 | 51202305 | DRIVING PILES | 384 | FOOT | $1.00 | $0.0100 | $1.00 | $0.1000 | $0.0100 | |
| 22 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $10,000.00 | $6,000.00 | $10,000.00 | $6,000.00 | $12,500.00 | |
| 23 | 51500100 | NAME PLATES | 1 | EACH | $490.00 | $1,000.00 | $850.00 | $600.00 | $1,000.00 | |
| 24 | 542D0223 | P CUL CL D 1 18 | 42 | FOOT | $52.00 | $95.00 | $80.00 | $95.00 | $100.00 | |
| 25 | 58600101 | GRANULAR BACKFILL STR | 97 | CU YD | $55.00 | $70.00 | $65.00 | $55.00 | $50.00 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $34,200.00 | $37,565.00 | $37,211.00 | $15,000.00 | |
| 27 | 72500300 | OBJECT MARKER T3 | 4 | EACH | $130.00 | $119.00 | $100.00 | $100.00 | $110.00 | |
| 28 | 72900100 | METAL POST TY A | 24 | FOOT | $22.00 | $27.00 | $20.00 | $30.00 | $20.00 |